First German Zero-Subsidy Offshore Wind Farm Starts Taking Shape
The title of this post, is the same as that of this article on offshoreWIND.biz.
This is the sub-heading.
Offshore installation work has started at the 913 MW Borkum Riffgrund 3, the first subsidy-free offshore wind farm in Germany to reach this development phase, Ørsted, the developer of the project, said.
These two paragraphs introduce the project.
The first of the 83 monopile foundations have now been installed at the site some 53 kilometres off the island of Borkum in the German North Sea by Jan De Nul’s Lez Alizés.
The installation directly follows the foundation work in the adjacent 253 MW Gode Wind 3 project, which is being built in parallel by Ørsted in the North Sea.
Ørsted’s web site gives this history of Borkum Riffgrund 3.
Borkum Riffgrund 3 is expected to be fully commissioned in 2025. It comprises three offshore wind projects which were originally awarded to Ørsted in auctions in 2017 and 2018 under the names of Borkum Riffgrund West 1, Borkum Riffgrund West 2 and OWP West. The three projects were renamed in September 2019 and will be built as one joint project under the name of Borkum Riffgrund 3.
Borkum Riffgrund 3 was awarded without subsidies to Ørsted. A number of companies across IT, retail and the chemicals industry have signed corporate power purchase agreements for Borkum Riffgrund 3.
If Ørsted is doing this in Germany, how come, we are not seeing more subsidy-free wind farms in Europe?
These two paragraphs from the article give a partial explanation.
After commissioning in 2025, a large part of the electricity generated by the wind farm will be used for the decarbonization of the industry – through the so-called Corporate Power Purchase Agreements (CPPAs). For the project, long-term power purchase agreements were concluded with the companies Covestro, Amazon, the Energie-Handels-Gesellschaft/REWE Group, as well as BASF and Google.
Shares for Borkum Riffgrund 3 were also sold to an institutional investor well before construction. In October 2021, Nuveen signed an agreement with Glennmont Partners to sell 50 percent of the shares in Borkum Riffgrund 3.
The article also states that Borkum Riffgrund 3 will be the largest offshore wind farm in Germany to date.
This Google Map shows the location of the German Borkum island to the North of the Dutch city of Groningen.
Note.
- Groningen is the city in the South-West corner of the map.
- Borkum is the horseshoe-shaped island at the top of the map.
There are a cluster of wind farms to the North of Borkum, which includes Borkum Riffgrund 1, 2 and 3.
Vattenfall Invests In 76-Megawatt Agrivoltaic Project
The title of this post, is the same as that of this media report from Vattenfall.
This is the sub-heading.
Agrivoltaics is the combination of sustainable agriculture and solar power generation on the same agricultural land. Vattenfall has now made a final investment decision for a 76-megawatt solar park Tützpatz in Mecklenburg-Western Pomerania. The project is being set up without state support.
These two paragraphs outline the project.
Photovoltaics is now one of the cheapest technologies among renewable energies, and solar power has a high level of acceptance among the population. However, critics of open space photovoltaics fear that expansion could take place at the expense of agricultural land used for food production. The relatively young technology of agrivoltaics, which can reconcile agricultural use and photovoltaics, can help to resolve this competitive situation.
For the first time, Vattenfall will implement this innovative concept of land use on a commercial scale with partners. The aim of the project in Tützpatz is to combine module types on different mounting systems with suitable agricultural uses over an area of 95 ha, and thus gain further practical experience for future commercial projects of this kind. According to current plans, construction at Tützpatz is scheduled to start in early summer 2023.
Note.
- Tützpatz is a few miles North of Lincoln.
- This project is subsidy-free.
- At Tützpatz, 76 MW is to be installed in 95 hectares, which is an energy density of 0.8 MW per hectare.
- Agrivoltaics have an extensive Wikipedia entry.
I would expect we could use agrivoltaics in quite a few places in Southern England.
First-Ever Subsidy-Free Offshore Wind Farm Halfway Done
The title of this post, is the same as that of this article on offshoreWIND.biz.
These three paragraphs, outline the project.
Cadeler’s wind turbine installation vessel Wind Osprey has installed the 70th Siemens Gamesa 11 MW wind turbine at the 1.5 GW Hollandse Kust Zuid offshore wind farm in the Dutch North Sea.
The installation of the 70th turbine marks the halfway milestone on the 140-turbine project, Cadeler said.
Once fully installed and commissioned in the summer of 2023, Hollandse Kust Zuid will become the largest operating offshore wind farm, as well as the first one built without government subsidies.
I very much believe that in the near future many, if not all wind farms will be built without subsidy.
Q&A: What does ‘Subsidy-Free’ Renewables Actually Mean?
The title of this post, is the same as that of this article on Carbon Brief.
This is the first paragraph.
Recent announcements in the UK and across the rest of Europe seem to be ushering in a new era of “subsidy-free” renewables, which can be deployed without government support.
The article gives a detailed explanation and is a must-read.
BayWa r.e. Unveils Subsidy-Free Floating Wind Project Offshore Portugal
The title of this post, is the same as that of this article on offshoreWIND.biz.
This is the first paragraph.
BayWa r.e. has officially applied to secure the rights for an exclusive use of the seabed for a commercial-scale floating offshore wind project in Portugal, which the company said will be the first subsidy-free floating wind farm in the world.
Note.
- BayWa are a German company headquartered in Munich.
- The windfarm will have a 600 MW capacity in total, in a dedicated zone off the coastline of Viana do Castelo.
- It will be a floating wind farm.
- Viana do Castelo is situated at the mouth of the Lima River and is about 74 km. to the North of Porto.
But surely the most significant fact about this project is that it is subsidy-free.
BayWa And Subsidy-Free Wind Farms
This page on the BayWa web site is entitled BayWa r.e. Sells UK’s First Subsidy-Free Wind Farm.
This is the first paragraph.
BayWa r.e. has reached a milestone for itself and the UK renewable energy sector with the completion and sale of the country’s first subsidy-free windfarm to James Jones & Sons Ltd and London-based specialist asset manager, Gresham House Asset Management.
Note.
- This is the first time, I’ve seen Gresham House associated with wind farms.
- BayWa appear to have a fifteen year agreement with Tesco for the generated electricity.
The whole page is a must read.
Conclusion
Does this mean, that we will be seeing subsidy-free floating wind farms around the UK?
Get the engineering, manufacturing and financial support right for floating wind farms in the UK and wind farms could be bumper-to-bumper around these islands.