The Anonymous Widower

Platform 0 At Redhill Station Is Progressing

Redhill station is being upgraded.

This picture of the new Platform 0 was taken from the existing Platform 1.

Works include.

  • The new Platform 0 will become a through platform for trains to London.
  • It is certainly long enough for a twelve car train.
  • It appears it will be fully connected to the entrsnce by the car park.
  • The current platform 1 will become a South-facing bay platform.

The January 2018 Edition of Modern Railways, also says this about the upgrade.

This is aimed to allow GWR to boost the Reading to Gatwick frequency from hourly to half-hourly from May 2018. The operator’s ultimate sim is to introduce a third hourly service on the North Downs line, although concerns from Network Rail about level crossing risk have affected progress with this plan.

Currently, the journey between Reading to Gatwick Airport takes 76 minutes without a change, but the train reverses direction at Redhill. One driver told me, that if GWR issued the drivers with better shoes, they could save a minute or so on the timetable at Rewdhill.

But 76 minutes isn’t a bad time by way of the North Downs Line. Especially, as the trains have to negotiste eleven level crossing! Is that what Network Rail mean by level crossing risk?

If you take Crossrail’s estimate of the Reading to Farringdon time of 59 minutes and the timetabled Farringdon to Gatwick Airport time of 54 minutes, you get a time 113 minutes or nearly forty minutes longer than the shorter and more direct route.

The North Downs Line is partly electrified with third rail and I wonder what time a Class 802 train could achieve!

Conclusion

The Platform 0 works at Redhill station are part of a fifty million pound project, whivh will do the following.

  • Increase capacity at Redhill station.
  • Remove conflicts between Brighton Line and Reading to Gatwick Airport services.
  • Enable a two trains per hour service between Reading and Gatwick Airport.

It will be interesting to see if it works in May 2018.

The works do show how money spent on smaller projects can give multiple benefits.

 

December 21, 2017 - Posted by | Travel | , , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.