Testing Begins On Midland Main Line Electrification

The title of this post, is the same as that of this article on Rail Magazine.

  • From the article, it looks like the first part of mechanical testing has been completed as planned and unpowered pantograph runs have been performed at up to 110 mph.
  • It does seem to me, that this thirty  miles of electrification has avoided the troubles that have plagued similar projects in recent years.

Perhaps the good progress on this electrification, is making the government think again about early electrification of all of the  Midland Main Line

In Hopes Rekindled Of Full Midland Main Line Electrification. I showed how battery electric Class 810 trains would be able to work the route.

This was my conclusion of that earlier post.

It appears that both the Nottingham and Sheffield services can be run using battery electric Class 810 trains.

  • All four diesel engines in the Class 810 trains would need to be replaced with batteries.
  • The route between Clay Cross North Junction and Sheffield station, which will be shared with High Speed Two, will need to be electrified.
  • Charging facilities for the battery electric trains will need to be provided at Nottingham.

On the other hand using battery electric trains mean the two tricky sections of the Derwent Valley Mills and Leicester station and possibly others, won’t need to be electrified to enable electric trains to run on the East Midlands Railway network.

Will it be the first main line service in the world, run by battery electric trains?

There was one thing, that wasn’t available, a month ago, when I wrote that post – A charging system for battery electric trains, that could be installed at Nottingham.

In Vivarail’s Plans For Zero-Emission Trains, I report on Adrian Shooter’s plans for Vivarail, which are outlined in a video by Modern Railways.

Ar one point he says this   see about Vivarail’s Fast Charge system.

The system has now been given preliminary approval to be installed as the UK’s standard charging system for any make of train.

I may have got the word’s slightly wrong, but I believe the overall message is correct.

So could we see a Hitachi Class 810 train using Vivarail’s patented Fast Charge system at Nottingham?

In Interview: Hitachi’s Nick Hughes On Driving Innovation In Rail Propulsion, Nick Hughes of Hitachi is quoted as saying.

Rail is going to become increasingly digitised and integrated into other sectors involved in smart cities, mobility-as-a-service and flexible green grid. Therefore, Hitachi Rail won’t be able to stay at the forefront of innovation by its self. This is why we are focused on building partnerships with other like-minded, innovative, clean tech companies like Hyperdrive Innovation, Perpetuum and Hitachi group companies such as Hitachi ABB.

Does Vivarail fit that philosophy? In my view, it does!

This Hitachi infographic gives the specification of their Regional Battery Train.

Note.

  1. The range on battery power is 90 km or 56 miles at up to 100 mph.
  2. Class 810 trains could be converted to battery electric trains by replacing the diesel engines with batteries.
  3. As the electrification has reached Kettering. there is only 55 miles between London St Pancras and Nottingham without electrification.

I could see Class 810 trains running between St. Pancras and Nottingham on delivery, provided the following projects have been completed.

  • Hitachi have been able to give the Class 810 trains a range of say 60 miles on batteries.
  • Hitachi have modified their trains, so they can be recharged by a Vivarail Fast Charge system in fifteen minutes.
  • Vivarail have installed a Fast Charge facility at Nottingham station.

Network Rail are planning to extend the electrification from Kettering to Market Harborough, which would reduce the distance without electrification to under 50 miles. This would make running battery electric trains between London St. Pancras and Nottingham even easier.

Expanding The Network

If I am putting two and two together correctly and Hitachi have turned to Vivarail to provide a charging system or a licence for the use of the technology, I am sure, it would be possible to create a comprehensive network of battery electric trains.

Consider.

  • Hitachi should be able to squeeze a sixty mile range at 90-100 mph from a battery-equipped Class 810 trains.
  • Market Harborough and Derby are about 47 miles apart.
  • Derby and Sheffield are about 36 miles apart
  • Sheffield and Leeds are about 48 miles apart
  • Corby and Leicester are about 41 miles apart.

Vivarail Fast Charge systems at Derby, Leicester and Sheffield would enable the following routes to be run using battery electric trains.

  • London St. Pancras and Sheffield via Derby – Fast Charging at Derby and Sheffield
  • London St. Pancras and Leeds via Derby and Sheffield – Fast Charging at Derby and Sheffield
  • London St. Pancras and Sheffield via the Erewash Valley Line – Fast Charging at Ilkeston (?) and Sheffield
  • London St. Pancras and Leicester via Corby – Fast Charging at Leicester

Note.

  1. The only extra electrification needed for the initial network would be between Kettering and Market Harborough.
  2. The Class 810 trains would all be identical.
  3. The Class 810 trains might even be built and delivered as battery electric trains
  4. Trains would also charge the batteries between London St. Pancras and Market Harborough, between London St. Pancras and Corby. and between Leeds and Wakefield Westgate.

The network can be extended by adding more electrification and Fast Charge systems.

Conclusion

The technologies of Hitachi and Vivarail seem complimentary and could result in a fully electric main line train network for East Midlands Railway.

 

 

October 19, 2020 - Posted by | Transport | , , , , , , , , ,

1 Comment »

  1. https://www.focustransport.org/2020/10/rail-operations-group-assists-with-dats.html gives some further info, and states: “It’s planned that electric trains should start running north of Bedford from next May, although Rail Minister Chris Heaton-Harris has previously suggested that trains could start running earlier once the testing is complete.”

    Comment by Peter Robins | October 28, 2020 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.