Platforms

Consider.

  • The station has seven platforms, which are numbers 1 to 7 from South to North.
  • My Hull Trains service from London arrived in the Northernmost platform, which is numbered 7.
  • Most Hull Trains services seem to use this platform.
  • LNER services also seem to use Platform 7.
  • Platforms 4, 5 and 6 seem to be the same length as Platform 7
  • A friendly station guy told me, that LNER have run nine-car Class 800 trains into the station. These trains are 234 metres long.
  • My pictures show that Platform 7 is more than adequate for Hull Train’s five-car Class 802 train, which is 130 metres long.
  • The platforms are wide.

This second Google Map shows the Western platform ends.

It looks to me, that the station should be capable of updating to have at least four platforms capable of taking trains, that are 200 metres long.

Current Long Distance Services To Hull Station

There are currently, two long distance services that terminate at Hull station.

  • One train per hour (tph) – Manchester Piccadilly – two hours
  • Eight trains per day (tpd) – London Kings Cross – two hours and forty-four minutes

Both services are run by modern trains.

Improvements To The Current London And Hull Service

I believe Hull Trains and LNER will run between London Kings Cross and Hull using battery-equipped versions of their Hitachi trains, within the next three years.

The trains will also be upgraded to make use of the digital in-cab signalling, that is being installed South of Doncaster, which will allow 140 mph running.

In Thoughts On Digital Signalling On The East Coast Main Line, I estimated that this could enable a two hours and thirty minute time between London Kings Cross and Hull.

It is very likely that the service will be hourly.

Hull Station As A High Speed Station

Plans for High Speed Two are still fluid, but as I said in Changes Signalled For HS2 Route In North, there is a possibility, that High Speed Two could be extended from Manchester Airport and Manchester Piccadilly to Leeds and ultimately to Newcastle and Hull.

In that post, I felt that services across the Pennines could be something like.

  • High Speed Two – Two tph between London and Hull via Manchester Airport, Manchester Piccadilly and Leeds
  • High Speed Two – One tph between London and Edinburgh via Manchester Airport, Manchester Piccadilly, Leeds, York and Newcastle.
  • Northern Powerhouse Rail – One tph between Liverpool and Edinburgh via Manchester Airport, Manchester Piccadilly, Leeds, York and Newcastle.
  • Northern Powerhouse Rail – Two tph between Liverpool and Sheffield via Manchester Airport and Manchester Piccadilly
  • Northern Powerhouse Rail – Two tph between Liverpool and Hull via Manchester Airport, Manchester Piccadilly and Leeds

There would be four tph between Manchester Airport and Hull via Manchester Piccadilly, Leeds and other intermediate stations.

I estimate that the following timings would be possible.

  • London Euston and Hull – two hours and 10 minutes – Currently two hours and forty-four minutes to London Kings Cross
  • Liverpool and Hull – one hour and thirty minutes – No direct service
  • Manchester and Hull – one hour and three minutes – Currently two hours

As I said earlier London Kings Cross and Hull could be only twenty minutes longer by the classic route on the East Coast Main Line.

I think it will be likely, that both High Speed Two and Northern Powerhouse Rail will use similar High Speed Two Classic-Compatible trains, which will have the following characteristics.

  • Two hundred metres long
  • Ability to run in pairs
  • 225 mph on High Speed Two
  • 125 mph and up to 140 mph on Classic High Speed Lines like East Coast Main Line, Midland Main Line and West Coast Main Line and sections of Northern Powerhouse Rail.

It would appear that as Hull station can already handle a nine-car Class 800 train, which is 234 metre long, it could probably handle the proposed High Speed Two Classic-Compatible trains.

I could see the following numbers of high speed trains terminating at Hull in a typical hour would be as follows.

  • Two High Speed Two trains from London Euston
  • Two Northern Powerhouse Trains from Liverpool Lime Street
  • One Hull Trains/LNER train from London Kings Cross

As Hull already has four platforms, that can accept 200 metre long trains, I don’t think the station will have any capacity problems.

Charging Battery Trains At Hull Station

If Hull Trains, LNER and TransPennine Express, decide to convert their Class 800 and Class 802 trains, that run to and from Hull to Hitachi Regional Battery Trains, they will need charging at Hull station, to be able to reach the electrification of the East Coast Main Line at Temple Hirst Junction.

In Thoughts On The Design Of Hitachi’s Battery Electric Trains, I said this about having a simple charger in a station.

At stations like Hull and Scarborough, this charger could be as simple as perhaps forty metres of 25 KVAC overhead electrification.

    • The train would stop in the station at the appropriate place.
    • The driver would raise the pantograph.
    • Charging would start.
    • When the battery is fully-charged, the driver would lower the pantograph.

This procedure could be easily automated and the overhead wire could be made electrically dead, if no train is connected.

Platforms 4 to 7 could be fitted out in this manner, to obtain maximum operational flexibility.

Full Electrification Of Hull Station

Full electrification of Hull station would also allow charging of any battery electric trains.

I would hope, that any partial electrification carried out to be able to charge trains would be expandable to a full electrification for the station and the connecting rail lines.

A Full Refurbishment

The station would need a full refurbishment and a possible sorting out of the approaches to the station.

But this type of project has been performed at Kings Cross and Liverpool Lime Street in recent years, so the expertise is certainly available.

These pictures are of Liverpool Lime Street station.

I could see Hull station being refurbished to this standard.

Conclusion

It is my belief that Hull would make a superb terminal station for both High Speed Two and Northern Powerhouse Rail

In the interim, it could be quickly developed as a modern terminal for long-distance battery electric trains to make services across the Pennines and to London zero carbon.

The work could also be organised as a series of smaller work packages, without interrupting train services to and from Hull.

 

 

 

 

 

 

 

October 9, 2020 - Posted by | Transport | , , , , , , , , , , , , ,

1 Comment »

  1. On a totally separate subject, it looks like the 737Max jets will get clearance to fly by the FAA soon. Boeing took a hit for their complacency with this plane and I find it hard to trust this aircraft. I do not want to fly on one myself.

    https://www.bbc.co.uk/news/business-54477605

    Comment by MauriceGReed | October 9, 2020 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.