Shell And ScottishPower Win Bids To Develop 5 GW Of Floating Wind Power In The UK

The title of this post, is the same as that of this press release from Shell.

This is three paragraphs from the press release.

Shell and ScottishPower have secured joint offers for seabed rights to develop large-scale floating wind farms as part of Crown Estate Scotland’s ScotWind leasing. The partners have won two sites representing a total of 5 gigawatts (GW) off the east and north-east coast of Scotland.

The new wind farms will be delivered through two joint ventures called MarramWind and CampionWind. They bring together ScottishPower’s and Shell’s decades of experience working offshore and significant presence in Scotland, as well as their strong innovation capabilities for delivering world-class offshore energy projects.

The development, construction and operation of ScotWind projects is set to bring new skilled jobs and manufacturing opportunities and boost local supply chains.

ScottishPower are actually involved in three large ScotWind projects; one by themselves and two in partnership with Shell.

MacHairWind

MachairWind is a project that Scottish Power is developing alone.

I wrote about this project in MacHairWind Wind Farm.

MarramWind And CampionWind

These two wind farms are being developed in partnership with Shell.

They both have their own web sites.

MarramWind’s web site has this introduction.

ScottishPower and Shell have joined forces to develop the MarramWind offshore windfarm following success in the recent ScotWind auction process by Crown Estate Scotland.

Located 75 kilometres off the North East coast of Scotland in water depths averaging 100 metres, the proposed MarramWind floating offshore windfarm could deliver up to 3 gigawatts (GW) of cleaner renewable energy.

This map clipped from the MarramWind web site, shows the location of the wind farm.

CampionWind’s web site has this introduction.

ScottishPower and Shell have joined forces to develop the CampionWind offshore windfarm following success in the recent ScotWind auction process by Crown Estate Scotland.

Located 100 kilometres from the east coast of Scotland, in water depths averaging 77 metres, the proposed CampionWind floating offshore windfarm could deliver up to 2 gigawatts (GW) of cleaner renewable energy.

This map clipped from the CampionWind web site, shows the location of the wind farm.

Note.

  1. The two wind farms will be within a few miles of each other.
  2. Both wind farms will use floating wind turbines.
  3. The water is a bit deeper at MarramWind, but this surely doesn’t bother a floating turbine.
  4. MarramWind and CampionWind will have a total capacity of 5 GW.
  5. Hywind Scotland is the world’s first commercial wind farm using floating wind turbines, situated 29 kilometres off Peterhead. This wind farm is only 30 MW, but in its first years of operation has achieved a capacity factor of over 50 %.
  6. The proposed turbines at Northern Horizons‘ 10 GW wind farm, which is 130 kilometres to the North-East of Shetland will be 20 MW giants and nearly as tall as The Shard in London.

So will Scottish Power and Shell design and build a combined field, similar in concept to Northern Horizons’ wind farm, using an armada of 250 floating wind turbines?

  • The wind turbines might be moored around a fixed or floating mother platform or structure, that will collect the electricity and deliver it to the shore.
  • Turbines could be serviced in situ or moved into port, as needed.
  • Extending the wind farm could just be a matter of mooring the extra turbines in position and then connecting them to the mother platform.
  • Is there a convenient disused oil or gas platform, that could be repurposed as the mother platform?

It certainly would appear to be a way of building large offshore fields in deep waters.

Where Would The Combined MarramWind And CampionWind Rank In Terms of UK Wind Farms?

Consider.

  • MarramWind and CampionWind will have a total capacity of 5 GW.
  • Phase one of the Hornsea Wind Farm is the largest offshore wind farm in the world, with a capacity of just over 1.2 GW and when complete it will have a capacity of 6 GW.
  • Northern Horizons is planned to be 10 GW.
  • The East Anglian Array could be as large as 7.2 GW.
  • The Dogger Bank Wind Farm is planned to be as large as 4.8 MW.
  • Norfolk Vanguard and Norfolk Boreas are a pair of 1.8 GW wind farms.
  • MacHairWind will be a 2 GW wind farm.

Note.

  1. This is not a complete list of large wind farms in the development pipeline.
  2. BP have obtained leases, but have not published their plans.
  3. Most farms under development are at least one GW.
  4. These farms are a total of 38.6 GW.

The Combined MarramWind and CampionWind would be one of several large wind farms around 5 GW.

There Is A Desperate Need For Energy Storage

If we are generating upwards of 40 GW of wind and solar energy in the UK, there will be a desperate need for energy storage to cover for the times, when the wind doesn’t blow and the sun doesn’t shine.

Scotland should be OK, as there are various energy storage projects in development.

  • The 1.5 GW/ 30 GWh Coire Glas project is according to SSE shovel-ready and has planning permission.
  • The 450 MW/2.8 GWh Red John project is being constructed.
  • Drax, ILI Group and SSE have several other projects under development.

So what would happen in the South?

The government appears to be on the case as I wrote in Ministerial Roundtable Seeks To Unlock Investment In UK Energy Storage.

But there is also the possibility of using hydrogen.

  • Hydrogen could be created by a series of giant electrolysers.
  • It could be blended with natural gas to eke out our natural gas and save carbon. According to HyDeploy, it appears that up to 20 % can be added, without needing to change boilers and appliances.
  • It can be stored in depleted offshore gas fields.
  • It can be used to power heavy transport like buses, trucks, trains and ships.
  • It can be burned in gas-fired power stations to generate electricity.

Hydrogen can also be used as a feedstock or green energy source for the making of chemicals, concrete and steel.

Conclusion

We are approaching the end of the first phase of the development of renewable energy in the UK.

Massive floating wind farms using armadas of floating wind farms, a large expansion of pumped storage hydro and a huge expansion of the use of hydrogen will see us through to a carbon-free future.

 

 

 

 

March 23, 2022 Posted by | Energy, Hydrogen | , , , , , , , , , , , , | 1 Comment

MacHairWind Wind Farm

MachairWind wind farm has its own page on the ScottishPower Renewables web site.

These are the two introductory paragraphs.

The MacHairWind project off the coast of Islay, which could deliver 2GW of cleaner renewable energy, will make a significant contribution to tackling climate change and achieving Net Zero, with the potential to generate enough clean electricity to power over 2 million homes in Scotland.

It will also build on ScottishPower’s long-standing presence and positive track record of investing in and working with local communities and businesses across Argyll & Bute to realise the benefits of renewable energy developments.

This Google Map shows the area of the wind farm, which is to the North West of the island of Islay.

Note.

  1. There certainly is a large space of empty sea to the North-West of Islay.
  2. Glasgow is not far away.

This second Google Map shows the area to the North-East of Islay.

Note.

Wikipedia says this about the relationship of the Cruachan power station and Hunterston’s nuclear stations.

Construction began in 1959 to coincide with the Hunterston A nuclear power station in Ayrshire. Cruachan uses cheap off-peak electricity generated at night to pump water to the higher reservoir, which can then be released during the day to provide power as necessary.

Now that the two nuclear stations are being decommissioned, will the MacHairWind wind farm be used to pump water to Cruachan’s higher reservoir?

Conclusion

The MacHairWind wind farm seems a well-positioned wind farm.

  • It is close to Glasgow.
  • It can be used in tandem with the Cruachan pumped hydro power station.
  • It will have access to the Western HVDC Link to send power to the North-West of England.

Is Scotland replacing the 1.2 GW Hunterston B nuclear power station with a 2 GW wind farm, with help from Cruachan and other proposed pumped storage hydro schemes to the North of Glasgow?

It also looks like increasing the power at Cruachan from the current 440 MW to a GW, by the building of Cruachan 2 would give the area even more energy security.

 

March 23, 2022 Posted by | Energy, Energy Storage | , , , , , , , | 4 Comments