Soham Station’s Inaugural Year A Soaring Success

The title of this post, is the same as that of this article on Rail Technology Magazine.

This is the first paragraph.

Soham station has seen healthy and consistent passenger usage over its first year since opening to the public, seeing almost 50,000 journeys starting or finishing there, according to Greater Anglia’s figures.

I took these pictures, when the station opened.

I think Soham station is a good design of a single-platform station.

  • It’s a short walk from car park or drop-off point to the platform.
  • There is adequate car parking.
  • There is a shelter.

The station has also been built, so that it can be expanded.

These are my thoughts.

A Service To Cambridge

Soham station probably needs a train service to Newmarket and Cambridge, as it already has a two-hourly service to Bury St. Edmund’s, Ely and Ipswich and Peterborough.

Wikipedia says this.

There are no current plans for direct services to Cambridge, but the CPCA has expressed support for the idea in a future phase of the project. Mayor James Palmer said “the delivery of Soham station gives us a much stronger case to go to Government and Network Rail and lobby for the reinstating of the Snailwell loop which will provide a direct service between Ely, Soham, Newmarket and Cambridge”

This map from OpenRailwayMap shows the Snailwell Loop.

Note.

  1. The triangular junction in the middle of the map,
  2. The line from the junction leading East goes to Bury St. Edmunds and Ipswich.
  3. The line from the junction leading North goes to Soham, Ely and Peterborough.
  4. The line from the junction leading South goes to Newmarket and Cambridge.
  5. The Western side of the junction was removed by British Rail.

It would appear that by reinstating the Western side of the junction, a service between Ely and Cambridge via Soham and Newmarket could be run.

There are proposals for new stations in this area and given the need for comprehensive commuter services into Cambridge this Ely and Cambridge service could develop considerably.

The simplest service pattern would be

  • Peterborough via Ely, Manea, March and Whittlesea.
  • Ely non-stop.
  • Ipswich via Bury St. Edmunds and Stowmarket.
  • Cambridge via Newmarket and Dullingham.

All trains would be one train per two hours (tp2h).

Snailwell Junction And Cambridge

There could be problems between Snailwell junction and Cambridge, as the line is mainly single-track and it would need to handle the following trains.

Ipswich and Cambridge – 1 train per hour (tph)

Ely and Cambridge – 1 tp2h

Sundry freight trains.

In Roaming Around East Anglia – Newmarket Station, I wrote this about the plans of the East West Rail Consortium in the area.

In this document on the East-West Rail Consortium web site, this is said.

Note that doubling of Warren Hill Tunnel at Newmarket and
redoubling between Coldham Lane Junction and Chippenham Junction is included
in the infrastructure requirements. It is assumed that most freight would operate
via Newmarket, with a new north chord at Coldham Lane Junction, rather than
pursuing further doubling of the route via Soham.

So would it be possible to create a double-track railway through Newmarket station?

In the related post, I came to this conclusion.

Newmarket can benefit from East West Rail, but the two parties must agree objectives that don’t cause problems for the other.

But I do think, that Newmarket will not welcome the building of a double-track railway through the town.

The Proposed A14 Parkway Station

December 9, 2022 Posted by | Transport/Travel | , , , , , , , , | Leave a comment

Soham Station Aims For December 2021 Opening

This article on Rail Technology Magazine is entitled Soham Set To Benefit From New Station After 56 years Without.

Work only started on Soham station earlier this year, so this paragraph is a bit of a surprise.

The completion of the work means that from December, Greater Anglia’s Ipswich to Peterborough service will finally be able to stop at Soham once more, better connecting the population.

The work referred to is changes to the signalling to allow services to call at the new Soham station.

It certainly appears that the station is being built at a canter!

I have some thoughts on the station.

Station Location

This Google Map shows the town of Soham.

Note.

  1. The railway between Ely and Ipswich running North-South at the Western edge of the map.
  2. Station Road connecting the town centre to the railway.
  3. Looking at the map to a large scale, it certainly appears that construction has started, as dark green portacabins and red and white barriers ae visible.

This Network Rail visualisation shows the proposed station.

Note.

  1. The visualisation is looking to the East.
  2. Ely and Peterborough are to the left.
  3. Bury St. Edmunds and Ipswich are to the right.
  4. The footbridge is wide enough to cross a double-track, although the route is currently only single-track at this point.
  5. There is just a single platform on the town side of the track.

It appears to be a simple design, that possibly could speed the construction.

Station Design

This Network Rail visualisation is a closer view of the proposed station.

Note.

  1. The turning circle and the carpark on the town (Eastern) side of the station can be clearly seen.
  2. The single platform will be 100 metres long and will be able to accommodate a four-car Class 755 train, which is 80.7 metres long.
  3. It appears that there is a concrete wall at the back of the platform. Is this to protect passengers from the sometimes-biting winds of the Fens or the swirling air currents generated by passing freight trains.

The station and footbridge are future proofed for a possible second platform and lifts.

Services

Currently, Greater Anglia runs a train between Ipswich and Peterborough every two hours, although this was promised to be doubled in frequency at some time in the future.

Times to various stations are as follows.

  • Ipswich – 48 minutes
  • Bury St. Edmunds – 19 minutes
  • Ely – 9 minutes
  • Peterborough – 50 minutes

These times are from Real Time Trains, which already acknowledges the station.

Note that to get to the important city of Cambridge passengers will need to change at either Bury St. Edmunds or Ely.

In the future there are two ways that the connection between Soham and Cambridge can be improved.

Reinstatement Of The Warren Hill Junction and Snailwell Junction Chord

This Google Map shows the layout, where the Ely and Ipswich Line and the Cambridge Branch Line join to the North of Newmarket in a triangular junction.

Note.

  1. The A14 runs across the top of the map.
  2. The Ely and Ipswich Line runs in a curve to the South of the A14 and the British Racing School.
  3. The former Snailwell junction was to the South of the British Racing School and was the Northern point of the triangular junction.
  4. Chippenham junction is the Eastern point of the triangular junction and is where the Ely and Cambridge lines join.
  5. The former Warren Hill junction was at the South close to the stables of Godolphin and John Gosden and was the Southern point of the triangular junction. From Warren Hill junction the railway runs through the Warren Hill tunnel to Newmarket station and ultimately to Cambridge.

If the chord were to be reinstated between Snailwell and Warren Hill junctions, it would be possible to run an hourly service between Soham and Cambridge via Dullingham and Newmarket.

The A14 Parkway Station

The A14 Parkway station is a proposal from the East West Railway.

  • It would be just to the East of Chippenham junction and would be served by both Greater Anglia’s services between Ipswich and Cambridge and Ipswich and Peterborough.
  • It would also be close to the major road junction, where the A11 and the A14 meet.
  • It would be a Park-and-Ride station.

I believe it could be a major factor in cutting road mileage in East Anglia, as drivers going to Cambridge from Ipswich, Norwich, a large area of North-East East Anglia and North Essex could find that using the A14 Parkway station an easier and faster route. But the A14 Parkway would need a frequent service to the soon-to-be-three main Cambridge stations.

A Soham and Cambridge service could reverse at the A14 Parkway station or by careful timetabling, passengers would be able to change trains in a minute or two.

Two Trains Per Hour Between Newmarket and Cambridge

An hourly service between Soham and Cambridge would add an invaluable second hourly service between Newmarket and Cambridge.

It would also fit in with the regular proposals to reopen stations at Six Mile Bottom, Fulbourn and Cherry Hinton.

 

August 31, 2021 Posted by | Transport/Travel | , , , , , , | 1 Comment

Roaming Around East Anglia – Freight Trains Through Newmarket

The East West Rail Consortium plan to change the route of freight trains to and from Haven Ports; Felixstowe, Harwich and Ipswich to the West of Kennett station.

In this document on the East-West Rail Consortium web site, this is said.

Note that doubling of Warren Hill Tunnel at Newmarket and
redoubling between Coldham Lane Junction and Chippenham Junction is included
in the infrastructure requirements. It is assumed that most freight would operate
via Newmarket, with a new north chord at Coldham Lane Junction, rather than
pursuing further doubling of the route via Soham.

How would these changes affect Newmarket and the horse-racing industry in the town?

How Many Freight Trains Are We Talking About?

This table shows the number of freight trains going through Kennett station on the 1st of March 2019.

  • 00  1  1
  • 01  1  0
  • 02  0  1
  • 03  2  1
  • 04  1  1
  • 05  1  1
  • 06  1  2
  • 07  1  1
  • 08  1  0
  • 09  1  0
  • 10  1  0
  • 11  0  0
  • 12  0  0
  • 13  2  2
  • 14  0  2
  • 15  1  1
  • 16  0  1
  • 17  1  1
  • 18  0  1
  • 19  1  1
  • 20  1  0
  • 21  1  2
  • 22  0  2
  • 23  0  0

In the table the first figure is the hour, the second figure is the number of freight trains going West and the third figure is the number of freight trains going East.

This gives a daily total of eighteen trains going West and twenty-one trains going twenty-one trains going East.

But these figures will increase!

At present, Network Rail are adding a passing loop on the Felixstowe Branch Line. This article on Rail Magazine is entitled £60.4m Felixstowe Branch Upgrade Under Way and says this about the upgrade.

Installing the new line will create capacity for up to ten additional freight trains, each the equivalent of 76 lorries.

Not all will come via Kennett, as some will go via London.

The Port of Felixstowe will get larger and other improvements on the route across Suffolk will increase the number of freight trains passing through Kennett station.

I estimate that it is very likely that in a few years there will be two trains per hour (tph) in both directions for every hour of the day.

Rerouting The Trains Through Newmarket

Currently, these freight trains go via Ely, but the plan of the East West Rail Consortium would be to reroute all these freight trains through the Warren Hill tunnel and Newmarket station.

I suspect the reasons for the change of route could include the following.

Accessing The East West Rail Link From Newmarket Is Easy And Quick

If as expected the East West Rail Link joins the London-Cambridge Line just South of Cambridge South station, then the trains would run through Dullingham, Cambridge and Cambridge South stations, when running between the East West Rail Link and Newmarket station.

The East West Rail Link Will Be An Efficient Railway

Drive on a new motorway and the curves are smooth with relaxed gradients.

A new railway will be like that too and less energy will be used to power trains along its length.

Increasing the Capacity Through Ely Is Difficult

There is a very complicated track layout at Ely and increasing the number of trains might be difficult or very expensive.

Freight Trains Will Use The East West Rail Link To Avoid London

Take going between the Haven Ports and Bristol or South Wales.

Currently, these trains tend to go via London and in a couple of years will have to share tracks with London’s intensive Crossrail network between Acton Main Line and Reading stations.

Using the East West Rail Link, the trains would join the Great Western Main Line at Didcot, a few miles West of Reading.

How many services will use the East West Rail Link to by-pass London?

Freight Trains Will Use The East West Rail Link To Get To The West Coast Main Line

Currently, these trains either go via London or take the slow cross-country route via Peterborough to Nuneaton for the West Coast Main Line.

If they use the East-West Rail Link, they can join the West Coast Main Line at Bletchley.

The East-West Rail Link Will Be An Important Freight Link

I think that as the years pass and more freight terminals are created, we will see more freight trains using the East-West-Rail-Link and many of these trains will go through Newmarket.

What Problems Would The Rerouting Create In Newmarket?

I can see these problems.

Noise And Vibration

Four freight trains per hour will create a lot of noise and vibration as they pass through.

Frightening The Horses

This Google Map shows a corner of the gallops at Newmarket.

Note how the railway from the East splits into two, to the West of the band of trees running down the map.

  • The top branch curves away to the North and goes through Soham to Ely.
  • The bottom branch curves away to the South and goes through Warren Hill Tunnel to Newmarket station and then on to Cambridge.

Alongside, the Southern route is the Al Bahatri all-weather gallop, which is an important facility for training racehorses. It can just be picked out as a sand-coloured line.

Currently, nearly all the freight trains take the Northern route to Ely, keeping them away from the Al Bahatri.

But, if the main freight route was through the town, as planned by the East West Rail Consortium, then at least four freight trains per hour would run alongside the gallop. There could also be four passenger trains per hour.

Railway Electrification

It is unlikely, that the railway through Newmarket will be electrified, but under a different government, this could happen.

It might add another dimension to disturbance through the town, as you get pantograph noise and occasional sparks and flashes. I don’t know how horses will react, but from my own experience years ago, they do react to electrical fields.

The Rail Freight Industry

Look at most freight trains on the UK’s railways and the locomotive on the front, is a noisy, smelly and polluting Class 66 or Class 70 locomotive.

You’ll see these American imports, which don’t meet the latest emission regulations, hauling freight trains, even when there are overhead wires for electric haulage.

Why?

Because rail freight companies are so driven by accountants, that they can’t be bothered to obtain more modern diesel locomotives, that are quieter, more powerful and less polluting.

The picture shows a modern Class 68 locomotive at Stratford. These are quieter and meet most of the noise and emission regulations.

Mitigating The Problems

I’ll deal with various methods, that could be used, starting with the easiest.

A Level Railway Through The Town

It looks like the Victorian engineers, who built the railway through the town, built it as level as possible, so that steam locomotives didn’t have to work so hard in the Warren Hill Tunnel, which I don’t think has a chimney for smoke.

Modern engineers will ensure that the railway is as level as possible, with gentle gradients and curves all the way between Kennett and Dullingham stations.

Passenger Trains With Batteries

Greater Anglia’s new Class 755 trains are powered by both overhead electrification and onboard diesel engines. The latter sit in a power pack in the middle of the train.

Not having seen or heard one of these Swiss-built trains in the metal, I can make no comment as to the noise and vibration of these trains, but they should be quieter than the current three-car Class 170 trains.

It does appear that passenger trains built in the last years are much quieter, as they are much more aerodynamically correct and slippery, so they generate less noise.

The new trains have also been ordered for the South Wales Metro. But the Welsh trains will additionally be fitted with batteries to avoid some difficult electrification in the Valleys.

So if the passenger trains prove to be noisy through the town, which I doubt they will be, there will be the option of adding batteries to avoid the use of diesel power.

It is my belief, that technology will ensure that passenger trains will not be a problem.

More Environmentally-Friendly Freight Locomotives

As I said earlier, smelly, noisy and polluting freight locomotives are a big problem.

This is not just a problem for places like Newmarket with special circumstances, but on railways like the London Overground and those in Central Birmingham, Leeds and Manchester,, where suburban electric railways have to accommodate heavy rail freight.

The railway locomotive manufacturers have designed solutions for the problem in recent years.

Stadler, who are an innovative Swiss company have started to manufacture a Class 93 locomotive, which can run on diesel, electric and/or battery power. I’m fairly sure, that one of the design goals of this locomotive is to be able to haul a heavy freight train between Felixstowe and Peterborough, using electric power where it is available and a mix of diesel and battery at other times.

At Newmarket if the new double-track was well-designed and almost level, I suspect that a Class 93 locomotive could haul a train between Kennett and Dullingham stations on battery power.

Locomotives of this type should be compulsory on all freight routes through sensitive areas.

The government must legislate, as left to themselves the rail freight companies will sit on their hands and wallets.

One of the conditions of a double-track railway through Newmarket, should be that only locomotives that meet the latest noise, vibration and pollution standards, like the Class 93 locomotive should be allowed.

Quieter 100 mph Freight Trains

Karl Watts, who is a disruptive innovator and CEO of the Rail Operations Group, has bought the first ten Class 93 locomotives and intends to use them to haul 100 mph freight trains, where the routes allow.

On the electrified Great Eastern Main Line between Ipswich and London, the operating speed is 100 mph. But freight trains trundle up and down at 75 mph, thus slowing all of the passenger services.

Watts plans to use the Class 93 locomotives with new 100 mph container wagons to run freight trains at 100 mph on this and other routes, which would increase the freight and passenger capacity of the line.

New 100 mph freight wagons will be smoother, quieter and used through Newmarket at an appropriate speed would remove a large proportion of the noise and vibration.

Again, it would need investment from the freight companies.

However, modern freight trains hauled by modern hybrid locomotives like the Class 93 could significantly remove noise and vibration.

Lengthen Warren Hill Tunnel

A second bore will be dug to double-track the kilometre long Warren Hill Tunnel.

Some rail tunnels have been extended with covers and this technique might be possible at the Newmarket station end of the tunnel. The techniques exist, so that housing or other developments can be built on top of the railway.

Techniques like this not only suppress noise and vibration, but create much needed housing.

Acoustic Barriers

You see these a lot in Germany to reduce noise and vibration from railway lines in sensitive area, but rarely in the UK.

Conclusion

It will be difficult to put a double-track railway through Newmarket, but I believe that using modern rolling stock and some advanced construction, that a solution can be found.

Newmarket should dig in its heels and only accept the best to force rail freight companies to get their act together.

Government too, should enforce the current regulations on diesel locomotives, which most of the current locomotives do not meet.

March 4, 2019 Posted by | Sport, Transport/Travel | , , , , , , , , , , | 5 Comments

Roaming Around East Anglia – Newmarket Station

I went to Newmarket station for two reasons; to assess if the East West Rail Consortium’s plans for Newmarket were feasible and also to see a friend, who trains racehorses in the town, to tell him about the plans.

I should say, that I haven’t been to Newmarket for perhaps six years and it struck me that the town was much more crowded with traffic, with a lot of full car-parks. Around the station, there were lots of cars parked. How many were owned  by commuters going to Cambridge.

The Plans Of The East West Rail Consortium For Newmarket

In this document on the East-West Rail Consortium web site, this is said.

Note that doubling of Warren Hill Tunnel at Newmarket and
redoubling between Coldham Lane Junction and Chippenham Junction is included
in the infrastructure requirements. It is assumed that most freight would operate
via Newmarket, with a new north chord at Coldham Lane Junction, rather than
pursuing further doubling of the route via Soham.

So would it be possible to create a double-track railway through Newmarket station?

These are pictures that I took of the station.

It does appear that there is space for another track on the other side of the current track to the platform.

Newmarket station has some positive attributes.

  • It is in the centre of the town.
  • There is enough shelter and storage for cycles.
  • The platform will be long enough for Greater Anglia’s new four-car Class 755 trains.
  • There is a wide, spacious platform.

But these are outweighed by these drawbacks.

  • The vehicle access is terrible.
  • There is no Kiss-and-Ride facility.
  • Car parking is in the surrounding streets and as it’s free, the local roads will get choked, especially when Greater Anglia’s larger trains are introduced later this year.
  • The East West Rail Link will introduce a two trains per hour (tph) through the station.
  • Will the platform at Newmarket be long enough for the East West Consortium trains, which will be running between Ipswich and Oxford? Probably not!
  • There is no coffee kiosk, shop or toilets.

But above all it is not a destination station., that gives a good impression for visitors and tourists, who could make up a proportion of travellers.

The East West Rail Consortium are planning a parkway station on the A14 to the North of Newmarket and this will surely solve the problem of traffic and parking, that blocks the local streets,

But I believe that Newmarket needs a station, that will attract visitors.

My pictures, show the previous station building still standing next door to the current station.

  • This could be converted into a first-class station with excellent passenger facilities.
  • There could be a large taxi rank.
  • There could be passenger drop-off and pick-up facilities.
  • There is space for a bus connection to the race-course on race-days.
  • Limited car-parking of a short-term nature.
  • A two-hundred metre  long platform could be built to accommodate the longest-possible trains.

This Google Map, shows the combined site of the current and previous stations.

Both stations are effectively side-by-side, with the current station to the East.

The large area behind the stations is parking for horse-boxes during the numerous sales at Tattersalls. For much of the year, it is virtually empty.

I’m pretty sure, that with some management, the area could serve both its current purpose and as a forecourt to a landmark station,, that would enhance the town and the racing industry.

I don’t think that a second platform would be needed for the following reasons.

  • Adding the step-free access to the seond platform would cost a seven figure sum.
  • Commuters into Cambridge would be encounraged to use the proposed A14 Parkway station.
  • Probably only on race days, would there be large enough numbers of passengers to need to accommodate two trains in the station at the same time..

However space could be left, if a second platform were to be needed in the future.

Conclusion And Recommendations

The current Newmarket station is totally inadequate for the current service of one three-car train per hour in both directions.

Greater Anglia’s new Class 755 trains could be a car longer and will certainly attract more passengers to use Newmarket station, as new trains always do!

I feel that in the next couple of years, possible additional trains, more passengers and lack of car parking will create problems at Newmarket station.

I would recommend the following actions.

A14 Parkway Station

Work should start as soon as is practical for the A14 Parkway station, proposed by the East West Rail Consortium.

This station would have the following Greater Anglia services.

  • Peterborough and Colchester – 1 tph
  • Ipswich and Cambridge – 1 tph

These two services would give the following frequencies to these places.

  • Bury St. Edmunds – 2 tph direct
  • Colchester – 1 tph direct and 2 tph with a change at Ipswich
  • Diss – 1 tph with a change at Stowmarket
  • Ipswich – 2 tph direct
  • London – 1 tph with a change at Cambridge and 1 tph with a change at Ely
  • Newmarket – 1 tph direct
  • Norwich – 1 tph with a change at Cambridge, 1 tph with a change at Ely and 2 tph with a change at Stowmarket
  • Peterborough – 1 tph direct and 1 tph with a change at Cambridge
  • Stansted Airport – 2 tph with a change at Cambridge
  • Stowmarket – 2 tph direct

A14 Parkway station sitting at the junction of two of the busiest roads in East Anglia; the A11 and A14, and two important rail routes,would be one of the most important stations in the East.

The station could only be named after Ancient Britain’s most famous queen, who by repute once lived in the area.

Upgrade Newmarket Station

Hopefrully, the A14 Parkway station would ease the problems at Newmarket station and this would enable work to progress on the design of an upgraded Newmarket station, that would serve the town, the racing industry and the towns tourist attractions.

Improved Train Services To/From Cambridge

Once the East West Rail Link opens between Cambridge and Oxford, the current service between Ipswich and Cambridge, could eventually be replaced with a service between Manningtree and Oxford or possibly Reading, that calls at Ipswich, Stowmarket, Bury St. |Edmunds, A14
Parkway, Newmarket, Cambridge, Cambridge South, Bedford, Bletchley, Milton Keynes, Bicester, Oxford and several smaller intermediate stations.

The three Cambridge stations of Cambridge, Cambridge North and Cambridge South will also increasingly be connected to the surrounding stations like A 14 Parkway, Bury St. Edmunds, Cambourne, Ely, Kings Lynn, March, Newmarket and Peterborough. Services will be at a frequency of at least two tph, with some as high as four tph.

In addition, there could be new services to Haverhill and Wisbech.

Newmarket will get a share of these services and I wouldn’t be surprised to see these frequencies from Newmarket station to the three Cambridge stations.

  • Cambridge – 4 tph direct
  • Cambridge North – 2 tph direct and 2 tph with a change at Cambridge
  • Cambridge South – 2 tph direct and 2 tph with a change at Cambridge

Cambridge is becoming one of the most important cities in Europe and Newmarket can benefit by holding on to big sister’s skirts.

West Suffolk And London Services

If you look at the sizeable towns in Suffolk, the following ones that are rail connected, do not have a direct train service to London.

  • Beccles
  • Bury St. Edmunds
  • Felixstowe
  • Halesworth
  • Lowestoft
  • Newmarket
  • Sudbury
  • Woodbridge

Greater Anglia’s new Class 755 trains, will be running three trains per day, between Liverpool Street and Lowestoft, which will reduce this list to just.

  • Bury St. Edmunds
  • Felixstowe
  • Newmarket
  • Sudbury

If Felixstowe is discounted as it is on a  branch line busy with freight trains and Sudbury because it is on a single track branch line, we are left with just.

  • Bury St. Edmunds
  • Newmarket

Add in the proposed A14 Parkway station and is it feasible to run a service between London Liverpool Street and Bury St. Edmunds via Cambridge, Newmarket and A14 Parkway.

I calculate that a round trip would be possible in around four hours, thus making three trains per day possible.

I suspect, there would be capacity problems on the Southern section of the West Anglia Main Line, but if this were to be four-0tracked as is proposed, this would ease that problem.

So a service between West Suffolk and London, is probably one for the future.

A Final Conclusion

Newmarket can benefit from East West Rail, but the two parties must agree objectives that don’t cause problems for the other.

 

 

 