New ‘HS3’ Link To Yorkshire Proposed By Thinktank After Region’s HS2 Axe

The title of this post, is the same as this article in the Yorkshire Post.

This is the introductory paragraph.

A new “HS3” high-speed rail line between Yorkshire and the Nottinghamshire town of Newark could help make up for the loss of the HS2 eastern leg from Yorkshire, a report by transport think-tank; Greengauge 21 has suggested.

There is also this map from Greengauge 21.

I clipped my copy of the map from this report on Greengauge 21, which is entitled East, West, North And South.

Note.

  1. As in the Integrated Plan For The North And Midlands, Derby, Nottingham and Sheffield have direct connections to London via High Speed Two.
  2. The Derby leg is extended to Sheffield via the existing Midland Main Line.
  3. The Nottingham leg is extended to Newark, where it joins the East Coast Main Line.
  4. A new High Speed Line, which is shown in white and labelled HS3 links Newark to the East Coast Main Line and the line between Leeds and York at a new triangular junction South of Colton Junction.
  5. Part of the current route between Doncaster and Colton Junction is the Selby Diversion, which according to Wikipedia was built for speeds upward of 140 mph.
  6. The route splits in the region of Colton Junction with the Western leg going to Leeds and Bradford and he Northern leg going to York and Newcastle.

I feel this is a better plan than the previous one from High Speed Two.

  • It adds Bradford, Derby and Nottingham to the High Speed Two network.
  • There is a connection to Birmingham and possibly the South West and Wales.
  • The East Coast Main Line is effectively four-tracked between Newark North Gate and York.

I have a few thoughts.

Colton Junction

This junction will feature a lot in this post, so I had better explain where it is.

The Selby Diversion was built in the 1980s to create a new route, which avoided the newly-discovered Selby coalfield.

Colton Junction is about six miles South of York and is at the Northern end of the Selby Diversion.

This Google Map shows the junction.

Note.

  1. The East Coast Main Line going between South-West and North-East across the map.
  2. The railway going North-East leads to York.
  3. The village of Colton is at the top of the map.
  4. Colton Junction is South of the village, where the East Coast Main Line splits.
  5. The line going South-West is the route without electrification to Leeds, used by TransPennine Express and others.

The line going South is the Selby Diversion, used by all trains on the East Coast Main Line.

East Midlands Hub Or East Midlands Parkway

Some reports indicate that a new Birmingham and Nottingham High Speed Line will go via East Midland Parkway station.

  • East Midland Parkway is a fully-functioning four-platform station.
  • It is already operating.
  • There will soon be a large brownfield site next door, when the coal-fired Radcliffe-on-Soar power-station is demolished.
  • It has connections to Nottingham and Sheffield via Derby and Chesterfield.
  • Platforms are probably long enough to handle splitting and joining.
  • An advanced passenger shuttle could be built to East Midlands Airport.

This map from High Speed Two shows the route of the Eastern leg of High Speed Two, where it passes East Midland Parkway station and Radcliffe-on-Soar power-station.

Note.

  1. The coloured line is the route of High Speed Two.
  2. Red indicates viaduct
  3. Yellow indicates cutting.
  4. Green indicates green tunnel.
  5. There is a curious clover-leaf shape  to the East of High Speed Two.

This Google Map shows the same area.

Note

  1. The River Soar and Remembrance Way can be picked out on both maps.
  2. The Midland Main Line runs North-South in the Google Map and passes through East Midlands Parkway station.
  3. It is possible to pick out the curious clover leaf shape to the North of the railway station, where the rail line goes into the power station.
  4. Returning to the High Speed Two map it is possible to pick out the railway and power stations.

This map from High Speed Two shows the route of the Eastern leg of High Speed Two, to the South-West of East Midlands Parkway station.

Note.

  1. The coloured line is the route of High Speed Two.
  2. Red indicates viaduct.
  3. East Midlands Parkway station is in the North-East corner of the map.
  4. The Midland Main Line runs North-South down the Eastern side of the map.

Could the route of High Speed Two be adjusted so that it runs through East Midlands Parkway station?

This Google Map shows a similar area as the second High Speed Two map.

With the exception of the village of Radcliffe-on-Soar, there aren’t many, who would get in the way of the development of a connection between High Speed Two and the Midland Main Line to the South of East Midlands Parkway station.

  • High Speed Two crosses Remembrance Way  in the South West corner of the map, where there is a junction with the M1 and runs diagonally across the map.
  • High Speed Two could probably sneak up the North side of Remembrance Way.
  • The station might need to be moved to the North a bit to give space.
  • The map also shows the space to the East, that will be created with the demolishing of the power station.

Developing East Midlands Parkway instead of East Midlands Hub could be the more affordable option.

High Speed Two’s Eastern Leg Services

This graphic shows High Speed Two’s services before the Eastern Leg was deleted.

Note.

  1. Western Leg services are to the left of the vertical black line.
  2. Eastern Leg services are to the right of the vertical black line.
  3. Blue indicates a full-size service.
  4. Yellow indicates a Classic-Compatible service.

Destinations on the former Eastern Leg get the following services.

  • Chesterfield – 1 tph
  • Darlington – 2 tph
  • Durham – 1 tph
  • East Midlands Hub – 7 tph
  • Leeds – 5 tph
  • Newcastle – 3 tph
  • Sheffield – 2 tph
  • York – 6 tph

Note.

  1. Two trains will split and join at East Midlands Hub or East Midlands Parkway. But given what I said earlier, the split will take place at East Midlands Parkway.
  2. Derby, Chesterfield and Sheffield could get two tph.
  3. If the pattern of the currently proposed High Speed Two service is followed, that would mean that 5tph to Leeds and four tph to York and further North would go through Nottingham.

I suspect that there could be a reduction in either High Speed Services on the Eastern Leg or on the East Coast Main Line.

Splitting And Joining At East Midlands Parkway

Consider.

  • All Northbound services on High Speed Two and the Midland Main Line pass through East Midlands Parkway station in the same direction.
  • All Southbound services on High Speed Two and the Midland Main Line pass through East Midlands Parkway station in the same direction.
  • The four platforms at East Midlands Parkway station will give a lot of flexibility.

If trains split and joined at East Midlands Parkway, there would be no need to reverse to serve Derby, Chesterfield and Sheffield. I can’t see how this could be performed at East Midlands Hub without the Sheffield train reversing. This probably explains why in the original plans for High Speed Two, Sheffield and Chesterfield had their own spur and Derby was not served directly by High Speed Two.

The redesign in the Integrated Rail Plan For The North And Midlands, which abandons the Sheffield spur, probably reduces the costs significantly.

Nottingham

Nottingham will be an extremely busy station with these services running through.

  • High Speed Two – 2 tph – Birmingham Curzon Street and Leeds HS2 via Nottingham – Full-Size – 200 metres
  • High Speed Two – 1 tph – Birmingham Curzon Street and Newcastle via Nottingham, York, Darlington and Durham – Classic-Compatible – 200 metres
  • High Speed Two – 1 tph – London and Leeds HS2 via Nottingham – Classic-Compatible – 200 metres
  • High Speed Two – 1 tph – London and Leeds HS2 via Nottingham – Full-Size – 400 metres
  • High Speed Two – 1 tph – London and Leeds HS2 via Birmingham Interchange and Nottingham  – Full-Size – 400 metres
  • High Speed Two – 1 tph – London and York via Nottingham – Classic-Compatible – 200 metres
  • High Speed Two – 1 tph – London and Newcastle via Nottingham and York – Classic-Compatible – 200 metres
  • High Speed Two – 1 tph – London and Newcastle via Nottingham, York and Darlington – Classic-Compatible – 200 metres
  • East Midlands Railway – 1 tph – London St. Pancras and Nottingham via Kettering, Market Harborough and Leicester  – Class 810
  • East Midlands Railway – 1 tph – London St. Pancras and Nottingham via Kettering, Market Harborough, Leicester, Loughborough, East Midlands Parkway and Beeston – Class 810
  • East Midlands Railway – 1 tph – Liverpool Lime Street and Norwich via Chesterfield, Alfreton, Nottingham, Grantham, Peterborough and several other stations – Class 158/170
  • East Midlands Railway – 1 tph – Crewe and Newark Castle via Nottingham and several other stations – Class 158/170
  • East Midlands Railway – 1 tph – Leicester and Lincoln via East Midlands Parkway, Attenborough, Beeston, Nottingham, Carlton and several other stations – Class 158/170
  • CrossCountry – 1 tph – Cardiff Central and Nottingham via Derby, Spondon, Long Eaton, Beeston and several other stations – Class 170
  • CrossCountry – 1 tph – Birmingham New Street and Nottingham via Derby – Class 170
  • Midlands Connect – 1 tph – Leeds and Bedford via Nottingham and Leicester – Classic-Compatible – 200 metres

Note.

  1. With High Speed Two services London means London Euston and Old Oak Common.
  2. Two High Speed Two services do not stop in Nottingham
  3. With several of these routes I have only put in a few intermediate stations to show the routing of the train at Nottingham.

These services total up to  twelve tph going through Nottingham and four tph terminating at Nottingham from London St. Pancras and Birmingham New Street.

Nottingham station would need to be able to handle the following with respect to through trains.

  • A train every five minutes.
  • Some trains would be 400 metres long.

But there is plenty of space in Nottingham station and High Speed Two’s digital signalling will be able to handle 18 tph.

Nottingham And Newark

The Nottingham and Lincoln Line between Nottingham and Newark appears from my helicopter to be fairly straight.

  • The line is double track.
  • There are eight stations between Nottingham and the East Coast Main Line.
  • The maximum speed of the line is 70 mph.
  • It is 18.1 miles between Nottingham and the East Coast Main Line.
  • I suspect that it could be upgraded to a 100 mph between Nottingham and the East Coast Main Line.

Typical services in tph will be the same as at Nottingham, which is 12 tph.  But there are also occasional freight trains and Peak services to and from London St. Pancras.

With digital signalling on this relatively-simple section, if it were to be fitted with High Speed Two digital signalling, that will have to be able to handle 18 tph, what would you do with the other six tph?

  • Some paths would be used to handle the occasional freight trains and Peak services to and from London St. Pancras.
  • Some of the capacity could also be used by the stopping trains.

The amount of traffic would probably be less than on the Great Eastern Main Line, which is capable of 100 mph running.

Newark

Newark has the notorious flat crossing, where the Nottingham and Lincoln Line crosses the East Coast Main Line.

This Google Map shows the track layout at Newark.

Note.

  1. Newark Castle station is on the Nottingham and Lincoln Line and is in the South-West corner of the map.
  2. Newark North Gate station is on the East Coast Main Line and is in the South-East corner of the map.
  3. The two rail lines run diagonally across the map and cross near the top of the map towards the right.
  4. Nottingham lies in a South-Westerly direction from this map.
  5. Lincoln lies in a North-Easterly direction from this map.
  6. Doncaster, Leeds and York lie in a North-Westerly direction from this map.
  7. Grantham, Peterborough and London lie in a South-Easterly direction from this map.

Under the Greengauge 21 plan, trains will need to run in the following directions.

  • In both directions on the East Coast Main Line.
  • In both directions on the Nottingham and Lincoln Line.
  • Coming South on the East Coast Main Line, trains will need to be able to go towards Nottingham on the Notting and Lincoln Line.
  • Coming from Nottingham on the Nottingham and Lincoln Line, trains will need to be able to go Leeds and York on the East Coast Main Line.

It would be a complicated set of junctions and flyovers for a railway, but not impossible to design and build.

Newark North Gate And Colton Junction

I’ll repeat the map I showed earlier, that shows the routes between Newark North Gate and Colton Junction.

Note.

  1. The current East Coast Main Line via Doncaster is shown dotted in black.
  2. The proposed new route, which is called HS3 is shown in white.
  3. Colton Junction is at the Northern end of the new track.

I suspect that the new route would be built to the same operating standards as High Speed Two.

  • Operating speed of 205 mph.
  • High specification electrification.
  • Signalling capable of handling 18 tph.
  • All classic and Classic-Compatible high speed trains would be able to take both routes, but would be limited to 125 mph or 140 mph with in-cab digital signalling on the East Coast Main Line.
  • Trains needing to call at Doncaster and freight trains, would use the East Coast Main Line.
  • Full-Size High Speed Two trains would generally use the new high speed line.

It looks to be a good way to increase capacity between Newark and Leeds and York.

Timings Between Newark North Gate And Colton Junction

Consider.

  • Newark North Gate and Colton Junction are 63 miles apart.
  • Trains take 39 minutes.
  • There is a stop at Doncaster.

This is an average speed of 97 mph.

If trains went non-stop on the new ‘HS3’ route, there would be these timings at different average speeds.

  • 100 mph – 37.8 minutes
  • 125 mph – 30.2 minutes
  • 140 mph – 27 minutes
  • 160 mph – 23.6 minutes
  • 180 mph – 22.2 minutes
  • 200 mph – 18.9 minutes

Note.

  1. I have assumed the distance is the same as via the East Coast Main Line.
  2. I have made no allowance for longer acceleration and deceleration times to and from higher line speeds.
  3. High Speed Two Classic Compatible Trains could handle up to 205 mph if the track could support it.

It does appear that savings of upwards of fifteen minutes could be possible on all services that could use the new route.

Both East Coast Main Line and High Speed Two services would get time savings.

Colton Junction And York

As I saw and wrote about in London To Edinburgh On Lumo, the route between Leeds and York is being fully electrified.

The East Coast Main Line is already fully electrified, so I doubt the connection between ‘HS3’  and York will be difficult.

Trains will just exchange a 205 mph track for the East Coast Main Line’s 125 mph or 140 mph with in-cab digital signalling.

Colton Junction And Leeds

This High Speed Two Map shows the original planned track layout for High Speed Two to the East of Leeds.

Note.

  1. The large blue dot indicates Leeds HS2 station.
  2. The orange lines indicate the new high speed tracks for High Speed Two.
  3. The track going North-East is High Speed Two’s connection to the East Coast Main Line in the area of Colton Junction.
  4. The track going South is the Eastern Leg of High Speed Two to East Midlands Hub station, which has now been deleted.

Would it be possible to modify the route of High Speed Two to create a link between the Norther end of Newark and Colton Junction High Speed Line, which Greengauge 21 called HS3 and the proposed Leeds HS2 station?

This map from High Speed Two shows the area, where the High Speed Two Lines were originally proposed to run.

Note.

  1. The village of Swillington to the East of the proposed route of the Eastern Leg of High Speed Two.
  2. Junction 45 of the M1 in the North-West corner of the map.
  3. The River Aire and the Aire and Calder Navigation Canal on the route of High Speed Two to Leeds HS2 station.

This Google Map shows the same area.

I’m no expert, but I do believe that it would be possible to create a chord to allow trains to access Leeds HS2 station from the York direction.

I would suspect that High Speed Two looked seriously at this chord, as it would enable the proposed Leeds HS2 station to have services to York, Newcastle and Edinburgh using the East Coast Main Line.

But there is one problem with this route – It doesn’t allow and easy solution to serve Bradford.

This map from High Speed Two, shows the Leeds HS2 station and the last bit of the approach from the East.

This article on the Architects Journal is entitled Foster + Partners behind designs for Leeds HS2 Station. The article shows.

  • Leeds HS2 station is being designed as a terminal station.
  • It shares a common concourse with the current Leeds station.

It appears from the pictures in the Architects Journal article, that passengers would have to change trains to get to Bradford.

The alternative would be for trains into Leeds to take the route used by Northern’s service between York and Blackpool North, which goes via Church Fenton, Micklefield, East Garforth, Garforth, Leeds, Bramley, New Pudsey and Bradford Interchange.

But judging by the times of other services, Colton Junction and Leeds would take over twenty minutes and it would be a further twenty minutes to Bradford Interchange.

I can’t think that this is a viable alternative.

Conclusion

I am led to the conclusion, that to get a decent service into Leeds from the East using Greengaige 21’s ‘HS3’ between Newark and Colton junction, would necessitate the building of a new Leeds HS2 station and a new route between the new station and Colton junction.

December 7, 2021 - Posted by | Transport/Travel | , , , , , , , , ,

8 Comments »

  1. the latest GG21 publication reiterates what is in http://www.greengauge21.net/wp-content/uploads/GG21_Meeting_Rail_Needs_Of_The_Midlands_And_North_A4P_FINAL.pdf (see p46). The proposed ‘HS3’ link is to Temple Hirst Jcn, and would branch to Lds at Hambleton.

    Comment by Peter Robins | December 7, 2021 | Reply

  2. Thanks for that. I couldn’t find much about the route, but there’s plenty of open land. I suspect no-one wanted to build houses over a coal-field with all the problems of subsidence that could bring.

    Comment by AnonW | December 7, 2021 | Reply

    • yes, essentially it moves the original Leeds HS2 branch further E to the E of Doncaster. As they point out, this is largely flat, and considerably less populated than the original, which had to weave around some quite densely populated areas of S Yorks. It also gives extra flexibility, and if the Pudsey line is electrified, Bradford trains could run through Lds to Hambleton and turn S. I think it’s a good idea.

      The Union Connectivity Review recommended bypasses of York and Durham too. Combine those, and you should cut quite some time off Scotland-London/Brum/E Midlands travel times.

      Comment by Peter Robins | December 7, 2021 | Reply

      • Should we also consider that if trains terminated in a platform at Bradford, this might take pressure of the crowded Leeds station.

        Perhaps the new Bradford station in the market might be a good idea. Trains would also not have to reverse in Leeds, which slows down the service.

        Comment by AnonW | December 7, 2021

      • The IRP gives funding to a Leeds Metro, which should take pressure off Lds by moving some local traffic to the streets. We will see. I think it’s pretty clear that there’s no funding atm for a new Bradford stn.

        Comment by Peter Robins | December 7, 2021

  3. […] New ‘HS3’ Link To Yorkshire Proposed By Thinktank After Region’s HS2 Axe, I showed that a short length of faster by-pass line could give decent ties […]

    Pingback by Are Short Lengths Of High Speed Line A Good Idea? « The Anonymous Widower | December 8, 2021 | Reply

  4. How about reviving Virgin’s ECML plan of 2000?I never liked the idea of HS2 east because of the long diversion via Birmingham.

    Comment by hugh | December 9, 2021 | Reply

  5. It is perhaps worth noting that the current eastward route from Leeds was designed and engineered from Neville Hill to Micklefield as a four track capable route although only ever carrying two. Church Fenton to Colton junction is already four track. OK it’s never going to be 300km/h compatible but upgrades to the current route might be more quickly delivered than HS3 and address capacity constraints over the section to York. The major problem here is the slow approach/exit busy Leeds station. Perhaps a rebuilt Marsh Lane station to handle the local terminators? Tram connector to “new” station & city? So just like Birmingham.

    Comment by Fenline Scouser | December 9, 2021 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: