The Anonymous Widower

The New Light Freight Terminal At Liverpool Street Station

These pictures show the old cab road at Liverpool Street station, where the proposed light freight terminal will be developed.

The spacious cab road shut a few years ago and was moved to its current position in front of the station. Nowadays it is used mainly for deliveries to the station and the retail units, by Network Rail maintenance vehicles and sometimes by Rail Replacement Buses.

This second set of pictures show the exit of the cab road in Primrose Street, behind the station.

Note  these points about the old cab road.

  1. There is some nice ironwork and a vaulted ceiling, but nothing that would be damaged if electric vans and cargo bikes used the cab road to serve freight shuttles.
  2. The road surface and the brickwork all appear to be in good condition.
  3. By removing the barrier between the cab road and platform 10, there would be no problem loading and unloading trains.
  4. There is also a good wide passage leading from the old cab road to the main concourse of the station.

I suspect that the only functional building in the area, which is the Left Luggage Office, will have to be moved. But it might be better placed on the main concourse.

Platform 10 Looks Very Convenient For The Freight Shuttle

The closeness of Platform 10 and the old cab road makes the platform look very convenient for the terminus of freight shuttles from London Gateway

How Will The Freight Shuttles Travel Between London Gateway And Liverpool Street Station?

The route from London Gateway to Liverpool Street station will be as follows.

This map from carto.metro.free.fr shows the tracks, where the Gospel Oak to Barking Line crosses over the Great Eastern Main Line.

The train will join the Great Eastern Main Line here for a fast run into Liverpool Street station.

  • I suspect the train will switch to the fast lines using the crossovers shown in the map.
  • Note that the performance of a Class 769 train on electrified track, will be only slightly less than the expresses.

At Liverpool Street station, the train will run into Platform 10.

Will Liverpool Street Station Lose A Platform?

Currently, Platforms 9 and 10 are generally used for the London and Norwich services.

  • These trains run at a frequency of two trains per hour (tph).
  • They are formed of a rake of Mark 3 coaches topped sand tailed by a Class 90 locomotive and a driving van trailer.
  • They call at various stations en route including Chelmsford, Colchester and Ipswich and are very heavily used at peak times.
  • Entry to and exit from the trains is not of a modern standard and I suspect turnround times can sometimes must be very slow.

From next year, these trains will be replaced  by modern twelve-car Class 745 trains.

  • These trains have 757 seats, which I have read somewhere is more than the current trains.
  • The trains will have level access between train and platform at all stations.
  • I suspect turnround times will be shorter, due to the modern design.

Frequency between London and Norwich will also be increased yp three tph, by extending a service between London and Ipswich, which will be run by a Class 720 train.

Will it be possible to fit three tph into Platforms 9 and 10?

I suspect that it might be tight, as over the last few months, Norwich trains have sometimes  been using higher numbered platforms like 14.

So will the proposed three tph to Colchester, Ipswich and Norwich be moved to two higher numbered platforms.

This would enable platform 10 to be used by freight shuttle trains, but will the station be able to run all the services, with one platform less?

Current Services Into Liverpool Street Station

Current services from Liverpool Street station are as follows.

  • Six tph – GEML – TfL Rail – Shenfield
  • Three tph – GEML – Greater Anglia – Southend
  • Two tph – GEML – Greater Anglia – Norwich
  • One tph – GEML – Greater Anglia – Ipswich
  • One tph – GEML – Greater Anglia – Clacton
  • One tph – GEML – Greater Anglia – Colchester Town
  • One tph – GEML – Greater Anglia – Braintree
  • Four tph – WAML- London Overground – Chingford
  • Two tph – WAML- London Overground – Cheshunt
  • Two tph – WAML- London Overground – Enfield Town
  • Four tph – WAML- Greater Anglia – Stansted Airport
  • Two tph – WAML- Greater Anglia – Hertford East
  • Two tph – WAML- Greater Anglia -Cambridge

Totalling these up means the following.

  • 16 tph use the double-track West Anglia Main Line (WAML)
  • 15 tph use the four-track Great Eastern Main Line (GEML) as far as Shenfield.
  • 6 tph use the double-track GEML to the North of Shenfield.

It looks neatly balanced.

Would moving Norwich services to a pair of the higher-numbered platforms improve operation?

All WAML services would be in platforms 1 to 9, as against platforms 1 to 8 now!

All GEML services would be in platforms 10 to 18, as against platforms 9 to 18 now!

If platform 10 is used by the freight shuttles, this would make operational sense, as the shuttle will approach Liverpool Street along the GEML after joining at Manor Park station.

Future Services Into Liverpool Street Station

From 2021 or so, these could be the from Liverpool Street station.

  • Three tph – GEML – Greater Anglia – Southend
  • Three tph – GEML – Greater Anglia – Norwich
  • One tph – GEML – Greater Anglia – Clacton
  • One tph – GEML – Greater Anglia – Colchester Town
  • One tph – GEML – Greater Anglia – Braintree
  • Four tph – WAML- London Overground – Chingford
  • Two tph – WAML- London Overground – Cheshunt
  • Two tph – WAML- London Overground – Enfield Town
  • Four tph – WAML- Greater Anglia – Stansted Airport
  • Two tph – WAML- Greater Anglia – Hertford East
  • Two tph – WAML- Greater Anglia -Cambridge

Totalling these up means the following.

  • 16 tph use the double-track West Anglia Main Line (WAML)
  • 9 tph use the four-track Great Eastern Main Line (GEML) as far as Shenfield.
  • 12 tph from Crossrail will use the slow lines as far as Shenfield.
  • 3 tph use the double-track GEML to the North of Shenfield.

Crossrail has opened up capacity on the Great Eastern Main Line.

  • Currently, there are 15 tph on the GEML using platforms 9 to 15.
  • In 2021, there will be just 9 tph on the GEML using platforms 10 to 17.

There will be extra services to Lowestoft and Crossrail’s Peak Hour service to Gidea Park station.

But even so, I suspect there will be space for more services.

 

 

November 3, 2019 Posted by | Transport/Travel | , , , , , , | 11 Comments

High Speed Urban Freight Logistics By Rail

The title of this article is the same as that of this article  on World Cargo News.

It describes from a freight operator’s point-of-view,  Rail Operation’s Group‘s plans to run freight services between London Gateway and Liverpool Street station, which I wrote about in  A Freight Shuttle For Liverpool Street Station Planned.

Points include.

  • Current operators are struggling to lower their carbon footprint.
  • Congestion is affecting delivery times.
  • Charges to use London’s ULEZ could add two hundred pounds per round trip to costs.
  • To enter London, trucks will need high visibility cabs in a couple of years time.
  • Last mile delivery would be by e-vans and cargo bikes.
  • This initial service is about proving the concept and identifying the best techniques.

The article also discloses that Rail Operations Group are planning to run a high-speed overnight freight service between London Gateway and the Central Belt in Scotland, using their modified Class 769 trains.

  • Journey time will be reduced from eleven-twelve hours by truck to five-and-a-half by rail.
  • The deadline for guaranteed overnight delivery will go from 20:00 to 23:00.
  • Trains will be running at 100 mph on electricity all the way.
  • If it works going North, surely it will work going South.

I can see Rail Operations Group needing a lot more trains, than the two they have ordered.

 

 