Beeching Reversal – Unlocking Capacity And Services Through Bramley (Hants)

This is one of the Beeching Reversal projects that the Government and Network Rail are proposing to reverse some of the Beeching cuts.

Bramley Station

Bramley (Hants) station is on the  Reading-Basingstoke Line, which is 15.5 miles long.

  • The line is double-track.
  • Bramley station is the nearest one to Basingstoke station.
  • The two stations are about five miles apart.
  • The basic local service is two trains per hour (tph), with trains taking a few minutes under half-an-hour.
  • The speed limit is listed in Wikipedia at 75 mph and my Class 165 train was travelling at about 60 mph on both journeys between Basingstoke and Bramley stations.

This Google Map shows Bramley station.

Note the level crossing, just to the North of the station.

These are some pictures, that I took, whilst I spent about thirty minutes at Bramley station.

Note

  1. In the thirty minutes, I was at the station, two long freight trains and three passenger trains came through.
  2. The level crossing barriers were going up and down like a whore’s drawers.
  3. Each level crossing closure resulted in long queues at the barriers.

It reminded me how bad the level crossing at Brimsdown station used to be in the Peak in 1966, when I crossed it twice every day to go to and from work at Enfield Rolling Mills. At least I was on two wheels and it gave me a break from pedalling!

There is more on the problems of the level crossing on this article on the Bramley Parish Council web site, which is entitled Living With Our Level Crossing.

Current Future Plans For the Reading-Basingstoke Line

The Wikipedia entry for the Reading-Basingstoke Line has a Future section, where this is said.

The railway is listed with Network Rail as part of route 13, the Great Western main line, and was due to be electrified with 25 kV overhead wiring by 2017 as part of the modernisation of the main line.[8] In July 2007, plans were agreed to build a station in Reading south of Southcote Junction in the Green Park business park, serving the southern suburbs of Reading and also the Madejski Stadium. Construction of Reading Green Park railway station was expected to be completed in 2010; the plans were suspended in 2011, but were reinstated in 2013. It is now set to open by the end of 2020[9], with electrification along the line at a later date.

It is my view, that the new Reading Green Park station will probably mean that four tph between Reading and Basingstoke stations will be needed. especially if a second new station were to be built at Chineham.

But four tph would probably be impossible, without improving the traffic of both rail and road through Bramley.

Solving The Level Crossing Problem

Ideally, the level crossing should be closed and the road diverted or put on a bridge,

If you look at a wider map of the area, building a by-pass to enable road traffic to avoid the crossing will be difficult if not impossible.

But this is not an untypical problem on rail networks and not just in the UK.

I suspect that with precise train control using digital ERTMS  signalling, trains and level crossing closures can be timed to improve traffic on both road and rail.

Consider.

  • If trains crossed on the level crossing and they were under precise control, this would reduce the number of level crossing closures per hour.
  • If the line speed was higher and the trains ran faster, this should ease timetabling, as there could be more train paths per hour.
  • Faster accelerating electric trains would save time too, by shortening station dwell times.
  • A third track might be laid in places.
  • The signalling could possibly drive the train or tell the driver exactly what speed to travel, so trains passed on the crossing or in the station.

As Network Rail and their contractors roll-out ERTMS, they’ll discover better and more intelligent ways to deploy the system.

Electric Trains Would Help

Electric trains accelerate faster and if they use regenerative braking to batteries, this cuts station dwell times.

But powering them by electrification would mean the connecting lines between the Reading and Basingstoke Lines and the nearest electrified lines would also have to be electrified.  This would make the scheme excessively expensive.

But Battery Electric Trains Could Be Better!

I believe that battery electric trains, would be a more-than-viable alternative.

  • You still get the performance advantages of electric trains.
  • With charging at just one end of the route, a battery electric train could run a round trip on battery power.

The big advantage, would be that the only new electrification infrastructure needed would be to charge the trains.

Charging Battery Electric Trains At Reading Station

Reading is a fully electrified station and the shuttle trains to and from Basingstoke station, appear to use Platform 2.

This Google Map shows electrification gantries over Platforms 1, 2 and 3 at Reading station.

Note.

  1. The route between Reading station and Southcote junction, where the Basingstoke and Newbury routes divide, may be under two miles, but it is fully electrified.
  2. Trains take three minutes to travel between Reading station and Southcote junction.
  3. Trains wait for up to twenty minutes in the platform at Reading station.

It would appear that trains get enough time at Reading to fully charge the batteries.

Charging Battery Electric Trains At Basingstoke Station

The shuttle trains between Reading and Basingstoke stations, appear to use Platform 5 in Basingstoke station.

This Google Map shows Platform 5 at Basingstoke station.

Platform 5 is towards the top of the map and contains a two-car train.

These pictures show the platform.

Note.

  1. There would appear to be space on the North side of Platform 5 to install another platform, if one should be needed.
  2. It appears from the Google Map, that Platform 5 could take a four-car train.
  3. The platform is wide and spacious for passengers.
  4. I suspect a Fast Charge system of some sort could be installed in this platform.

As at Reading, trains can take around twenty minutes to turn back at Basingstoke, which would be ideal for a battery charge.

What Trains Could Work The Shuttle?

After South Western Railway‘s interim Managing Director; Mark Hopwood’s comments, that led me to write Converting Class 456 Trains Into Two-Car Battery Electric Trains, these trains must be a possibility.

I also think, that as both South Western Railway and Great Western Railway are both First Group companies, there won’t be too much argument about who supplies the trains for the shuttle.

CrossCountry Trains Between Reading And Basingstoke

CrossCountry will need to replace their Class 220 trains with electric or bi-mode trains soon, to meet the dates for decarbonisation.

The prime candidate must be a dual-voltage version of Hitachi’s Regional Battery Train, which could easily work the 15.5 miles between Reading and Basingstoke on battery power, after charging up on the electrification at both ends.

The trains could also be easily fitted with the ERTMS signalling equipment that will be required to go smoothly along the line.

Freight Trains Between Reading And Basingstoke

We might see this section of the UK rail network, electrified for freight, but as it would require lots of connecting electrification, I think it is more likely that freight locomotives will be powered by an alternative fuel like hydrogen or bio-diesel. This would cut electrification needs, but still reduce carbon emissions.

Freight locomotives are already being fitted with the required ERTMS signalling equipment.

 

Conclusion

I am absolutely sure, that there’s a technological solution in there, that can increase the number of trains through Bramley.

But diverting the road traffic and clossing the level crossing would appear to be difficult.

 

 

August 14, 2020 - Posted by | Transport | , , , , , , , , ,

1 Comment »

  1. […] Chord Re-Opening of Camberwell Station Unlocking Capacity And Services Through Bramley (Hants) Aston Rowant Extension Of The Chinnor Railway Carshalton Beeches Step-Free […]

    Pingback by Beeching Reversal: Fifty Disused Rail Lines On Track To Reopen « The Anonymous Widower | August 15, 2020 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.