The Anonymous Widower

Cerulean Winds Submits 1 GW Aspen Offshore Wind Project In Scotland (UK)

The title of this post, is the same as that of this article on enerdata.

These first two paragraphs add more details.

Floating wind developer Cerulean Winds has submitted an offshore consent application for its 1 GW Aspen floating wind project to the local authorities in Scotland (UK). The application was submitted to the Scottish Marine Directorate Licensing Operations Team and is supported by an Environmental Impact Assessment (EIA) of the project. The Aspen project is comprised of 72 wind turbines to be installed 100 km off the coast in the Central North Sea to deliver 1 GW of renewable energy, expecting to start operations before 2030. The development is expected to attract a total investment of GBP11bn (€12.6bn) across a 50-year lifespan.

Cerulean Winds is partnering on the project’s delivery with NOV, Siemens Energy, Bilfinger and Ocean Installer. The company plans to develop three floating offshore wind projects in the Central North Sea (Aspen, Beech and Cedar), which are expected to be comprised of over 300 wind turbines in total.

This wind farm along with its sisters ; Beech and Cedar doesn’t appear to have been added to Wikipedia’s master list of offshore wind farms.

From a Cerulean infographic on this page, it appears that Aspen, Beech and Cedar are all 1008 MW wind farms, that are planned to be operational in 2028, starting in 2028 and starting in 2028. It would be good for the ambitions of Ed Miliband, if these three wind farms were fully operational by the end of 2030.

September 12, 2025 Posted by | Energy | , , , , , , , | 1 Comment

US Floating Wind Platform Developer Issues RFI To Fabricators Worldwide

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

Aikido Technologies, which recently secured a spot at a Norwegian offshore demo site, has released an RFI for its 15 MW ‘AO60’ floating wind platform to offshore wind fabricators.

These are the first four paragraphs which add more details.

The California-based floating wind foundation developer said on social media that it had issued the RFI to more than ten “top-tier offshore wind fabricators from around the world”.

The RFI has been released in three separate packages, each tailored to a specific type of facility: one for standard offshore steel shops, one for tubular/jacket yards, and one for monopile/tower facilities.

“This is how we can build 1, 50 or 100 of these units with existing fabrication capabilities, with components that can be easily transported around the world for final assembly at a local port. No need for custom yards, custom vessels or custom ports”, Aikido Technologies said.

In May 2025, the company was allocated a slot for its AO60 platform at the Marine Energy Test Centre (METCentre) in Norway, where Aikido will deploy what it says is a first-of-its-kind 15 MW demonstration project.

As someone, who wrote project management computer systems for thirty years, I like Aikido’s plans and feel they would be well suited to the UK, where we have quite a few local ports, that would appear suitable for final assembly of the A060 platforms.

In Yarmouth Harbour To Be ‘Completed’ In £60m Project, I describe the expansion of the Port of Great Yarmouth.

These two paragraphs describe the work to be done.

Peel Ports said it would invest between £50m and £60m in Great Yarmouth’s Outer Harbour by developing the southern terminal, creating a roll-on roll-off (RORO) lift ramp and a large storage area.

Port director Richard Goffin said the construction work, which is set to begin in 2026, would “complete” the port as laid out in a business case in the early 2000s.

This image from Peel Ports Group shows how the Port of Great Yarmouth will look after the the proposed development.

As the Port of Great Yarmouth has a depth of ten metres it could be an ideal base for the assembly and maintenance of floating wind turbines.

August 12, 2025 Posted by | Energy, Transport/Travel | , , , , , , , , | Leave a comment

Three Applications Submitted In Malta’s First Offshore Wind Tender

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

The Maltese government has received three submissions in the pre-qualification period for the country’s first offshore wind tender, which will award a concession for a floating wind project with an installed capacity of around 300 MW.

These first two paragraphs add more detail.

The Ministry for the Environment, Energy, and Public Cleanliness said on 22 July that the submission phase for the Preliminary Qualification Questionnaire (PQQ), launched in December 2024, had concluded, with three companies and consortia looking to participate in the process: Code Zero Consortium, led by SEP (Malta) Holding; Atlas Med Wind, a consortium led by Italy’s GreenIT SpA; and MCKEDRIK Sole Member, a sole applicant based in Greece.

In December last year, Malta opened the PQQ period, seeking to pre-qualify potential developers who will then be invited to participate in the next stage(s) of the tender to build Malta’s first floating wind farm. The project is planned to have an installed capacity of between 280 MW and 320 MW

Note.

  1. Despite being Malta’s first offshore wind farm, it will be a floating wind farm.
  2. It is a medium-sized wind farm, which will probably give the Maltese chances to supply some services.
  3. The consortia seem to have some local involvement.

Malta appears to be taking a sensible route.

I asked Google AI, what was Malta’s electricity generating capacity and got this reply.

Malta’s total electricity generation capacity is approximately 0.83 million kilowatts, according to TheGlobalEconomy.com. This value represents the latest data from 2023. The majority of this capacity comes from conventional power plants, with a smaller but growing contribution from renewable sources.

As 0.83 million kilowatts is 830 MW, these offshore wind farms could replace up to 36 % of Malta’s current generating capacity.

From my experience of the island Malta is not a bad place to live, so recruiting the specialist engineers, that are needed shouldn’t be a problem.

I can also see other small countries following a similar route to Malta.

July 23, 2025 Posted by | Energy | , , , | Leave a comment

Offshore Solar Farm Ready For Tow Out To Hollandse Kust Noord Wind Project

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

What is described as the “world’s first” offshore solar farm integrated within a wind farm has completed assembly at the Port of Amsterdam and is ready for deployment at the Hollandse Kust Noord (HKN) offshore wind farm in the North Sea.

These two paragraphs give more details about the project.

Dutch company Oceans of Energy assembled the floating solar farm in three days. The system will be towed 18.5 kilometres offshore this summer to be installed at the HKN site, operated by CrossWind, a joint venture (JV) between Shell and Eneco.

According to Oceans of Energy, the project uses prefabricated floating solar units designed for offshore conditions and is seen as a step toward scaling hybrid wind-solar developments.

There are several ways to generate renewable energy.

As wind, solar, tidal and wave power are often out of phase with each other, if you are using two together in a hybrid setup, then it is probably not a bad idea to add a BESS or other form of storage to the mix.

In Oceans of Energy To Build Offshore Solar Array At Hollandse Kust Noord Offshore Wind Park, I said that the Dutch were putting batteries in the design of Hollanse Kust Noord offshore wind farm.

June 27, 2025 Posted by | Energy | , , , , , , , , , | Leave a comment

Japanese Company Takes Part In Spain’s Floating Wind Demonstration Project

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

Japan’s Electric Power Development, also known as J-Power, has joined the WHEEL floating offshore wind demonstration project in Spain.

These three paragraphs add more details.

The WHEEL demonstration project is led by the Madrid-headquartered company Esteyco. WHEEL will feature one turbine installed three kilometres off the eastern coast of Gran Canaria, Spain.

Through this project, J-Power aims to acquire knowledge in the manufacturing, assembly, installation, and operation of floating offshore wind power, contributing to the development of floating offshore wind projects in Japan and abroad, the company said.

A floating offshore wind turbine, with a capacity of 6.17 MW, will be constructed and tested using WHEEL, which combines the advantages of barge-type foundations and spar-type foundations.

There is a visualisation of the WHEEL project in the linked article.

Conclusion

I like the concept of WHEEL.

In Norwegians Developing Monopile Foundation For 100-Metre Depths, I write about my involvement with a company called Balaena Structures in the 1970s, who were trying to develop a reusable oil and gas platform. I have a feeling, that WHEEL and the Balaena have dynamic and floating properties in common.

June 25, 2025 Posted by | Energy | , , , , , , , , , | Leave a comment

Project To Demonstrate 15+ MW Turbine On Ocergy’s Floating Platform Kicks Off

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

The Reduced Commercial Risks with Demo of 15+ MW (RECORD15) joint industry project, which aims to install a latest generation turbine with a rated power over 15 MW on Ocergy’s floating platform in 2028, has been launched

The visualisation of the 15 MW turbine on its float in the article is impressive.

These two paragraphs add more details.

The Front-End Engineering Design (FEED) contract for this pilot project was recently signed between Ocergy and three offshore wind developers: EnBW Energie Baden-Württemberg AG, Kyuden Mirai Energy, and TEPCO Renewable Power.

Ocergy’s platform, the turbine agnostic OCG-Wind, is a modular design supporting an optimised assembly process from pre-fabricated steel sub-assemblies, allowing serial production using today’s existing supply chain and infrastructure, said the company.

Note.

  • The average size of onshore wind turbine in the UK is 1.6 MW.
  • Whitelee wind farm in Scotland, which is the largest onshore wind farm in the UK, uses 215 x 2.5 MW turbines.
  • The Dogger Bank wind farm used 13 and 14 MW turbines on fixed foundations.

A 15+ MW turbine on a floating foundation will surely give Ocergy’s technology a very good test.

But it will be needed.

This is the overview of the Bowdun wind farm in Scotland, taken from the project’s web site.

The Bowdun Offshore Wind Farm will be located in the E3 leasing zone, which lies 44km off the coast of Aberdeenshire.

The zone, awarded to TWP under the ScotWind leasing round in January 2022, covers an area of 187km.

With water depths below 70m, it is highly suitable for fixed-foundation turbines, which will most likely sit on jacket foundations.

TWP plans to develop a 1GW offshore wind farm at the site. The base case is that the farm will number between 40-60 turbines, using ‘next-generation’ models with a capacity
between 18 MW and 25 MW. Construction is anticipated to commence in 2029 with commissioning planned for 2032-2033.

This project base case will evolve as we gain knowledge from our site investigations and conduct technology research.

If turbines between 18 MW and 25 MW are to be used on fixed foundations, I can see a need to develop floats that will handle them.

June 23, 2025 Posted by | Design, Energy | , , , , | Leave a comment

Equinor, EDF-ESB Joint Venture Secure 1.5 GW Sites In UK Floating Wind Leasing Round

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

The Crown Estate has selected Equinor and Gwynt Glas, a joint venture between EDF Renewables UK and ESB, as preferred bidders in the seabed leasing round for floating wind projects in the Celtic Sea.

These two paragraphs give more details.

Selected on 12 June, each of the two developers was awarded 1.5 GW of capacity in their respective project development area (PDA) for an annual option fee of GBP 350/MW (approximately EUR 410/MW).

The Crown Estate launched the floating wind leasing round (Offshore Wind Leasing Round 5) in February 2024, offering three areas off the coasts of Wales and South West England for a total of up to 4.5 GW of installed capacity.

Note.

  1. It looks like the Crown Estate are working to get a contract for the third site.
  2. The ports of Bristol and Port Talbot could be handling the assembly of the floating turbines.
  3. The Crown Estate has also established a new strategic approach with the National Energy System Operator (NESO).

Given the problems some wind and solar farms have had to get connected, the Crown Estate’s link up with NESO could be attractive to developers?

Conclusion

This looks a good bit of business by the Crown Estate in the Celtic Sea.

Did they get NESO to be helpful, by asking senior people for tea with Charles and Camilla at Highgrove?

June 19, 2025 Posted by | Energy | , , , , , , , , | 1 Comment

Flotation, Vargronn Complete NorthConnect Deal

The title of this post, is the same as that of this article on Renews.biz.

This is the sub-heading.

1.4GW Cenos floater backers seal ‘productive partnership’ with interconnector acquisition

These three paragraphs add more details to the deal.

Flotation Energy and Vargronn have closed their acquisition of the NorthConnect interconnector project between Scotland and Norway.

The developers said the deal had followed close collaboration on shared transmission infrastructure and a common grid connection point for the interconnector and the proposed 1.4GW Cenos floating wind farm off east Scotland.

NorthConnect already has consent for an offshore and onshore cable route to a substation near Boddam, Aberdeenshire, that will link to SSEN’s Peterhead substation.

This looks like a clever use of the permissions for the interconnector to connect the Cenos wind farm to the grid.

June 13, 2025 Posted by | Energy | , , , , , | Leave a comment

UK To Launch Seventh CfD Auction In August, Offshore Wind Has Its Own AR7 Timeline

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

The UK government has published an indicative timeline for the Contract for Difference (CfD) Allocation Round 7 (AR7), stating that it expects to open the auction in August and announce the results between late 2025 and early 2026. The timeline for offshore wind projects is now separate from that for other technologies, which will enable the confirmation of results as soon as possible, according to the Department for Energy Security and Net Zero (DESNZ).

These first two paragraphs give more details of the Contract for Difference Auction.

The planned AR7 timeline for offshore wind, including both fixed-bottom and floating wind, sets the auction opening date between 7 to 27 August 2025, with results expected to be in from the second half of December 2025 to the second half of February 2026, depending on non-qualifying applicants requesting a Tier 1 review and/or Tier 2 appeal.

Before the launch of the seventh CfD allocation round, the government will publish Clean Industry Bonus results. This is scheduled for June.

I think this is going to be a very different Contract for Difference Auction to those held under the previous Conservative government.

  • Will prices be as high?
  • Will some regular companies in the auctions not bother to bid?
  • Will there be bids for onshore wind in England?

It will be quite, if not very interesting!

 

May 30, 2025 Posted by | Energy | , , , , | Leave a comment

Haventus, Sarens PSG Unveil ‘On-Land to Launch’ Floating Wind Solution

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

UK companies Haventus and Sarens PSG have developed a low-cost solution for the integration and launch of floating offshore wind turbines.

These two introductory paragraphs add more details.

Haventus said that it is working to enable offshore wind project developers to acquire fully assembled floating bases and turbines at Ardersier, Scotland, as well as providing dry storage which does not require complex licensing.

A heavy-lift solution will enable safe on-land integration and launch to the harbour of fully integrated floating offshore wind turbines.

Note.

  1. Haventus introduce themselves on their web site, as an energy transition facilities provider, offering pivotal infrastructure for the offshore wind industry. The first facility, they are developing is the Port of Ardesier in the North of Scotland, to the North-East of Inverness.
  2. Sarens PSG introduce themselves on their web site, as specialists in turnkey heavy lifting and transportation solutions for offshore wind component load-in, marshalling, assembly, deployment, and integration.

It looks to me that the two companies are ideal partners to put together flotillas of large floating wind turbines.

These two paragraphs seem to describe the objectives of the partnership.

This should shorten supply chains through single-site sourcing of key components and remove the operational, safety, logistical, and engineering complexity that comes with storage and integration activities in the marine environment.

The companies also said that the solution can also drive down the costs and accelerate floating offshore wind deployment by simplifying transport and installation requirements and remove the obstacles of weather and design life variables that must be considered with ‘wet’ storage and integration.

I was always told as a young engineer to define your objectives first, as you might find this helps with the design and costs of the project.

I do wonder sometimes, if the objectives of High Speed Two smelt too much of a project designed by lots of parties, who all had different objectives.

The Location Of The Port Of Ardesier

This Google Map shows the location of the Port of Ardesier in relation to Inverness, the Orkneys and Shetlands, and Norway.

The Port of Ardesier would appear to be ideally placed to bring in business for the partnership.

 

May 14, 2025 Posted by | Design, Energy | , , , , , , , , , , | Leave a comment