This article on London Reconnections is entitled Back to the Future: (Re)lengthening and Shortening at Waterloo.

It describes in detail why and how the platforms at Waterloo station are being lengthened and shortened and information on other important topics can be gleaned.

Why Did The Train Hit The Barrier Train?

It doesn’t actually say why, but it does discuss the need for the barrier train to protect the workforce. As the train hit the barrier train, it seemed to have worked.

If you want to know more, I suggest you search for barrier in the comments added to the article by others. If nothing, you’ll realise there’s a lot to go wrong.

Why Weren’t The International Platforms Used Earlier?

The platforms were designed to handle six trains per hour (tph) with a long dwell time in the platform and after modification they will handle 18 tph for the Windsor Lines. So a lot of serious work was needed!

There was also complicated ownership of the five platforms.

Looking at it from a planning point of view, the provision of a terminal for Eurostar in London could have been handled better.

Why Are The International Platforms Only Being Used For A Few Weeks And Then Reopening in 2018?

The platforms are needed for this August’s blockade, but there is still a lot of work to do.

Effectively, the remodelling of the International Platforms have been almost split into two independent projects.

I like the way they’ve done this.

How Will Suburban Capacity Change?

In addition to the five platforms in the old International station, platforms 1-6 will also be remodelled for suburban use.

Currently, the slow lines through Wimbledon can handle 18-19 tph into four platforms.

After completion . these same slow lines will handle 22 tph, but they will have the use of two extra platforms.

In An Analysis Of Waterloo Suburban Services Proposed To Move To Crossrail 2, I showed that if you were running 4 tph on the four branches  to Chessington South, Epsom, Hampton Court and Shepperton, which will transfer to Crossrail 2, then you need.

  • New 100 mph trains.
  • A capacity of 20 tph between Waterloo and Wimbledon.

Both these conditions will be met.

How Will The Passenger Experience At Waterloo Change?

Read the article and there are some snippets in there, that give me hope, that passengers will like it. See what you think!

Conclusion

It is a highly intricate and difficult project, that will be performed in a short time.

 

 