Did The Project Management Go Wrong On The Holloway Road Bridge?
It was originally planned that the bridge decking where Holloway Road crosses the Gospel Oak to Barking Line (GOBlin) at Upper Holloway station would be replaced over Christmas this year.
But plans were obviously changed.
This article in the Islington Gazette is entitled Holloway Road closures: Islington Council threatens to sue TfL over ‘last-minute’ plans.
This is said.
TfL says work to transfer underground pipes and cables from the old bridge to another specially-made bridge has proved problematic because of their “complex layout, poor condition and a leaking water main”.
But Cllr Webbe was having none of it. She said: “This section of Holloway Road will be closed in at least one direction for nearly three months, including over half term, Christmas and New Year.
It looks like the water main is the problem and perhaps this didn’t show up until they started to move everything.
But whatever the problem was, it looks to me like there has been a cock-up by someone.
Was it the surveyor, who looked at the moving of the cables and the water main and didn’t quantify the task properly?
Surely though, the big problem now is that if this bridge problem delays the rebuilding of the trac for the GOBlink, which is needed for the electrification.
It’s a mess!
I took these pictures of the area today.
I walked down from Archway station and then caught a free bus to Holloway Road. At least TfL had got the buses right.
But except for Junction Road from Archway to Kentish Town, which was blocked solid, the traffic levels were very low.
October 24, 2016 - Posted by AnonW | Transport/Travel | Bridges, Construction, Driving, Gospel Oak And Barking Line, Upper Holloway Station
1 Comment »
Leave a Reply Cancel reply
This site uses Akismet to reduce spam. Learn how your comment data is processed.
About This Blog
What this blog will eventually be about I do not know.
But it will be about how I’m coping with the loss of my wife and son to cancer in recent years and how I manage with being a coeliac and recovering from a stroke. It will be about travel, sport, engineering, food, art, computers, large projects and London, that are some of the passions that fill my life.
And hopefully, it will get rid of the lonely times, from which I still suffer.
Why Anonymous? That’s how you feel at times.
Charities
Useful Links
Top Posts
- How Much Power Is Needed To Run A Train At 125 Or 100 mph?
- Job Scam - Hyde Park Hotel
- UK And Welsh Governments To Explore New Rail Links Between South Wales And England
- How Much Water Vapour Is In A Cubic Metre Of Air at A Given Temperature And Relative Humidity?
- Elizabeth Line: Commuters Say Service 'Not What Was Promised'
- Platforms 11 and 12 At Stratford
- Beeching Reversal: Fifty Disused Rail Lines On Track To Reopen
- So Many Cases On A Train!
- More Frequent Trains And A New Station For The London Overground
- Extending The Elizabeth Line – Connecting West Anglia Main Line Services To The Central Tunnel
WordPress Admin
-
Join 1,891 other subscribers
Archives
Categories
- Advertising Architecture Art Australia Banks Battery-Electric Trains BBC Buses Cambridge Cancer Coeliac Construction COVID-19 Crossrail Cycling Death Decarbonisation Design Development Docklands Light Railway Driving Electrification Energy Engineering Entertainment Flying Football France Freight Germany Global Warming/Zero-Carbon Good Design Gospel Oak And Barking Line Greater Anglia Great Western Railway Heathrow Airport High Speed Two Housing Hydrogen-Powered Trains Innovation Internet Ipswich Town Law Liverpool London London Overground London Underground Manchester Marks and Spencer My House New Bus for London New Stations Offshore Wind Power Olympics Phones Politics Project Management Religion Scotland Shopping Stations Step-Free Stroke Tax Television Thameslink The Netherlands Trains Trams Tunnels United States Walking Weather Wind Power Zopa
Tweets
Error: Twitter did not respond. Please wait a few minutes and refresh this page.
[…] on the Holloway Road Bridge, which is not in Murphy’s contract, that I wrote about in Did The Project Management Go Wrong On The Holloway Road Bridge?, can’t have helped […]
Pingback by Are Murphy Group Playing A Long Game? « The Anonymous Widower | November 17, 2016 |