The title of this post, is the same as that of this article on Rail Engineer.

It is an article that should be read, by anybody with an interest in either Merseyrail’s trains or modern urban rail networks in general. As Stadler, will be providing a fleet of trains for the Tyne and Wear Metro, I suspect a lot of the points made in the article can be expected to have parallels on that network as well.

What About The Signalling?

The article talks about the management of the signalling, but it says little about signalling in the future, although it does say that Merseyrail will be covered by a very high capacity digital network.

London’s Digital Signalling Revolution

In London, there are four tunnelled routes, that in a few years time will be running under full digital signalling.

  • Crossrail
  • East London Line
  • Northern and City Line
  • Thameslink

Note.

  1. Thameslink is already running upwards of twenty trains per hour (tph) using digital ERTMS signalling.
  2. Crossrail will be running 24 tph using digital ERTMS signalling.
  3. The East London Line currently handles 16 tph and will soon be handling 20 tph.
  4. The Northern and City Line will be going to digital ERTMS signalling, when it is applied to the Southern end of the East Coast Main Line.
  5. , In addition to the Circle, District, Jubilee, Metropolitan, Northern and Victoria Lines of the London Underground have digital signalling.
  6. Dear old Vicky is actually running 36 tph between two-platform stations at Brixton and Walthamstow Central.
  7. I wouldn’t bet against Vicky running the magic 40 tph, to become the most frequency line in the world.

All of these London systems, have one great advantage. In the tunnelled sections of the routes, there is generally only one class of fully digitally-equipped train, which must make system design and implementation easier.

Liverpool’s Digital Signalling Revolution

Consider.

  • As the article says, Merseyrail now has a world-class high-capacity digital network, that is accessible by all of its trains.
  • It has ordered 52 new Class 777 trains and has options for another sixty.
  • There are proposals to extend the Merseyrail network to Manchester, Preston, Skelmersdale, Warrington, Wigan and Wrexham.
  • The Northern Line runs at a frequency of 12 tph.
  • The Wirral Line runs at a frequency of 14 tph.
  • The loop Line has recently been relaid, so is probably high-quality track.

Compared to London’s tunnelled routes, the Northern and Wirral Lines are not handling a large number of trains.

But Liverpool now has a digital network to support the signalling and trains that could be upgraded to use it are arriving.

I wouldn’t be surprised to find that the maximum train frequency on Merseyrail is at least twenty tph or one train every three minutes.

What Would Twenty tph Do For The Wirral Line?

Currently, the following destinations are served by the Wirral Line and the services use the Loop under Liverpool City Centre.

Note.

  1. The current frequency around the Loop is 14 tph.
  2. Merseyrail is proposing to extend the Ellesmere Port service to Helsby, using battery-equipped Class 777 trains
  3. There is also an hourly service from Bidston to Wrexham Central in the Borderlands Line.
  4. I can see no technical reason why, the Bidston and Wrexham service could not be run using battery-equipped Class 777 trains and terminating in the Loop.

Surely, the ultimate twenty tph service on the Wirral Line would be as follows.

  • Chester – Four tph
  • Helsby via Ellesmere Port – Four tph
  • New Brighton – Four tph
  • West Kirby – Four tph
  • Wrexham Central – Four tph

All twenty tph would terminate in the Loop under Liverpool City Centre.

What Would Twenty tph Do For The Northern Line?

Currently, the following Northern destinations are served by the Northern Line.

And these Southern destinations are served.

Note.

  1. The current frequency, through the central section is 12 tph.
  2. There is a proposal, that I wrote about in Liverpool’s Forgotten Tunnel for the trains terminating at Liverpool Central station to use the Wapping Tunnel to connect to the City Line.
  3. There is a proposal to extend the Ormskirk service to Preston, using battery-equipped Class 777 trains.
  4. There is a proposal to extend the Kirkby service to Headbolt Lane and Skelmersdale, using battery-equipped Class 777 trains.
  5. There must also be a possibility of a service that extends the Kirkby service to Wigan Wallgate, using battery-equipped Class 777 trains.

The service des appear to be biased towards the Northern end, with more possibilities there for extra trains than in the South.

This is why the plan to expand to the East through the Wapping Tunnel has evolved, as it gives the following possible destinations.

  • Manchester Oxford Road
  • Warrington Bank Quay
  • Warrington Central
  • Wigan North Western

Note.

  1. All destinations are currently served from Liverpool Lime Street by Northern.
  2. There must also be the possibility of a direct service to Liverpool Airport.
  3. There must also be the possibility of a service on the Canada Dock Branch to Bootle.

I can envisage between 12 and 16 tph through the Wapping Tunnel, which with the four tph to Hunts Cross could mean 16 to 20 tph on the Northern Line.

Conclusion

It would appear that a very frequent system can be developed on Merseyside, if frequencies common in London can be achieved.

 

August 23, 2020 - Posted by | Transport | , , , , , , ,

2 Comments »

  1. The 777s are 4 cars long. They can be long, but I believe they want more frequency, so can keep the trains shorter.

    Comment by John | August 31, 2020 | Reply

    • Liverpool’s digital network will allow both longer and more frequent trains. The only limitation is platform length on the various routes.

      Comment by AnonW | August 31, 2020 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.