Ticketing On Heathrow Southern Railway

This article on City AM is entitled New Elizabeth Line Services Are Coming To Heathrow’s Terminal 5 After Airport Strikes Deal With The Government and TfL. It contains this paragraph.

Heathrow has also announced that it is introducing Oyster and contactless payments for all rail services going into the airport. From May 2018, new ticket readers will be installed at Heathrow, so anyone using Heathrow Express and TfL Rail will be able to use an Oyster or contactless.

When I passed through Heathrow a couple of weeks ago, there was evidence of new ticket gates being installed.

Heathrow Southern Railway’s Proposed Services

Heathrow Southern Railway are proposing four services to the West of Terminal 5 at Heathrow.

  • Heathrow Express from Terminal 5 to Woking, Guildford and Basingstoke, with an additional stop at Farnborough Main.
  • Crossrail from Terminal 5 to Staines
  • A service from Terminal 5 to Waterloo with stops at Staines, Clapham Junction and possibly Ashford, Felham, Twickenham, Richmond and Vauxhall.
  • A service from Terminal 5 to Weybridge with stops at Egham, Virginia Water, Chertsey and Addlestone.

Some of the stations like those between Feltham and Waterloo already accept contactless ticking, but surely all of them must if Heathrow Southern Railway is built, as you’ll be able to use contactless ticketing at Heathrow, but not at say Woking or Basingstoke.

Onward From Basingstoke, Guildford And Woking

A proportion of travellers from places like Bournemouth, Exeter, Portsmouth, Salisbury and Southampton will use Heathrow Southern Railway to get to the airport, with an appropriate change at Basingstoke, Guidford or Woking.

Will these travellers want to use contactless ticketing?

Conclusion

There will be a lot of discussions about ticketing on the Heathrow Southern Railway.

These ticketing issues, help to make it very understandable, why MTR, a partner in South Western Railway, want to join the Heathrow Southern Railway, as I wrote about in MTR Vying To Join Heathrow Southern Rail Bid.

Travellers want the ticketing system with the least hassle and as London is proving, contactless ticketing with bank cards works well!

 

 

 

April 8, 2018 Posted by | Transport | , , , , | Leave a comment

GWR Announces Plans To Replace Class 332s As It Takes Over Heathrow Express Service

The title of this post, is the same as that of this article on Global Rail News.

In some ways, I was surprised that Heathrow Airport are handing over the running of Heathrow Express to Great Western Railway (GWR).

But.

  • It seems, that the main problem, in that HS2 want their depot for construction of their new line.
  • GWR will use twelve Class 387 trains to run the service as opposed to the the current fourteen Class 332 trains.
  • The new trains will be updated with First Class, high speed wi-fi and more luggage space.
  • The deal seems to run to 2028.

I do think, that the main reason could be, that this gives FirstGroup or MTR Corporation a say in all the railways, serving or going near Heathrow Airport.

  • GWR is owned by FirstGroup.
  • Crossrail is operated by MTR on begalf of Transport for London.
  • South Western Railway is a joint venture between FirstGroup and MTR.

The operation of Heathrow Express by GWR completes the set.

My post; MTR Vying To Join Heathrow Southern Rail Bid, could link MTR to the proposed Heathrow Southern Railway, who are hoping to create a link into Heathrow Airport from the South.

One of the plans of Heathrow Southern Railway is to create a new Basingstoke/Guildford – Woking – Heathrow – Paddington service.

  • This would have a frequency of two trains per hour (tph) between Paddington and  both Basingstoke and Guildford.
  • This would mean there would be a four tph Frequency between Paddington and Woking via Heathrow Terminal 5, Heathrow Terminal 2/3 and Old Oak Common.
  • Creating the new service by extending Heathrow Express, means that the new service can take-over the paths used  by  Heathrow Express, to and from Paddington.
  • It is also worth noting that the Class 387 trains, that GWR are proposing to use on Heathrow Express are dual-voltage and can run on tracks with third-rail electrification.

Heathrow Express will become a double-ended service,  in much the same way that Gatwick Express takes passengers from both London and Brighton to the airport.

GWR taking over Heathrow Express must make the operation of trains to and from Heathrow Airport easier.

Why Change The Trains?

I think there are various reasons.

Operation And Maintenance

Obviously, if GWR uses only Class 387 trains on their shorter electrified routes from Paddington, this gives advantages in terms of operation, maintenance and staff utilisation and training.

I suspect too, that GWR have the depot space and sidings, to accommodate all the Class 387 trains they need.

Increasing Fleet Size

There are two published plans y to increase rail services to Heathrow.

  • Heathrow Southern Railway would like to extend Heathrow Express to Woking and ultimately to Basingstoke and Guildford.
  • Western access to Heathrow could also be a route for Heathrow Express to perhaps Reading and Oxford.

In the future there could be other services.

  • Developments could mean that a Heathrow-Gatwick service could be possible and worthwhile.
  • There is speculation in the media, about a direct service between Heathrow and Southampton.

Any expansion of services would probably need more trains.

If they need more Class 387 trains in the future, there are two operators, who have small fleets of Class 387 trains.

Some of these might become available, as the operators consolidate and update their fleets.

Acquiring more Class 332 trains could be problematical.

The Class 387 trains route, means that Heathrow Express will remain a  fleet of identical trains.

Operation On Routes With Third Rail Electrification

Any expansion of Heathrow Express to the Western side of Terminal 5 could connect to the extensive network of third-rail electrification.

For this reason, a Heathrow Express fleet without the capability to use third-rail electrification, would be limited in its market.

The Class 387 trains have been designed as dual voltage units and could work on third-rail networks by adding third-rail shoes.

Can Class 332 trains work on third-rail routes?

Operating Speed

The Class 387 trains are also 110 mph trains, whereas the operating speed of the Class 332 trains is 100 mph.

The faster operating speed must help operation on the busy fast lines to and from Paddington, where the Class 800 trains are 125 mph capable.

Train Length Issues

Consider.

  • The current Class 332 trains, run as nine-car trains, consisting of one four-car and one five-car trainset.
  • Class 387 trains are basically a four-car trainset, which can run as four, eight or twelve-car trains.
  • To complicate matters, Crossrail, which will use the same platforms at Heathrow are planning to nine-car Class 345 trains, but these could be lengthened to ten or even eleven cars.

These probably cause no problems with the current service, as running eight-car Class 387 trains would probably provide enough capacity.

Would a twelve-car Class 387 train need some platforms to be lengthened?

A four-car Class 387 unit is 80.77 metres long, so a twelve-car train would be 243 metres long.

This compares with the following.

  • Heathrow Express Class 332 – Nine cars – 206 metres.
  • Crossrail Class 345 – Nine cars – 205 metres
  • High Speed Train running with eight carriages – 220 metres
  • Inter-City 225 running with nine carriages – 246 metres
  • Two five-car Class 444 trains running togeyther – 230 metres
  • Two five-car Class 800 trains running together – 260 metres

A twelve-car Class 387 train is long, but not wildly out of line.

As the pairs of Class 800 trains work into Paddington,, I suspect twelve-car Class 387 trains can do the same.

If there is a problem, it will be in the Hathrow stations.

Alternatively, could some extra cars be built by Bombardier to create five-car trains, that would work as ten-car units, which would be around two hundred metres long?

Joining And Splitting Of Trains

Could Heathrow Express benefit from trains with the ability to split and join?

When there are more than one route to the West from Terminal 5, there may be advantages for trains to split and join in Terminal 5 station, to serve more than one destination to the West of the airport.

This picture was taken, as I watched two Class 387 trains joining together.

Note the driver in the cab on the right, controlling the process.

There is also a gangway between the two Class 387 trains, which the Class 332 trains don’t have.

Updating The Trains

The production of Class 387 trains has only just finished at Derby, but the Class 332 trains were built twenty years ago.

So could it be, that creating a modern fleet with all the features needed is easier with the later trains?

Suitability For Use With Heathrow Southern Railway Proposal

There are various issues here.

These concern fleet size and capacity

  • Any extensions to the South and West will need more trains.
  • If express services between Basingstoke, Guildford and Woking, and Paddington via Heathrow are successful, this could lead to calls for more services and other destinations, which could need more trains.
  • If five-car units were needed, then Bombardier could probably oblige.
  • There may be a need to lengthen platforms at the Heathrow stations.

Expanding a Class 387 train fleet would be easier.

There are also line speed issues.

  • What would be the design operating speed of Heathrow Southern Railway’s tracks alongside the M25? – 90, 100 or even 125 mph!
  • Could the operating speed of the Chertsey Branch Line be increased to the same speed, as there are only two stations; Chertsey and Addlestone?

The 110 mph maximum speed of a Class 387 could be a serious advantage, as speed sells!

How Many Trains Would Need To Be Converted?

Currently, there are fourteen Class 332 trains working Heathrow Express services.

They usually work in pairs, so there are seven trains.

If these are replaced by twelve-car Class 387 formations, that means up to twenty-one trains will be needed for the airport services from their current fleet of forty-five trains.

Eight-car formations would need fourteen trains.

Conclusion

It appears to me, that it is good decision to change the fleet for Class 387 trains.

Overall Conclusion

It’s all coming together for Heathrow Southern Railway.

March 28, 2018 Posted by | Transport | , , , , , , | 12 Comments

MTR Vying To Join Heathrow Southern Rail Bid

The title of this post, is the same as that of this article in New Civil Engineer.

The title gives you all you need, but consider these facts about MTR.

  • MTR is a Hong Kong company with a revene of about £4 billion per year, which is about the same size as the Stagecoach Group.
  • MTR will be running Crossrail for Transport for London.
  • MTR in partnership with First Group, are running South Western Railway.

In addition, FirstGroup are running Great Western Railway.

So it could seem logical for MTR to be included in the consortium behind Heathrow Southern Railway, as they could have a lot of influence on the consortium’s policies.

In an argument about train paths or stations, MTR or their partner; First Group, will be involved on both sides.

The problem is Heathrow Airport and their ownership of Heathrow Express, especially if it is extended deep into South Western Railway territory at Basingstoke, Guildford or Working.

This is said on the Heathrow Southern Railway web site.

Whether or not a third runway is built, many more passengers and airport workers need to be accessing Heathrow by train. The Government’s recent M25 South West Quadrant Study ruled out widening the motorway. HSR provides the alternative, switching traffic from the roads and contributing to improving local air quality. We estimate that HSR will reduce use of this section of the M25 by over three million car trips a year.

Heathrow might be a greedy bully, but they probably need a superb rail service more, than they need to own Heathrow Express.

MTR and AECOM, who is a large partner in Heathrow Southern Railway partner, are big enough to stand up to anybody.

 

March 21, 2018 Posted by | Transport | , , , , , , , | 2 Comments