Will Crossrail Open To Reading in 2019?

The latest rather dodgy date for the opening of Crossrail’s Core Tunnel is Autumn 2019.

In the January 2019 Edition of Modern Railways, there is an article, which is entitled Crossrail Can’t Commit To Autumn Opening.

This a paragraph from the article.

TfL also says that it is exploring with DfT the possibility of beginning to operate Reading to Paddington services ahead of the completion of the Elizabeth Line to help provide a boost in revenue.

This is a very interesting possibility.

How Much Work Is Still To Be Done To The West of Hayes & Harlington?

This is the key factor as to whether Western Branch of Crossrail can be opened.

  • The biggest problem is that Class 345 trains can’t run to Heathrow as there are signalling issues to eradicate.
  • There are also several stations, that need to be completed.

There is no work-round to the first problem, but trains seem to be able to call at the unfinished stations.

It would appear, that for TfL’s proposal to be taken fully forward, the signalling issues to and from Heathrow, must be dealt with.

The stations can be finished later.

The Current Proposed Crossrail Service To Reading And Maidenhead

These are the proposed services shown on Wikipedia, so they could have been updated.

Reading To Paddington – Limited Stop

This service will be run at two trains per hour (tph) in the Peak with no trains in the Off-Peak.

Stops are Twyford, Maidenhead, Slough, West Drayton and Ealing Broadway.

Reading To Paddington – All Stations

This service will be run at two tph all day.

The service will call at all stations except Hanwell and Acton Main Line.

Maidenhead To Paddington

This service will be run at two tph all day.

The service will call at all stations except Hanwell and Acton Main Line.

A Summary Of Peak/Off Peak Calls

Adding these service up, gives the following numbers for Peak and Off Peak calls in trains per hour (tph)

  • Reading – 4,2
  • Twyford – 4,2
  • Maidenhead – 6,4
  • Taplow – 4.4
  • Burnham 4,4
  • Slough – 6,4
  • Langley – 4,4
  • Iver – 4,4
  • West Drayton – 6,4
  • Hayes & Harlington – 4.4
  • Southall – 4,4
  • Hanwell – None to Reading/Maidenhead
  • West Ealing – 4.4
  • Ealing Broadway – 6,4
  • Acton Main Line – None to Reading/Maidenhead
  • Paddington – 6,4

Note.

  1. 4,2 means 4 tph in the Peak and 2 tph in the Off Peak.
  2. It would appear that all stations except Reading and Twyford have at least four tph all day.
  3. Stations between Hayes & Harlington and Ealing Broadway will get another six tph all day going to Heathrow.
  4. Acton Main Line station will get another four tph all day going to Heathrow.

This gives the following frequencies.

  • Reading – 4,2
  • Twyford – 4,2
  • Maidenhead – 6,4
  • Taplow – 4.4
  • Burnham 4,4
  • Slough – 6,4
  • Langley – 4,4
  • Iver – 4,4
  • West Drayton – 6,4
  • Hayes & Harlington – 10,10
  • Southall – 10,10
  • Hanwell – 6,6
  • West Ealing – 10,10
  • Ealing Broadway – 12,10
  • Acton Main Line – 4,4
  • Paddington – 12,10

I can draw these conclusions from the figures.

  • Every station has a good service from Crossrail.
  • But could Reading and Twyford have another two tph in the Off-Peak to make the services four tph all day?
  • Paddington station would need perhaps two or three platforms dedicated to Crossrail to handle twelve tph.
  • The maximum frequency of 12 tph should be easily handled with conventional signalling and could be increased with modern digital signalling.

It looks like running the Western services of Crossrail from Paddington could be a possibility.

Consider.

  • The Reading and Maidenhead services will be run on routes with mainly conventional signalling.
  • The Class 345 trains, which each can hold 1,500 passengers would give a massive capacity boost to the outer Crossrail stations.
  • Heathrow services can be run with Class 345 trains, when the signalling problems are solved.
  • Higher frequencies to and from Paddington may enable trains to provide a better interchange with branch line services, at West Ealing, Slough, Maidenhead and Twyford.

But I think that separating these services initially from Crossrail will have substantial operational and development  benefits.

  • Paddington to Reading is essentially a self-contained railway, with a major branch to Heathrow and four small branch lines worked by diesel shuttle trains.
  • The route, with the exception of the Heathrow branch, has conventional signalling.
  • The signalling problems of the Heathrow branch can be solved independently.
  • The Western branches of Crossrail could be fully debugged before trains start running through the Core Tunnel.

I also wonder, if the route could be useful for mileage accumulation, driver training  and certification of newly-delivered trains.

Is It Just About The Money?

The original Modern Railways extract said that the proposal was to help provide TfL with extra revenue.

It must bring in revenue and especially when the Heathrow Branch is working reliably to plan.

Faster Journeys

Modern Class 345 trains have the following advantages over the current British Rail-era Class 156 trains.

  • They are slightly faster.
  • They have better acceleration.
  • They are modern trains designed for short dwell times at stations.

It would be very likely, that journey times between Paddington and Reading, will improve..

Passenger Behaviour

But passengers may change their behaviour .

  • Will passengers use Crossrail as a lower-cost alternative to Heathrow Express?
  • Will passengers use Crossrail as a faster alternative to the Piccadilly Line?
  • Will passengers,  going between Heathrow and the West and Wales, use Crossrail to and from Reading, with a change at Hayes & Harlingon?
  • Will passengers on branch lines find the extra capacity helpful, when travelling to London or Reading?

In addition, as I said earlier, I think opening Paddington to Reading early,, could make finishing the Crossrail project easier.

If nothing else, it shortens the to-do list!

GWR Might Object

Will GWR object to losing their local services between Reading and London to Crossrail?

Consider the following issues.

Heathrow Express

GWR have taken over the lucrative Heathrow Express.

  • Heathrow Express will be run using 110 mph Class 387 trains in an Airport Express configuration.
  • Will these trains be less of a block on the line, than the 100 mph Class 332 trains currently running the service?
  • Currently both Class 332 and Class 800 trains take nine 9½ minutes to go between Paddington and Heathrow Airport Junction.

Perhaps GWR could squeeze in extra trains, by replacing the Class 332 trains with faster Class 387 trains?

The more trains they could squeeze into Paddington, the larger their revenue.

Reading, Bedwyn and Oxford Services

I am not sure, but it does appear that GWR services to places like Bedwyn and Oxford will in future be run using the new five-car Class 802 trains.

  • The trains will surely use electric traction on the fast lines to Paddington.
  • Will passengers going between Bedwyn/Oxford and stations between Reading and Paddington, be happy to change at Reading?

As it appears that Bedwyn/Oxford services might not need to use the slow lines, these will be used  exclusively by  Crossrail and the occasional freight.

Could Bedwyn And Oxford Services Be Combined?

There is also the possibility that to save paths on the fast lines between Reading and Paddington, that hourly Bedwyn and Oxford services could be combined and split at Reading.

  • GWR already splits and joins Class 387 trains at Reading.
  • Class 800/802 trains are designed to be split and joined quickly.
  • Timings to the two destinations are about the same, being around 75 minutes.

Two five-car Class 802 trains with one running to Bedwyn and one to Oxford might be a good idea. Especially, as it saves one high-speed path between Paddington and Reading  and possibly a few trains.

It does look, that Oxford and Bedwyn services could be moved out of the way of Crossrail services.

Will There Be Enough Class 800/802 Trains?

In Huge Increase In Capacity On GWR As Final Class 800 Enters Traffic, I wrote that there are now only fifteen trains of a total fleet of 93 trains to be delivered.

I suspect that GWR can find enough trains to run Bedwyn/Oxford services to London.

Too Many Class 387 Trains!

But it does strike me that GWR will have too many Class 387 trains, if Crossrail takes over local services to Reading and Class 802 trains take over services to Bedwyn and Oxford.

Twelve Class 387 trains are being converted to take over Heathrow Express services, but that still leaves GWR with 33 trains to find a use for.

It seems like Greater Anglia’s twenty Class 379 trains, they could become homeless orphans.

Will The Class 769 Trains Get In The Way?

Original plans talked about using 100 mph Class 769 trains to back up the Class 387 trains, whilst twelve of these were updated to Heathrow Express standard.

But it appears now from Wikipedia and other sources on the Internet, that these trains will concentrate on the following services.

  • Reading To Gatwick Airport
  • Reading to Oxford

I can’t find any reference of them continuing to serve Paddington, so it looks like they should keep out of the way.

Serving The Henley And Marlow Branches

Henley-on-THames station on the Henley Branch Line and Bourne End station on the Marlow Branch Line are having their Peak services to London gradually withdrawn.

If Crossrail took over services between Reading and Paddington, the frequencies in the Peak at the interchange stations would be.

  • Maindenhead for the Marlow Branch Line – 6 tph,
  • Twyford for the Henley Branch Line – 4 tph

Two tph at each interchange station run limited stop to and from Paddington.

The trains will each hold 1,500 passengers.

Could it be that GWR feel that the increased frequencies and reduced journey times to and from Paddington mean that there is a lesser need to run a direct diesel service.

But I could see the following.

  • A four-car shuttle train, which could be a Class 769 bi-mode, at two tph on the Henley Branch Line.
  • Two tph on the Marlow Branch Line.

At least GWR have the trains to provide a service to match customer demand.

I also wouldn’t be surprised to see a radical plan for these branches.

No Diesel Running Into Paddington

Every train run by GWR and Crossrail, between Paddington and Reading, would use electric traction.

  • Now that large numbers of Class 800/802 trains have been delivered, it can’t be long before the last InterCity 125 runs into Paddington on a regular service.
  • Class 165 and Class 166 diesel trains will be refurbished and sent to the West Country.
  • Bedwyn and Oxford services will be run by Class 800/802 trains.

In addition all GWR trains running into Paddington will be 125 mph units running on electricity.

What is that worth as a marketing hook?

Conclusion

It looks to me, that running a full Western Branch service for Crossrail could be a good move.

So will it happen in 2019?

I think it all depends on solving the signalling issues on the Heathrow Branch!

But I feel, it should be possible, otherwise TfL wouldn’t have suggested it!

December 30, 2018 - Posted by | Transport | , , , , , , , ,

1 Comment »

  1. […] Will Crossrail Open To Reading in 2019?, I analysed this possibility, after it was raised in the January 2019 Edition of Modern […]

    Pingback by Crossrail Service To Reading On Track For December Opening « The Anonymous Widower | April 16, 2019 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: