UK Offshore Wind In 2030 – Calculated May 2026
The next general election is likely to be held in 2029, so how much wind energy will be added during the next Parliament?
The Current Position
The Wikipedia entry for the list of operational wind farms in the UK, says this.
In July 2025, there were offshore wind farms consisting of 2,809 turbines with a combined capacity of 16,035 megawatts.
Due To Be Commissioned In 2026
It would appear these wind farms will come on-line in 2026.
- Doggerbank A – 1235 MW – Fixed
- Sofia – 1400 MW – Fixed
This would add 2635 MW to give a total of 18,670 MW.
Due To Be Commissioned In 2027
It would appear these wind farms will come on-line in 2027.
- Doggerbank B – 1235 MW – Fixed
- Doggerbank C – 1218 MW – Fixed
- East Anglia 1 North – 800 MW – Fixed
- East Anglia 2 – 900 MW – Fixed
- East Anglia 3 – 1372 MW – Fixed
- Hornsea 3 – 2852 MW – Fixed
- Llŷr 1 – 100 MW – Floating
- Llŷr 2 – 100 MW – Floating
- Norfolk Boreas – 1380 MW – Fixed
- Pentland – 100 MW – Floating
- Whitecross – 100 MW – Floating
This would add 10157 MW to give a total of 28,827 MW.
Due To Be Commissioned In 2028
It would appear these wind farms will come on-line in 2028.
- Morecambe – 480 MW – Fixed
This would add 480 MW to give a total of 29,307 MW.
Due To Be Commissioned In 2029
It would appear these wind farms will come on-line in 2029.
- West Of Orkney – 2000 MW – Fixed
This would add 2000 MW to give a total of 31,307 MW.
Due To Be Commissioned In 2030
It would appear these wind farms will come on-line in 2030.
- Ramplion 2 Extension – 1200 MW – Fixed
- Norfolk Vanguard East – 1380 MW – Fixed
- Norfolk Vanguard West – 1380 MW – Fixed
- Awel y Môr – 1100 MW – Fixed
- Berwick Bank – 4100 MW – Fixed
- Outer Dowsing – 1500 MW – Fixed
- Caledonia – 2000 MW – Fixed
- N3 Project – 495 MW – Fixed/Floating
- North Falls – 504 MW – Fixed
This would add 14,659 MW to give a total of 45.966 MW.
Due To Be Commissioned In 2031
It would appear these wind farms will come on-line in 2031.
- Awel y Môr – 775 MW – Fixed
- Berwick Bank – 1380 MW – Fixed
- Dogger Bank SW – 1500 MW – Fixed
- Spiorad na Mara – 840 MW – Mixed
This would add 4,495 MW to give a total of 50,461 MW.
Due To Be Commissioned In 2032
It would appear these wind farms will come on-line in 2032.
- Caledonia – 2000 MW – Fixed
- Dogger Bank SE – 1500 MW – Fixed
This would add 3,500 MW to give a total of 53,961 MW.
Due To Be Commissioned In 2033
It would appear these wind farms will come on-line in 2033.
- Ayre 1008 MW – Fixed
- Bowdun – 1008 MW – Fixed
- Buchan – 960 MW – Floating
This would add 2,976 MW to give a total of 56,937 MW.
Due To Be Commissioned In 2036
It would appear these wind farms will come on-line in 2033.
- Havbredey – 1,500 MW – Fixed
This would add 1,500 MW to give a total of 58,437 MW.
Capacity Summary
- 2025 – None – 16,035 MW
- 2026 – 2635 MW – 18,670 MW
- 2027 – 10157 MW – 28,827 MW
- 2028 – 480 MW – 29,307 MW
- 2029 – 3500 MW – 31,307 MW
- 2030 – 14155 MW – 45.462 MW
- 2031 – 4,495 MW – 50,461 MW
- 2032 – 3,500 MW – 53,961 MW
- 2033 – 2,976 MW – 56,937 MW
- 2036 – 1,500 MW – 58437 MW
We’re still be adding capacity into the 2030s.
Project To Demonstrate 15+ MW Turbine On Ocergy’s Floating Platform Kicks Off
The title of this post, is the same as that of this article on offshoreWIND.biz.
This is the sub-heading.
The Reduced Commercial Risks with Demo of 15+ MW (RECORD15) joint industry project, which aims to install a latest generation turbine with a rated power over 15 MW on Ocergy’s floating platform in 2028, has been launched
The visualisation of the 15 MW turbine on its float in the article is impressive.
These two paragraphs add more details.
The Front-End Engineering Design (FEED) contract for this pilot project was recently signed between Ocergy and three offshore wind developers: EnBW Energie Baden-Württemberg AG, Kyuden Mirai Energy, and TEPCO Renewable Power.
Ocergy’s platform, the turbine agnostic OCG-Wind, is a modular design supporting an optimised assembly process from pre-fabricated steel sub-assemblies, allowing serial production using today’s existing supply chain and infrastructure, said the company.
Note.
- The average size of onshore wind turbine in the UK is 1.6 MW.
- Whitelee wind farm in Scotland, which is the largest onshore wind farm in the UK, uses 215 x 2.5 MW turbines.
- The Dogger Bank wind farm used 13 and 14 MW turbines on fixed foundations.
A 15+ MW turbine on a floating foundation will surely give Ocergy’s technology a very good test.
But it will be needed.
This is the overview of the Bowdun wind farm in Scotland, taken from the project’s web site.
The Bowdun Offshore Wind Farm will be located in the E3 leasing zone, which lies 44km off the coast of Aberdeenshire.
The zone, awarded to TWP under the ScotWind leasing round in January 2022, covers an area of 187km.
With water depths below 70m, it is highly suitable for fixed-foundation turbines, which will most likely sit on jacket foundations.
TWP plans to develop a 1GW offshore wind farm at the site. The base case is that the farm will number between 40-60 turbines, using ‘next-generation’ models with a capacity
between 18 MW and 25 MW. Construction is anticipated to commence in 2029 with commissioning planned for 2032-2033.This project base case will evolve as we gain knowledge from our site investigations and conduct technology research.
If turbines between 18 MW and 25 MW are to be used on fixed foundations, I can see a need to develop floats that will handle them.
Thistle Wind Partners Rename 2 GW ScotWind Offshore Wind Projects
The title of this post, is the same as that of this article on offshoreWIND.biz.
This is the sub-heading.
Thistle Wind Partners (TWP), a consortium founded by DEME Concession, Qair, and Aspiravi, has announced the final names for its two ScotWind offshore wind projects
This is the first paragraph.
TWP won the seabed leasing rights for two offshore wind projects in the ScotWind auction last year, in which 25 GW of capacity was awarded.
These paragraphs give details of the new names and an update on the sizes of the turbines.
The consortium plans to build the 1 GW Bowdun offshore wind project, originally named Cluaran Deas Ear, located off the coast of Stonehaven and lying 44 kilometres out from the landmark of Bowdun Head.
The site covers an area of 187 square kilometres (in the E3 leasing zone). The project is planned to feature between 50 and 60 wind turbines with an individual capacity of 18-25 MW each, depending upon the final design choice.
The second wind farm, located 33 kilometres from the East Mainland of Orkney in the NE2 leasing zone, is named the Ayre Offshore Wind Farm, originally called Clearan Ear-Thuath. This will be a 1 GW floating wind project following a similar base case for turbine numbers and capacity as Bowdun.
Note.
- They appear to be using 18-25 MW turbines.
- These are the first wind farms, that have talked about using such large turbines.
- 18 MW turbines would need 55 turbines for a GW.
- 25 MW turbines would need 40 turbines for a GW.
- Ayre wind farm has a web page, which says that it will have 56 x 18 MW turbines.
- Bowden wind farm has a web page, which says that it will have 56 x 18 MW turbines.
- The web site does say that the size and number of turbines is provisional.
Construction of both farms should start in 2029, with commissioning in 2033.
A Worthwhile Tailpiece
The article has a good tailpiece in the last paragraph.
TWP is one of the founders of a new initiative from the University of Highlands & Islands to deliver a STEM (Science, Technology, Engineering, and Mathematics) outreach programme for primary schools in Scotland, providing materials and teacher training.
TWP obviously intend to catch the next generation of technologists young.
Conclusion
Thistle Wind Partners have gone for the bold option.