The Anonymous Widower

Able Seaton Port

Able Seaton Port has been in the news several time recently. So I looked it up on Google Maps.

These four paragraphs on the Able Seaton Port website outline the capabilities of the port.

ABLE Seaton Port (ASP) is located in the centre of the UK on the North East Coast close to the mouth of the River Tees and covers 51 hectares (126 acres) including a 10 hectare (25 acre) dry dock (currently wet) – one of the world’s largest.

It is capable of handling all types of offshore construction vessels, has significant crane capacity and quays, which have been constructed particularly to suit the requirements of the heavy fabrication industry.

Quays 10 & 11 are some of the strongest in Europe at 306m long. They are dredged to -15m chart datum and are designed with a quay loading capacity of 40T/m² with a heavy load-out pad area capable of 60T/m².

Quay 6 is a new heavy-lift quay at the northern end of the wet dock. At 60T/m² this is one of the heaviest load out quays in Europe. It’s function is to service the Brent field decommissioning project which ABLE is undertaking with partners Shell and Allseas.

Note.

The four platforms with their helipads.

Is the platform at the Northern end of the dock concerned with the Brent field decommissioning project?

There seems to be lots of components around the dock ready to be assembled into assemblies like wind turbine foundations.

As Able say this is certainly a large facility.

This second Google Map is a 3D-visualisation of the Southern three platforms.

The view has all changed now according to this news item on the Able Seaton Port, which is entitled First Campaign To Install Turbines At World’s Largest Offshore Wind Farm Is Underway.

A new vessel called Voltaire will be used to install the turbines.

This page on the Dogger Bank Wind Farm web site, is entitled Largest Jack-Up Vessel Voltaire Arrives In The UK To Build Largest Wind Farm In The World.

These are the bullet points.

  • Largest offshore jack-up vessel and first seaworthy ultra-low emission installation vessel Voltaire arrives in the UK for her very first assignment on Dogger Bank Wind Farm.
  • The vessel will install turbines for all three Dogger Bank Wind Farm phases, a total of 277 units of GE Renewable Energy Haliade-X offshore wind turbines.

These three paragraphs describe the assembly of the wind farm.

The largest offshore jack-up installation vessel ever built, Voltaire, has just arrived in the UK port of Able Seaton ahead of its first campaign on Dogger Bank Wind Farm.

Voltaire of Jan De Nul Group was delivered in late 2022. Since then she has been undertaking final preparations for her very first assignment, the construction of the Dogger Bank Wind Farm phases A, B and C.

In total, the vessel will be responsible for installing 277 GE Renewable Energy Haliade-X turbines. Voltaire will sail out in early July to begin installation

As in an earlier life I was writing project management software for North Sea oil and gas, I can obviously say history is repeating itself. In the 1970s offshore work got easier as cranes got bigger  and now fifty years later, it looks like larger lifting capacity, is enabling the installation of larger turbines.