Renewable Power By 2030 In The UK
I am doing this to see what the total output will be by the net election.
Offshore Wind Power
I shall start with offshore wind power.
- Operational in July 2025 – 16,035 MW
- 2025 – Dogger Bank A – 1,235 MW
- 2026 – Sofia – 1,400 MW
- 2026 – Dogger Bank B – 1,235 MW
- 2026 – East Anglia 1 North – 800 MW
- 2026 – East Anglia 3 – 1,372 MW
- 2027 – Dogger Bank C – 1,218 MW
- 2027 – Hornsea 3 – 2,852 MW
- 2027 – Inch Cape – 1,080 MW
- 2027 – Llŷr 1 – 100 MW
- 2027 – Llŷr 2 – 100 MW
- 2027 – Norfolk Boreas – 1,380 M
- 2027 – Whitecross – 100 MW
- 2028 – Aspen – 1008 MW
- 2028 – Morecambe – 480 MW
- 2028 – Ossian – 2,610 MW
- 2028 – Stromar – 900 MW
- 2029 – Beech – 1008 MW
- 2029 – East Anglia 2 – 967 MW
- 2029 – Green Volt – 400 MW
- 2029 – Mona – 1,500 MW
- 2029 – Morgan – 1,500 MW
- 2029 – Norfolk Vanguard East – 1,380 MW
- 2029 – Norfolk Vanguard West – 1,380 MW
- 2029 – North Falls – 504 MW
- 2029 – West of Orkney – 2,000 MW
- 2030 – Awel y Môr – 500 MW
- 2030 – Bellrock – 1,200 MW
- 2030 – Berwick Bank – 4,100 MW
- 2030 – Caledonia – 2,000 MW
- 2030 – Cedar – 1008 MW
- 2030 – Five Estuaries – 353 MW
- 2030 – Morven – 2,907 MW
- 2030 – N3 Project – 495 MW
- 2030 – Outer Dowsing – 1,500 MW
- 2030 – Rampion 2 Extension – 1,200 MW
This gives these yearly totals, if I use pessimistic dates.
- 2025 – 1,235 MW
- 2026 – 4,807 MW
- 2027 – 5,350 MW
- 2028 – 4,998 MW
- 2029 – 9,631 MW
- 2030 – 15,263 MW
This adds up to a total of 58,897 MW.
Solar Power
For solar power, I just asked Google AI and received this answer.
The UK government aims to have between 45 and 47 gigawatts (GW) of solar power capacity by 2030. This goal is set out in the Solar Roadmap and aims to reduce energy bills and support the UK’s clean power objectives. The roadmap includes measures like installing solar on new homes and buildings, exploring solar carports, and improving access to rooftop solar for renters.
Let’s assume that we only achieve the lowest value of 45 GW.
But that will still give us at least 100 GW of renewable zero-carbon power.
Energy Storage
For pumped storage hydro, I asked Google AI and received this answer.
The UK’s pumped storage hydro (PSH) capacity is projected to more than double by 2030, with six projects in Scotland, including Coire Glas and Cruachan 2, potentially increasing capacity to around 7.7 GW from the current approximately 3 GW. This would be a significant step towards meeting the National Grid’s required 13 GW of new energy storage by 2030, though achieving this depends on policy support and investment.
It looks like there is about another 5 GW of capacity to find.
[…] in Renewable Power By 2030 In The UK, I calculated that by 2030 we will add these yearly additions of offshore wind […]
Pingback by How Will The UK Power All These Proposed Data Centres? « The Anonymous Widower | September 23, 2025 |
[…] Renewable Power By 2030 In The UK, I stated that by 2030, the UK would add nearly 59 GW of offshore […]
Pingback by America’s Looming Electricity Crisis Is Trump’s Achilles’ Heel « The Anonymous Widower | October 3, 2025 |
[…] Renewable Power By 2030 In The UK, I calculated these pessimistic offshore wind power totals for […]
Pingback by Wind Farms Generate Record Power On Cold November Evening « The Anonymous Widower | November 20, 2025 |
[…] Renewable Power By 2030 In The UK, I calculated how much offshore wind could be commissioned up to […]
Pingback by UK Continues Offshore Wind Expansion With 6 GW Leasing Round Planned For Early 2027 « The Anonymous Widower | March 27, 2026 |
The Notice to Mariners is a good source of progress
2026
Sofia has 2/3rd turbines installed. Nothing commissioned
Dogger Bank B 5 turbines installed
EA 3 about to commence turbine installation
EA1 Nth doesn’t appear to have made much progress and looks to be coordinated with EA2 now so not commissioned to back end of decade.
2027
Dogger Bank C all foundations installed
Hornsea 3 no foundations installed yet but did see a piece that some have arrived at the loading port recently
Inchape foundation commenced installation
Some are behind schedule but they are all in build is the good thing but all will run up against transmission constraints when we have good wind across the whole UK.until at least 2029.
Comment by Nicholas Ronald Lewis | March 28, 2026 |