Is Sizewell The Ideal Site For A Fleet Of Small Modular Nuclear Reactors?

As someone who spent forty years in project management, the Small Modular Nuclear Reactor or SMR could be a project manager’s dream.

Suppose you were putting a fleet of SMRs alongside Sizewell B.

This Google Map shows the current Sizewell site.

Sizewell A power station, with Sizewell B to its North, is on the coast.

This second Google Map shows the power stations to an enlarged scale.

Note the white dome in the middle of Sizewell B.

Sizewell A

Sizewell A power station was shut down at the end of 2006 and is still being decommissioned, according to this extract from Wikipedia.

The power station was shut down on 31 December 2006. The Nuclear Decommissioning Authority (NDA) is responsible for placing contracts for the decommissioning of Sizewell A, at a budgeted cost of £1.2 billion. Defuelling and removal of most buildings is expected to take until 2034, followed by a care and maintenance phase from 2034 to 2092. Demolition of reactor buildings and final site clearance is planned for 2088 to 2098.

Only a few of those, reading this post, will be around to see the final end of Sizewell A.

Note that the size of the Sizewell A site is 245 acres.

It appears to me, that if any power station will be able to be built on the cleared site of Sizewell A, until the late 2080s or 2090s.

Sizewell B

Sizewell B power station opened in 1995 and was originally planned to close in 2035. The owner; EDF Energy, has applied for a twenty-year extension to 2055.

Sizewell C

Sizewell C power station is currently under discussion.

  • It will be built by the French, with the help of Chinese money.
  • It will have an output of 3260 MW or 3.26 GW.
  • It will cost £18 billion.
  • It will take twelve years to build.

This Google Map shows Sizewell B and the are to the North.

I would assume it will be built in this area.

 

A Fleet Of Small Modular Nuclear Reactors

These are my thoughts on building a fleet of SMRs at Sizewell instead of the proposed Sizewell C.

Land Use

In Rolls-Royce signs MoU With Exelon For Compact Nuclear Power Stations, I gave these details of the Rolls-Royce design of SMR.

  • A Rolls-Royce SMR has an output of 440 MW.
  • The target cost is £1.8 billion for the fifth unit built
  • Each SMR will occupy 10 acres.
  • Eight SMRs would need to be built to match the output of Hinckley Point C, which will occupy 430 acres.

It looks on a simple calculation, that even if the SMRs needed fifteen acres, the amount of land needed would be a lot less.

Connection To The National Grid

The transmission line to the National Grid is already in place.

This Google Map shows the sub-station, which is to the South-West of Sizewell A.

From Sizewell, there is a massive twin overhead line to Ipswich.

This Google Map shows the overhead line as it crosses Junction 53 of the A14 to the West of Ipswich.

The pylons are in the centre of the map, with the wires going across.

The line has been built for a massive amount of nuclear power at Sizewell.

The Sizewell Railhead

This Google Map shows the railhead at Sizewell.

It can also be picked out in the South West corner of the first map.

  • The railhead is used to take out spent fuel for processing.
  • In the past, it brought in construction materials.
  • Wikipedia suggests if the Sizewell C is built, the might be a new railhead closer to the site.
  • If a fleet of SMRs were to be built, as the modules are transportable by truck, surely they could be move in by rail to avoid the roads in the area.
  • I am an advocate of reinstating the railway from Saxmundham to Aldeburgh, as this would be a way of doubling the frequency on the Southern section of the East Suffolk Line between Saxmundham and Ipswich stations.

I hope that whatever is built at Sizewell, that the rail lines in the area is developed to ease construction, get workers to the site and improve rail services on the East Suffolk Line.

Building A Fleet Of SMRs

One of the disadvantages of a large nuclear power station, is that you can’t get any power from the system until it is complete.

This of course applies to each of the individual units, but because they are smaller and created from a series of modules built in a factory, construction of each member of the fleet should be much quicker.

  • Rolls-Royce are aiming for a construction time of 500 days, from the fifth unit off the production line.
  • That would mean, that from Day 501, it could be producing power and earning money to pay for its siblings.
  • If the eight units were built in series, that would take eleven years to build a fleet of eight.

But as anybody, who has built anything even as humble as a garden shed knows, you build anything in a series of tasks, starting with the foundations.

I suspect that if a fleet were being built, that construction and assembly would overlap, so the total construction time could be reduced.

That’s one of the reasons, I said that building a fleet could be a project manager’s dream.

I suspect that if the project management was top-class, then a build time for a fleet of eight reactors could be nine years or less.

Resources are often a big problem in large projects.

But in a phased program, with the eight units assembled in turn over a number of years, I think things could be a lot easier.

Financing A Fleet Of SMRs

I think that this could be a big advantage of a fleet of SMRs over a large conventional large nuclear power station.

Consider

  • I said earlier, that as each unit was completed, it could be producing power and earning money to pay for its siblings.
  • Hinckley Point C is budgeted to cost £18 billion.
  • Eight Rolls-Royce SMRs could cost only £14.4 billion.

I very much feel that, as you would get a cash-flow from Day 500 and the fleet costs less, that the fleet of smaller stations is easier to finance.

Safety

SMRs will be built to the same safety standards as all the other UK reactors.

In this section on Wikipedia this is said about the Rolls-Royce SMR.

Rolls-Royce is preparing a close-coupled three-loop PWR design, sometimes called the UK SMR.

PWRs or pressurised water reactors are the most common nuclear reactors in the world and their regulation and safety is well-understood.

This is from the History section of their Wikipedia entry.

Several hundred PWRs are used for marine propulsion in aircraft carriers, nuclear submarines and ice breakers. In the US, they were originally designed at the Oak Ridge National Laboratory for use as a nuclear submarine power plant with a fully operational submarine power plant located at the Idaho National Laboratory. Follow-on work was conducted by Westinghouse Bettis Atomic Power Laboratory.

Rolls-Royce have a long history of building PWRs, and Rolls-Royce PWRs have been installed in all the Royal Navy’s nuclear submarines except the first. The Royal Navy’s second nuclear submarine; HMS Valiant, which entered service in 1966, was the first to be powered by a Rolls-Royce PWR.

How much of the design and experience of the nuclear submarine powerplant is carried over into the design of the Rolls-Royce SMR?

I don’t know much about the safety of nuclear power plants, but I would expect that if there was a very serious accident in a small reactor, it would be less serious than a similar accident in a large one.

Also, as the reactors in a fleet would probably be independent of each other, it is unlikely that a fault in one reactor should affect its siblings.

Local Reaction

I lived in the area, when Sizewell B was built and I also went over Sizewell A, whilst it was working.

From personal experience, I believe that many in Suffolk would welcome a fleet of SMRs.

  • Sizewell B brought a lot of employment to the area.
  • House prices rose!
  • Both Sizewell A and B have been well-run incident-free plants

Like me, some would doubt the wisdom of having a Chinese-funded Sizewell C.

Conclusion

Big nuclear has been out-performed by Rolls-Royce

November 19, 2020 Posted by | Energy, Transport | , , , , , , , , , , | 1 Comment

Sizewell C: Nuclear Power Station Plans For Suffolk Submitted

The title of this post, is the same as that as this article on the BBC.

A few points from the article.

  • It will provide enough electricity for six million homes.
  • It will create 25,000 jobs during construction.
  • Sizewell C will be a near replica to Hinckley Point C.
  • It will generate 3.2 GW of electricity.
  • It will be low-carbon electricity.

As a well-read and experienced engineer, I am not against the technologies of nuclear power.

But I do think, by the time it is completed , other technologies like wind and energy storage will be much better value. They will also be more flexible and easier to expand, should we get our energy forecasts wrong.

  • We will see higher power and more efficient wind farms, further out in the North Sea.
  • Massive energy storage systems, based on improved pumped storage technology and using new technology from companies like Highview Power, Zinc8 and others will be built.
  • Wind and solar power an energy storage are much easier to fund and financial institutions like L & G, Aberdeen Standard and Aviva have invested in the past for our future pensions.
  • If you want to go nuclear, small modular reactors, look to be much better value in the longer term.
  • I also don’t like the involvement of the Chinese in the project. History tells me, that all pandemics seem to start in the country!

It is my view that the biggest mistake we made in this country over energy was not to built the Severn Barrage.

My preferred design would be based on the ideas of Sir Frederick Snow.

There would have been a high and a low lake, either side of a central spine, behind an outer barrage.

  • Reversible turbines and pumps between the lakes would both generate and store electricity.
  • When proposed in the 1970s, it would have generated ten percent of the UK’s electricity.
  • A new road and rail crossing of the Severn, could have been built into the outer barrage.
  • A lock would have provided access for shipping.
  • It would have controlled the periodic, regular and often devastating flooding of the River Severn.

Some versions of the original design, even incorporated an international airport.

  • The runways would be in the right direction for the prevailing wind, with regard to take-off and landing.
  • Take-off would be over open sea.
  • High speed trains could speed travellers to and from London on an updated Great Western Railway.

I believe a modern design could be even better.

  • The central spine and the outer barrage would be the foundations for a large wind farm.
  • There would also be a large number of powerful floating wind turbines to the West of the outer barrage in the Severn Estuary.
  • A giant electrolyser on the central spine would produce hydrogen, that could be used to decarbonise the UK’s gas network.
  • A power interconnector could be built into the outer barrage to connect Wales to the nuclear power stations at Hinckley :Point.
  • A cluster of small nuclear reactors could be built on the central spine.
  • In the intervening fifty years, we have probably learned how to build a barrage like this, so that it can benefit birds and other wildlife.

I believe, it will never be too late to build a Severn Barrage.

 

May 27, 2020 Posted by | Energy Storage, Transport | , , , , , , , , , , | 3 Comments