I’m writing this post for two reasons.

The first is to inform people that in the Summer of 2021, there is going to be a closure of the Bank Branch of the Northern Line for several months.

The second, is to illustrate, how in a large transport system like London, good project management can carry out major works, without too much inconvenience to passengers.

This article on IanVisits is entitled Behind The Scenes At London Underground’s Bank Tube Station upgrade.

I suggest you read the article, to get the scale of the project.

In the Summer of 2021, a section of the Bank branch of the Northern line will close for roughly 3 months.

The main reason is so that the New Southbound tunnel can be joined to the existing Southbound tunnel, North and South of Bank station. Think of it as installing a by-pass round a village. Except it’s a railway and it’s around forty metres below ground.

Ian says this about what else will happen, whilst the Northern Line is closed.

While that’s going on, at Bank station, the old southbound tunnel will have it’s tracks filled in and turned into a new large concourse, while the currently hidden new side passages are cut through into the old northbound platform and finished off.

Come roughly September 2021, after a few months of closure, people will arrive at Bank station and see these huge new tunnels, the new escalators down to the DLR, the travolator to the Central line.

This approach is very common on the railways.

If a line has to be closed completely for a few months, say because a tunnel is being repaired, then during the closure, you do all the other tasks you can.

At Bank, where a new track is being connected, there will be no trains through the station for a few months. So all the other jobs will be done in this window.

There may also be other advantages. At Bank station, the Northbound track itself is not being radically changed, so it might be possible to use battery locomotives to bring in supplies and take out rubbish.

Summer 2021 Is Two And A Half Years Away

Project Planners have calculated and it will probably take until the end of 2020, for everything to be ready before the closure can take place, so that the joining of the tracks can begin.

But there could  other reasons, for the 2021 date.

Bank station is an important station on the Northern Line and closing it will cause a lot of inconvenience for passengers, many of whom will still be commuting to the City of London.

Some Big Projects Will Be Complete Before The Closure

Before Summer 2021, these big projects should have been completed.

  • One completed on Friday, when the new Bank Station entrance on Walbrook opened.
  • Crossrail will have opened.. On current forecasts nearly two years earlier.
  • The Northern City Line will be running new Class 717 trains into Moorgate station.
  • Travellers will have learned to use Thameslink as part of the Underground.

All of these projects will help passengers to cope with the Northern Line Closure at Bank station.

Bank Station Will Still Be Partially Open For Business

Bank station will not be fully-closed.

  • The Central Line will be working at Bank station, to something like full capacity.
  • The Waterloo & City Line will be working normally using the new Wallbrook entrance.
  • The Docklands Light Railway will be working, as is possible around all the work.
  • Some new and refurbished routes will connect the Central Line and Docklands Light Railway to the myriad station entrances around Bank Junction.
  • The Circle and District Lines will be working normally, through Monument station.

In addition, the City of London will have improved walking and cycling in the Square Mile.

Where Will Northern Line Trains Run During The Closure?

For a start, all Northern Line trains through Charing Cross station will be running normally.

The Northern Line Extension to Battersea might even have opened, which would give an extra Southern terminal to the Northern Line, which would help operation of the Charing Cross Branch.

Looking at the detailed tracks on carto.metro.free.fr, it appears that trains from the North can turn back at Euston and Moorgate.

Consider.

  • Euston will be in the throws of rebuilding for High Speed Two.
  • The Northern Line is the preferred route between Euston and the City.
  • Moorgate will be a fully step-free rebuilt station with connections to Crossrail and the Central Line.
  • Many people can walk to most parts of the Square Mile from Moorgate.

It looks to me, that it is most likely that Northern Line services will terminate at Moorgate during the closure of the Northern Line through Bank.

Northern Line trains approaching the City from the South have no such convenient turn back between Kennington and Bank stations.

I think the best direct service passengers from the Morden Branch to the City can expect will be a not-very-frequent shuttle service to London Bridge.

Most who need to go to Bank station from the South will find alternative routes and there are several.

  • Travel to London Bridge and walk across the river.
  • Change to the Waterloo and City Line at Waterloo.
  • Change to the Circle and District Lines at Embankment.
  • Change to the Central Line at Tottenham Court Road
  • Change to Crossrail at Tottenham Court Road and walk from Moorgate.

It should also be remembered, that as the closure is taking place in the Summer holidays, travellers should cope.

Conclusion

As Project Managers always seem to say.

You must get your ducks in a row!

So in this example, I would have felt that to have rebuilt Bank station without completion of the following projects.

  • Crossrail
  • Bank Station Walbrook Entrance

Would have been a lot harder.

This example also means that you must get your large projects in the right order, so they help each other to be delivered on time.

London has several large station interchange projects in the pipeline.

  • Camden Town station
  • East Croydon station
  • Holborn station.
  • Oxford Circus station
  • Victoria station

Which I believe should be done in the optimal order, so that travellers suffer the least disruption.

Smaller projects like a second entrance At Walthamstow Central station should probably be done at a time, when money and resources are available.

 

December 2, 2018 - Posted by | Transport | , , , , , , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.