Station Stop Performance Of The Intercity Tri-Mode Battery Train

Hitachi have stated that the their Intercity Tri-Mode Battery Trains will not use their diesel engines in stations and to leave the station.

The first Intercity Tri-Mode Battery Trains will be conversions of Class 802 trains.

This page on the Eversholt Rail web site, has a data sheet for a Class 802 train.

The data sheet shows the following for a five-car Class 802 train.

  • It can accelerate to 120 kph/75 mph in 100 seconds in electric mode.
  • It can accelerate to 160 kph/100 mph in 160 seconds in electric mode.
  • It can accelerate to 120 kph/75 mph in 140 seconds in diesel mode.
  • It can decelerate from 120 kph/75 mph in 50 seconds in electric mode.

Note.

  1. 75 mph is the operating speed of the Cornish Main Line and possibly the Highland Main Line.
  2. 100 mph is the operating speed for a lot of routes in the UK.
  3. It would appear that trains accelerate to 75 mph forty second faster in electric mode, compared to diesel mode.
  4. In diesel mode acceleration slows markedly once 100 kph is attained.

Can we assume that performance in battery mode, will be the same as in electric mode?

I am always being told by drivers of electric cars, trains and buses, that they have sparkling performance and my experience of riding in battery electric trains, indicates to me, that if the battery packs are well-engineered, then it is likely that performance in battery mode could be similar to electric mode, although acceleration and operating speed my be reduced to enable a longer range.

If this is the case, then the following times for a station call with a 75 mph operating speed are possible.

  • Electric mode – 50 + 60 + 100  = 210 seconds
  • Diesel mode – 50 + 60 + 140  = 250 seconds
  • Battery mode – 50 + 60 + 100  = 210 seconds

Note.

  1. The three figures for each mode are deceleration time, station dwell time and acceleration time.
  2. Times are measured from the start of deceleration from 75 mph, until the train accelerates back to 75 mph.
  3. I have assumed the train is in the station for one minute.

I suspect with a stop from 100 mph, that there are greater savings to be made than the forty seconds at 75 mph, due to the reduced acceleration in diesel mode past 100 kph.

Savings Between London Paddington And Penzance

There are fifteen stops between London Paddington and Penzance, which could mean over ten minutes could be saved on the journey.

This may not seem that significant, but it should be born in mind, that the fastest journey times between London and Penzance are between five hours and eight minutes and five hours and fourteen minutes.

So these small savings could bring a London Paddington and Penzance journey much closer to five hours.

Savings Between London Kings Cross And Inverness

There are probably not as great savings to be made on this route.

  • The electrification runs as far as Stirling.
  • There are only five intermediate stops between Stirling and Inverness
  • Stirling and Inverness are 151 miles apart.

On the other hand, the route has a lot of gradients, which may give opportunities to use the batteries to boost power on climbs and save fuel and emissions.

Conclusion

Replacing one or more of the diesel engines on a Class 800, 802, 805 or 810 train, on a route, where the full complement of diesel engines is not required, may well result in time savings on the journey, simply by reducing the time taken to accelerate back to operating speed.

I have indicated two routes, where savings can be made, but there may be other routes, where savings are possible.

December 20, 2020 Posted by | Transport/Travel | , , , , , , , | 2 Comments

Is The Eastern Leg Of High Speed Two Under Threat?

This page on the High Speed Two web site is entitled HS2 Phase 2b Eastern Leg.

These are the opening three paragraphs.

Earlier this year the government made clear in its response to the Oakervee Review its commitment to Phase 2b of HS2, ensuring we boost capacity, improve connectivity between our regions and share prosperity.

As part of this, the government plans to present an Integrated Rail Plan for the North and Midlands by the end of the year, informed by an assessment from the National Infrastructure Commission, which will look at how to deliver HS2 Phase 2b, Northern Powerhouse Rail, Midlands Rail Hub and other rail programmes better and more effectively.

In the meantime, the government has asked HS2 Ltd to pause work on the Eastern Leg. We recognise that this causes uncertainty and our Eastern Leg community engagement teams remain in place to support you.

The page then says that the work on the Western Leg should proceed, with the aim of a Western Leg Bill in early 2022.

In Northern Powerhouse Rail – Significant Upgrades Of The East Coast Main Line From Leeds To Newcastle (Via York And Darlington) And Restoration Of The Leamside Line, I showed that the current and future upgrades to the East Coast Main Line, required by the East Coast Main Line, Northern Powerhouse Rail and High Speed Two, will greatly reduce the times on services from London Kings Cross to Doncaster, Yorkshire, the North East and Scotland.

I said this on timings on the East Coast Main Line.

  • London Kings Cross and Doncaster could be around an hour.
  • London Kings Cross and Leeds could be around one hour and thirty minutes, using the current Doncaster and Leeds time, as against the one hour and twenty-one minutes for High Speed Two.
  • London Kings Cross and York could be around one hour and twenty-three minutes, using the current Doncaster and York time, as against the one hour and twenty-four minutes for High Speed Two.
  • Timings between York and Newcastle would be the same fifty-two minutes as High Speed Two, as the track will be the limitation for both services.
  • High Speed Two’s timing for York and Newcastle is given as fifty-two minutes, with York and Darlington as twenty-five minutes.
  • London Kings Cross and Darlington could be around one hour and forty-nine minutes
  • London Kings Cross and Newcastle could be around two hours and sixteen minutes.
  • London Kings Cross and Edinburgh would be under three-and-a-half hours, as against the proposed three hours and forty-eight minutes for High Speed Two.

LNER’s Azuma cavalry will hold the fort for as long as is needed.

I’ll now look at how various stations, will be affected if the Eastern Leg of High Speed Two is not built, until a couple of decades in the future.

Leeds

Current Long Distance Services At Leeds Station

Leeds station has the following long distance services in trains per hour (tph)

  • CrossCountry – 1
  • LNER – 2
  • TransPennine Express – 5

It is a bit thin compared to say Birmingham or Manchester.

Northern Powerhouse Rail And Leeds

Northern Powerhouse Rail has plans for Leeds with these services to other Northern cities.

  • Hull – two tph in 38 minutes
  • Manchester – six tph in 25 minutes
  • Newcastle – four tph in 58 minutes
  • Sheffield – four tph in 28 minutes.

From what they have written, the following could also be possible.

  • Bradford – six tph in a few minutes
  • Liverpool – four or more tph in 51 minutes
  • Manchester Airport – four or more tph in 35 minutes

It is an ambitious plan.

High Speed Two And Leeds

High Speed Two is planning to run the following trains to Leeds in every hour.

  • Birmingham Curzon Street and Leeds – 200 metre train
  • Birmingham Curzon Street and Leeds via East Midlands Hub – 200 metre train
  • London Euston and Leeds via Old Oak Common and East Midlands Hub – 200 metre train
  • London Euston and Leeds via Old Oak Common and East Midlands Hub – 400 metre train
  • London Euston and Leeds via Old Oak Common, Birmingham Interchange and East Midlands Hub – 400 metre train

Timings will be as follows.

  • Birmingham Curzon Street and Leeds – 49 minutes.
  • London Euston and Leeds – One hour and 21 minutes.

There will be about 1000 seats per hour between Birmingham Curzon Street and Leeds and 2500 seats per hour Between London Euston and Leeds.

High Speed Two And Leeds Via Manchester

This report on the Transport for the North web site, is entitled At A Glance – Northern Powerhouse Rail.

This map shows Transport for the North’s ideas for connections in the West linking Crewe, Liverpool, Manchester, Manchester Airport, Warrington and Wigan.

A black line goes East from Manchester to link it to Leeds via Huddersfield and Bradford.

  • This is proposed as a route shared between High Speed Two and Northern Powerhouse Rail.
  • High Speed Two are promising that London Euston and Manchester will be timed at one hour and eleven minutes.
  • London Euston and Manchester will have a frequency of three tph and will all be 400 metre High Speed Two Full Size trains, with about a thousand seats.
  • Northern Powerhouse Rail have an objective of a twenty-five minute journey time between Manchester and Leeds.

I would also build the Manchester and Leeds route with the following characteristics.

  • As a full-size tunnel capable of taking High Speed Two Full Size trains and the largest freight trains.
  • Intermediate and underground stations at Huddersfield and Bradford.
  • It could be built as a base tunnel, like the similarly-sized Gotthard base tunnel in Switzerland.
  • The Swiss tunnel has a maximum operating speed for passenger trains of 125 mph.

If it can be built for a reasonable cost and in a reasonable time-scale, it could be a way of doing the following.

  • Creating a straight 150 mph plus route across the Pennines, with a capacity of 18 tph.
  • Running high-capacity fast trains between London Euston and Leeds via Manchester Airport and Manchester.
  • Running freight trains between the two sides of the Pennines.
  • Creating a high frequency route between Liverpool and Hull via Manchester Airport, Manchester, Huddersfield and Bradford and Leeds.

The passenger service between Liverpool and Hull could be the world’s first high speed metro.

If the London Euston and Manchester trains, were to be extended to Leeds, London Euston and Leeds would take one hour and thirty-six minutes, which would only be fifteen minutes slower, than is promised for the route going via the Eastern Leg of High Speed Two.

London Kings Cross And Leeds

When the in-cab digital signalling is complete between London Kings Cross and Leeds, I am fairly confident that with a few other improvements and more zoom from the Azumas, that a London Kings Cross and Leeds time of one hour and fifty minutes will be possible.

But will two nine-car or pairs of five-car trains per hour (tph), be enough capacity? Especially, as pairs of five-car trains will split and join to serve a wider catchment area, which will harvest more passengers.

LNER will in a couple of years have an extra path every hour into Kings Cross.

I would feel that best use of this path would be to run between London Kings Cross and Edinburgh via Leeds and Newcastle.

  • Leeds and Newcastle could be the only intermediate stops.
  • Leeds would be the ideal place to change to Northern Powerhouse Rail for anywhere in the North of England.
  • My estimates, say it could run between London Kings Cross and Edinburgh in around three-and-a-half hours.
  • It would run non-stop between London Kings Cross and Leeds, Leeds and Newcastle and Newcastle and Edinburgh.

It would increase capacity, between the four major destinations on the route; London Kings Cross, Leeds, Newcastle and Edinburgh.

It could start running, once the digital signalling and current improvements to the East Coast Main Line are complete.

London St. Pancras And Leeds

I discussed, Northern Powerhouse Rail’s plan for Sheffield and Leeds in Northern Powerhouse Rail – Connecting Sheffield To HS2 And On To Leeds.

This could see the following new infrastructure.

  • Electrification between Clay Cross North Junction and Sheffield station of the route shared by the Midland Main Line and High Speed Two.
  • Electrification through Sheffield and on to Leeds, via the Wakefield Line
  • New stations for High Speed trains at Rotherham and Barnsley Dearne Valley.

I could see East Midlands Railway taking advantage of this route, with their new Class 810 trains and running a regular Leeds and St. Pancras service.

  • It would call at Wakefield Westgate, Barnsley Dearne Valley, Rotherham and Meadowhall. between Leeds and Sheffield stations.
  • It would take twenty-eight minutes between Leeds and Sheffield, if it met Northern Powerhouse Rail’s objective.
  • Perhaps one of the two tph between London St. Pancras and Sheffield could be extended to Leeds.

As the current time between London St. Pancras and Sheffield, is a few minutes under two hours, I can see a time of comfortably under two-and-a-half hours between London St. Pancras and Leeds.

A Summary Of Journey Times Between London And Leeds

I can summarise my estimates, between London and Leeds.

  • High Speed Two – Direct via Eastern Leg – One hour and twenty-one minutes.
  • High Speed Two – via Manchester – One hour and thirty-six minutes.
  • East Coast Main Line – via Doncaster – One hour and thirty minutes.
  • Midland Main Line – via Derby and Sheffield – Two hours and twenty minutes.

The direct High Speed Two route is the fastest., but others could be viable alternatives for some passengers.

Bradford

Consider.

  • Under current plans Bradford won’t be getting any high speed service from High Speed Two.
  • The best it can get under current plans is several direct services per day, between Bradford Forster Square and London Kings Cross in perhaps two hours.
  • The layout of the city and its two stations doesn’t give good connectivity.

Bradford, Harrogate, Huddersfield and Skipton could probably be served by trains to and from London Kings Cross that join and split at Leeds.

But if Northern Powerhouse Rail goes for a tunnel between Manchester and Leeds with Bradford as an underground station, it could be served by High Speed Two services going between London Euston and Leeds via Manchester.

I would estimate that if London Euston and Leeds via Manchester took around one hour and thirty-six minutes, London Euston and Bradford could take around an hour-and-a-half.

Darlington

I can summarise my estimates, between London and Darlington.

  • High Speed Two – Direct via Eastern Leg – One hour and forty-nine minutes.
  • High Speed Two – via Manchester and Leeds – Two hours and six minutes.
  • East Coast Main Line – via Doncaster – One hour and forty-nine minutes.

Improvements on the East Coast Main Line, needed to enable and speed-up High Speed Two services to York, Darlington and Newcastle; will speed up East Coast Main Line services to Darlington.

Edinburgh

I can summarise my estimates, between London and Edinburgh.

  • High Speed Two – Direct via Western Leg – Three hours and forty minutes.
  • High Speed Two – via Manchester and Leeds – Three hours and forty-eight minutes.
  • East Coast Main Line – via Doncaster – Three hours and thirty minutes.

Improvements on the East Coast Main Line, needed to enable and speed-up High Speed Two services to York, Darlington and Newcastle; will speed up East Coast Main Line services to Newcastle.

Harrogate

Consider.

  • Under current plans Harrogate won’t be getting any high speed service from High Speed Two.
  • The best it can get under current plans is several direct services per day, between Harrogate and London Kings Cross in perhaps two hours.

Bradford, Harrogate, Huddersfield and Skipton could possibly  be served by trains to and from London Kings Cross that join and split at Leeds.

Huddersfield

  • If Huddersfield is served by underground platforms beneath the current Huddersfield station, a lot of what I said for Bradford would apply to Huddersfield.
  • The timings would probably be around an-hour-and-a-half from London Euston.

Bradford, Harrogate, Huddersfield and Skipton could possibly be served by trains to and from London Kings Cross that join and split at Leeds.

Hull

Hull is an interesting destination.

  • Reaching Hull from the current High Speed Two network will need a change at Leeds or another station.
  • Using Northern Powerhouse Rail’s objectives on timings, London Euston and Hull via Manchester on High Speed Two, would be a few minutes under two-and-a-half hours.
  • I strongly feel, that London Kings Cross and Hull via Selby could be reduced to below two hours.

Hull would also make a superb Eastern terminal station for both Northern Powerhouse Rail and a High Speed Two service from London via Manchester and Leeds.

You pays your money and takes your choice.

Middlesbrough

Reaching Middlesbrough from the proposed High Speed Two network will need a change at York or another station.

But a time of two hours and twenty minutes, should be possible using the East Coast Main Line via Doncaster.

Improvements on the East Coast Main Line, needed to enable and speed-up High Speed Two services to York, Darlington and Newcastle, will speed up East Coast Main Line services to Middlesbrough.

Newcastle

I can summarise my estimates, between London and Newcastle.

  • High Speed Two – Direct via Eastern Leg – Two hours and seventeen minutes.
  • High Speed Two – via Manchester and Leeds – Two hours and thirty-four minutes.
  • East Coast Main Line – via Doncaster – Two hours and sixteen minutes.

Improvements on the East Coast Main Line, needed to enable and speed-up High Speed Two services to York, Darlington and Newcastle; will speed up East Coast Main Line services to Newcastle.

Nottingham

I will compare average speeds on the Midland Main Line between London St. Pancras and Nottingham and on the East Coast Main Line, between London Kings Cross and Leeds.

Currently.

  • London St. Pancras and Nottingham services, over the 126 mile route, take one hour and fifty minutes. which is an average speed of 69 mph.
  • London Kings Cross and Leeds services, over the 186 mile route, take two hours and thirteen minutes, which is an average speed of 94 mph.

Note.

  1. The two routes are of similar character and are fairly straight with large sections of 125 mph running and quadruple tracks.
  2. The East Coast Main Line to Leeds  is fully electrified, whereas the Midland Main Line is only partially electrified.
  3. Both routes have a small number of stops.
  4. In a few years time, services on both routes will be run by different members of the Hitachi AT-300 train family.

I don’t feel it would be unreasonable to assume that a London St. Pancras and Nottingham service could be run at an average speed of 94 mph, if the Midland Main Line were upgraded to the same standard as the East Coast Main Line.

This could mean a time of around one hour and twenty-one minutes between London St. Pancras and Nottingham, or a saving of twenty-nine minutes.

Is that possible?

  • The new Class 810 trains, will have four engines instead of the normal three for a five-car AT-300 train. Will they be able to be closer to the 125 mph line-speed on diesel power, where it is available on the Midland Main Line.
  • The trains will be able to use electrification between London St. Pancras and Market Harborough.
  • There have been hints, that more electrification may be installed on the Midland Main Line.
  • Hitachi have announced a battery electric version of the AT-300 train called an Intercity Tri-Mode Battery Train, where one or more of the diesel engines are replaced by battery packs.
  • The new trains will be ready to accept in-cab ERTMS digital signalling, so they could be able to run at up to 140 mph, if the track were to be upgraded.

I certainly feel, that substantial time savings could be possible between London St. Pancras and Nottingham.

Eighty-one minutes would be very convenient, as it would comfortably allow a three hour round trip, which would mean just six trains or more likely pairs of trains would be needed for the current two tph service.

Eighty-one minutes would not be the fifty-two minute service promised by High Speed Two!

But!

  • The new trains are planned to be introduced from 2023.
  • Who knows, when High Speed Two will arrive at the East Midlands Hub station?
  • They won’t need any new substantial infrastructure to replace the current trains.

I also suspect the new trains will have more seats, but, the capacity of the Class 810 train, has not been published.

Nottingham could also be served by a high speed service from London Kings Cross via Grantham, which I estimate would take about one hour and twenty minutes.

Sheffield

A lot of what I said for Nottingham can be applied to Sheffield.

  • Currently, London St. Pancras and Sheffield services, over the 165 mile route, take two hours, which is an average speed of 82.5 mph.
  • High Speed Two is promising a journey time of one hour and twenty-seven minutes.
  • An average speed of 90 mph, would mean a journey time of one hour and fifty minutes.
  • This would allow a four hour round trip, which would mean just eight trains or more likely pairs of trains would be needed for the current two tph service.

It would be very convenient for the operator.

It looks like if pairs of trains were to be run on both the Nottingham and Sheffield routes, that twenty-eight trains would be needed to run both services.

This fits well with a fleet size of thirty-three trains.

The only caveat, is that to get the required journey times, it might be necessary to rebuild and electrify the tracks, between Sheffield and Clay Cross North Junction.

  • These tracks will be shared with the future Sheffield Branch of High Speed Two.
  • It would only be 15.5 miles of double-track to rebuild and electrify.
  • It could be rebuilt to allow 140 mph running. Several minutes could be saved!

The electrification could allow Hitachi’s Intercity Tri-Mode Battery trains to be able to run the Sheffield service.

These trains would certainly be a way of avoiding the tricky electrification of the Derby and Clay Cross section of the route, which goes through the World Heritage Site of the Derwent Valley Mills.

Sheffield could also be served by a high speed service from London Kings Cross via Doncaster, which I estimate would take about one hour and thirty minutes.

Skipton

Consider.

  • Under current plans Skipton won’t be getting any high speed service from High Speed Two.
  • The best it can get under current plans is several direct services per day, between Skipton and London Kings Cross in perhaps two hours.

Bradford, Harrogate, Huddersfield and Skipton could possibly  be served by trains to and from London Kings Cross that join and split at Leeds.

Sunderland

Reaching Sunderland from the proposed High Speed Two network will need a change at York or another station.

But a time of two hours and thirty minutes, should be possible using the East Coast Main Line via Doncaster.

Improvements on the East Coast Main Line, needed to enable and speed-up High Speed Two services to York, Darlington and Newcastle, will speed up East Coast Main Line services to Sunderland.

York

I can summarise my estimates, between London and York.

  • High Speed Two – Direct via Eastern Leg – One hour and twenty-four minutes.
  • High Speed Two – via Manchester and Leeds – One hour and forty-two minutes.
  • East Coast Main Line – via Doncaster – One hour and twenty-four minutes.

Improvements on the East Coast Main Line, needed to enable and speed-up High Speed Two services to York, Darlington and Newcastle; will speed up East Coast Main Line services to York.

I believe strongly, that York would be about as fast from London, by either of the direct routes, but both would serve different intermediate destinations.

Conclusion

My first conclusion is a surprising one, but the promised timings from High Speed Two and the current timings in the timetable make it clear.

To achieve the required timings for High Speed Two, major improvements must be made to existing track and these improvements will mean that existing services will be competitive with High Speed Two on time.

These improvements fall into this category.

  • Improving the East Coast Main Line between York and Newcastle, will make East Coast Main Line services to York, Darlington, Durham and Newcastle competitive with High Speed Two services.
  • Improving the East Coast Main Line between York and Newcastle, may also mean that London Kings Cross and Edinburgh will be faster than the High Speed Two service between London Euston and Edinburgh.
  • Electrifying the route shared between Sheffield and Clay Cross North Junction, will speed up London St. Pancras and Sheffield services and make them more competitive with High Speed Two.

I suspect there may be similar mutual improvements on the Western leg of High Speed Two.

Other smaller conclusions from my analysis of the improvements include.

  • These improvements will create some extra capacity on the East Coast and Midland Main Lines, by removing bottlenecks and improving line speeds.
  • Electrification, even if it is only partial or discontinuous, will improve services on the Midland Main Line.
  • Some places like Harrogate, Middlesbrough and Skipton will never be served directly by High Speed Two, but are easily served by East Coast Main Line services from London Kings Cross.
  • Northern Powerhouse Rail is very much part of the North-South capacity for England.
  • In-cab ERTMS signalling will play a large part in increasing capacity and line speeds.

Perhaps in our planning of High Speed Two, we should plan all the routes in the North and Midlands in a much more holistic way.

If we look at the capacity between London and the North, I feel that with the addition of Phase 1 of High Speed Two to Birmingham in 2029-2033 and hopefully Phase 2a soon afterwards, that Phase 2b will not be needed for reasons of speed and capacity until years later.

So, I would pause most construction of the Eastern Leg of High Speed Two until Phase 1 and Phase 2a are complete.

I would make exceptions for the following.

  • Improvements to the shared section of the East Coast Main Line and High Speed Two, between York and Newcastle.
  • Building a high speed connection between Leeds and York for the use of Northern Powerhouse Rail and the East Coast Main Line.
  • Rebuilding and electrification of the shared section of the Midland Main Line and High Speed Two, between Clay Cross North Junction and Sheffield.
  • Improve and electrify the route between Sheffield and Leeds.

But I would continue with the design, as I feel that East of Leeds is very much sub-optimal at the present time.

The route of the Eastern leg of High Speed Two would be safeguarded.

But the biggest problem with the Eastern Leg of High Speed Two to Leeds, is that however it is built travellers to and from Leeds, York and further North will not see any improvements for some years, but improving the East Coast Main Line wouldn’t exactly see jam tomorrow, but tons of it by 2024.

 

 

 

 

December 7, 2020 Posted by | Transport/Travel | , , , , , , , , , , , , , , , , , , , | 2 Comments

Cost Studies Could See Electrification Comeback

This post was updated on the 1st May 2021.

The title of this post is the same as that of an article by Roger Ford in the September 2018 Edition of Modern Railways

There are now two studies into the cost of railway electrification.

Both arudies expected to be completed in October.

The article gives some examples of electrification costs per single track kilometre (stkm).

  • A sustained rolling program – £1million/stkm
  • Great Western Main Line – £3million/stkm
  • Northern England – Below £2million/stkm.
  • Cumbernauld-Springburn – £1.2million/stkm
  • East Coast Main Line – £500,000/stkm (At current prices)

The article finishes with these words.

£1million/stkm would be a feasible target.

That the Department for Transport has commissioned the independent review suggests electrification could still be on the agenda.

Roger is very much a respected commentator and his conclusions are more likely to be spot on, than wide of the mark.

Does Running Electric Trains On A Route Count As Electrification?

I ask this question deliberately, as over the last few years several schemes have been proposed to electrify perhaps two miles of line to a new development or city or town centre.

The Midland Metro is being extended to Wolverhampton station by building a tram line, that will be run using battery power on the existing trams.

Another example of this type of line is the extension of the Gospel Oak to Barking Line to Barking Riverside. After reading all the documentation, I have found that electric trains are mentioned several times, but electrification is not. As Bombardier Aventras probably can run on battery power, does this mean that the extension will be built without wires?

May 2021 Update – It now looks like the route is being fully electrified.

There are also some electrified branch lines, where the overhead electrification is unadulterated crap, that was erected over fifty years ago and has been got at by the steel moths.

Could we see the electrification on these branches removed to save on replacement and maintenance costs and the trains replaced by battery trains charged on the electrified main lines?

Recent Developments

I think various developments of recent years will help in the containing of electrification costs.

Batteries On Trains

It is my belief that batteries on trains could revolutionise the approach to electrification.

In my view, batteries are the only way to handle regenerative braking, which cuts energy costs.

This means, that if no trains using a route, return their braking energy through the electrification, then costs are saved by using simpler transformers.

Adequate battery capacity also gives other advantages.

  • Bombardier are fitting remote wake-up to Aventras. I wrote about this in Do Bombardier Aventras Have Remote Wake-Up?
  • Depots and sidings can be built with only limited electrification.
  • Hitachi use batteries charged by regenerative braking to provide hotel power for Class 800 trains.
  • Batteries are a simple way of moving trains in a Last Mile application on perhaps a short branch line.
  • Battery power can be used to rescue a train, when the electrification fails.

Reports exist of Alstom, Bombardier, CAF, Hitachi, Siemens and Stadler using or researching the use of batteries in trains.

May 2021 Update – All Merseyrail’s Class 777 trains and East Coast Trains’ Class 803 trains will have small batteries for all purposes except traction.

Hydrogen Power

I am becoming more enthusiastic about hydrogen power, which is primarily being developed by Alstom.

  • The UK could produce a lot of hydrogen easily from electrolysis of either brine to produce chlorine or water to produce hydrogen and oxygen.
  • Wind power would be a convenient way to provide the electricity needed.
  • Alstom are starting a project at Widnes to convert redundant Class 321 trains to hydrogen power.

A hydrogen powered Class 321 train would appear to be a powerful concept.

  • The trains will still be able to run on electrification.
  • The trains are pollution-free.
  • The trains make extensive use of batteries.
  • Alstom quote ranges of several hundred kilometres.
  • It would appear that the trains will still be capable of 100 mph after conversion.
  • Class 321 trains can be updated with quality interiors.

I believe these trains could find a solid market extending electrified routes.

Porterbrook’s Class 769 Trains

The Class 769 trains have been a long time coming, but companies have ordered 35 of these bi-mode upgrades of Class 319 trains.

  • They will be capable of 100 mph on electricity
  • They will be capable of 90 mph-plus on diesel
  • They will be able to use 25 KVAC overhead or 750 VDC third rail electrification.
  • They have been designed with a powerful hill-climbing capability.

Looking at the orders, some need the hill-climbing capability and GWR’s proposal to use the trains on the dual-voltage Reading-Gatwick route is a sensible one.

Bombardier’s 125 mph Bi-Mode Aventra With Batteries

I think that this train and others like it will be the future for many rail routes in the UK and around the world.

I will use the Midland Main Line as an example of the use of this type of train.

In a few years time, this important route will have the following characteristics.

  • A high proportion of 125 mph running.
  • Electrification between St. Pancras and Kettering/Corby
  • Possibly, electrification between Sheffield and Clay Cross courtesy of High Speed Two.

Full electrification would be difficult as part of the route is through a World Heritage Site.

But Bombardier’s train would swap power source intelligently as it powered its way along at 125 mph.

May 2021 Update –Hitachi got the order and their Class 810 trains appear to be capable of being converted into Hitachi Intercity Tri-Mode Battery Trains, which are described in this Hitachi infographic.

Note the claim of fuel and carbon saving of at least twenty percent.

Stadler’s Electric/Diesel/Battery Hybrid Train

This version of Greater Anglia’s Class 755 train, has been ordered for the South Wales Metro.

It can run on the following power sources.

  • 25 KVAC overhead electrification.
  • Onboard diesel generators.
  • Batteries

An intelligent control system will select the best power source.

With a central power pack between passenger cars, the design of this train is slightly quirky.

  • It is a 100 mph train with lots of acceleration.
  • I’m sure it could be equipped for 750 VDC electrification.
  • The power pack can be configured for different operators and types of routes.
  • Stadler are quite happy to sell small fleets of trains into niche markets.
  • It is a member of the successful Flirt family of trains, which are selling all over the world.

I wouldn’t be surprised to see more of these trains sold to the UK.

Hitachi’s Class 800 Trains and Class 802 Trains

Hitachi’s Class 800 trains are already running on the Great Western Railway.

  • They have an operating speed of 125 mph on both electricity and diesel.
  • TransPennine Express have ordered nineteen Class 802 trains.
  • Hull Trains have ordered five Class 802 trains.

I have gone from London to Swansea and back in a day in Class 800 trains and they the new trains seem to be performing well.

They will get even better, as electrification is extended to Cardiff.

May 2021 Update –Hitachi are developing battery-electric and tri-mode versions of these trains.

100/125 mph Bi-Mode Trains

In the previous sub-sections I have talked about four new bi-mode trains, that can run using electrification and under their own power.

  • Class 321 Hydrogen
  • Porterbrook’s Class 769 Train
  • High Speed Bi-Mode Aventra
  • Tri-Mode Stadler Flirt
  • Hitachi’s Class 800 Trains and Class 802 Trains

The designs are different, but they have common features.

  • An operating speed of at least 100 mph on electrified lines.
  • 90 mph-plus operating speed, when independently powered.
  • An out-and-back range of at least 200 miles away from electrification.
  • Proven designs from large families of trains.

Only one new route for these trains has been fully disclosed and that is Greater Anglia’s new Liverpool Street-Lowestoft service.

  • There will be three round trips a day between Lowestoft and London, using Class 755 trains.
  • North of Ipswich, diesel power will be used.
  • South of Ipswich, electric power will be used and trains will join the 100 mph queues to and from London.
  • Extra trains North of Ipswich, will use additional Class 755 trains, shuttling up and down the East Suffolk Line.

As the Class 755 trains and the express Class 745 trains on London-Ipswich-Norwich services will share the same team of drivers, it is an efficient use of bi-mode trains to extend an electric network.

Several of the proposed electrification schemes in the UK in addition to allowing electric trains, will also open up new routes for bi-mode and tri-mode trains.

  • Stirling to Perth electrification would allow bi-mode trains to run between Glasgow and Aberdeen via Dundee.
  • Leeds to York electrification would improve TransPennine bi-mode performance and allow electric trains access to Neville Hill TMD from the East Coast Main Line.
  • Sheffield to Clay Closs electrification for High Speed Two would also improve bi-mode performance on the Midland Main Line.

I think it should be born in mind, that the rolling out of the Class 800 trains all over the GWR, seems to have generated few bad reports, after a few initial problems.

In Thoughts On The Introduction Of Class 800 Trains On The Great Western Railway, I came to this conclusion.

There’s nothing much wrong operationally or passenger-wise with the Class 800 trains, that will not be put right by minor adjustments in the next couple of years.

So perhaps extending an electric network with quality bi-mode trains works well.

Used creatively bi-mode trains will increase the return on the money invested  in electrification.

Tram-Trains

I first saw tram-trains in Kassel in 2015 and I wrote about them in The Trams And Tram-Trains Of Kassel.

We are now embracing this technology in a trial in Sheffield using new Class 399 tram-trains.

I believe that, the UK is fertile territory for this technology.

  • KeolisAmey Wales haven’t waited for the results of the Sheffield trial and have already ordered thirty-six tram-trains with batteries for the South Wales Metro.
  • It also looks as if the West Midlands are planning to use the technology on an extension of the Midland Metro to Brierley Hill.
  • Glasgow are investigating a tram-train route to Glasgow Airport.

Although Network Rail and the Department for Transport seem to be only lukewarm on the technology, it does appear that local interests are much more enthusiastic.

In my view, the South Wales Metro is going to be a game changer, as it uses existing tracks, virtually standard tram-trains, electric/diesel/battery trains and a modicum of street running to transform a city’s transport system.

Intelligent Pantographs

I have read that the electro-diesel Class 88 locomotive can change between electric and diesel modes at line speed.

As a Control Engineer, I don’t believe it would be an impossible problem for a train powered by a mixture of 25 KVAC overhead electrification and diesel, battery, hydrogen or some other fuel to raise and lower a pantograph efficiently, to take advantage of any overhead wires that exist.

The raising and lowering could even be GPS controlled and totally automatic, with the driver just monitoring.

Ingenious Electrification Techniques

In Novel Solution Cuts Cardiff Bridge Wiring Cost, I wrote about how two simple techniques; an insulating coating and surge arresters, saved about ten million pounds, by avoiding a bridge reconstruction.

How much can be saved on electrification schemes by using simple and proven techniques like these?

Better Surveying And Site Information

A lot of the UK’s railways are like long Victorian buildings.

If you’ve ever tried to renovate a cottage that was built around the middle of the nineteenth century, you will understand the following.

  • It is unlikely you will have any accurate plans.
  • Some of the construction will be very good, but other parts will be downright shoddy.
  • You have no idea of the quality of the foundations.
  • If the building is Listed you’ll have a whole new level of bureaucracy to deal with.

Now scale your problems up to say a ten mile stretch of rail line, that needs to be electrified.

Instead of dealing with a cottage-sized plot, you may now be dealing with the following.

  • A double track railway with four train per hour (tph) in both directions.
  • A site that is several miles long.
  • Access to the work-site could be difficult.

So just surveying what has to be done and making sure you have details on any unforeseen underground structures like sewers, gas and water mains and old mine workings, can be a major undertaking.

Reading local newspaper reports on the Gospel Oak to Barking electrification, you get the impression the following happened.

  • Various overhead gantries were built to the wrong size.
  • A sewer was found, that had been missed by surveyors.
  • It was wrongly thought that the bridge at Crouch Hill station had sufficient clearance for the electrification. So much more work had to be done.

At least there weren’t any mine workings in East London, but as you can imagine these are a major problem in areas in the North.

Surely, nearly twenty years into the 21st century, we can avoid problems like these.

Discontinuous Electrification

Low bridges and and other structures crossing the tracks, can be  a big and expensive problem, when it comes to electrifying railway lines.

In the proposed electrification of the lines for the South Wales Metro, look at these statistics.

  • A total of 172 km. of track will be electrified.
  • Fifty-six structures were identified as needing to be raised.

The cost savings of eliminating some of this bridge raising would not be small.

In the July 2018 Edition of Modern Railways, there is an article entitled KeolisAmey Wins Welsh Franchise.

This is said about the electrification on the South Wales Metro.

KeolisAmey has opted to use continuous overhead line equipment but discontinuous power on the Core Valley Lnes (CVL), meaning isolated OLE will be installed under bridges. On reaching a permanently earthed section, trains will automatically switch from 25 KVAC overhead to on-board battery supply, but the pantograph will remain in contact with the overhead cable, ready to collect power after the section. The company believes this method of reducing costly and disruptive engineering works could revive the business cases of cancelled electrification schemes. Hopes of having money left over for other schemes rest partly on this choice of technology.

In the final design, KeolisAmey have been able to use this discontinuous power solution at all but one of the fifty-six structures.

These structures will be checked and refurbished as required, but they would be unlikely to need lengthy closures, which would disrupt traffic, cyclists and walkers.

Each structure would need a bespoke structure to create a rail or wire on which the pantograph, would ride from one side of the structure to the other. But installing these would be a task of a much smaller magnitude.

There must be a lot of scope for both cost and time savings.

I think in the future, when it comes to electrifying existing lines, I think we’ll increasing see, this type of discontinuous electrification used to avoid rebuilding a structurally-sound bridge or structure.

I also think, that experience will give engineers a more extensive library of solutions.

Hopefully, costs could be driven downwards, instead of spiralling upwards!

Complimentary Design Of Trains And New Electrified Routes

In recent years two major electric rail projects have been planned, which have gone much further than the old philosophy of just putting up wires and a adding fleet of new trains.

I believe that the Crossrail Class 345 trains and the tunnel under London were designed to be complimentary to each other to improve operation and safety and cut operating costs.

But the interesting project is the South Wales Metro, where discontinuous electrification and battery power have been used to design, what should be a world-class metro at an affordable cost.

Too many electrification schemes have been designed by dull people, who don’t appreciate the developments that are happening.

Conclusion On Recent Developments

UK railways are doing better on electrification than many think.

Possible Developments

These are ideas I’ve seen talked about or are my own speculation.

Intelligent Discontinuous Third Rail Electrification

New third rail electrification is not installed much these days, due to perceived safety problems.

I have seen it proposed by respected commentators, that third rail electrification could play a part in the charging of train batteries.

Discontinuous third-rail electrification is already used extensively, at places like level crossings and where a safe route is needed for staff to cross the line.

But it is done in a crude manner, where the contact shoes on the train run up and down the sloping ends of the third rail.

As a time-expired Control Engineer, I’m fairly sure that a much better, safer system can be designed.

On the South Wales Metro, where discontinuous overhead electrification is to be used, battery power will be used to bridge the gaps.

Supposing trains on a third-rail electrified route, were fitted with batteries that gave the train a range of say two kilometres. This would give sufficient range to recover a train, where the power failed to a safe evacuation point.

The range on battery power would mean that there could be substantial gaps between sections of electrification, which would be sized to maximise safety, operational efficiency and minimise energy use.

Each section of electrification would only be switched on, when a train was present.

Train drivers could also have an emergency system to cut the power in a particular section, if they saw anything untoward, such as graffiti artists on the line.

Third Rail Electrification In Stations

I have seen it proposed by respected commentators, that third rail electrification could play a part in the charging of train batteries.

When you consider that trains often spend fifteen or twenty minutes at a terminal station, it could make it easier to run electric or bi-mode trains with batteries on branch lines.

The rail would normally be switched off and would only be switched on, when a train was above and connected to the rail.

As a time-expired Control Engineer, I’m fairly sure that a safe system can be designed.

Third Rail Electrification On Viaducts

To some overhead electrification gantries on top of a high viaduct are an unnecessary eyesore.

So why not use third-rail electrification, on top of viaducts like these?

Trains would need to be able to swap efficiently and reliably between modes.

Gravity-Assisted Electrification

For a country with no really high mountains, we have quite a few railways, that have the following characteristics.

  • Heavily-used commuter routes.
  • Double-track
  • A height difference of perhaps two hundred metres.

These are a few examples.

  • Cardiff Queen Street to Aberdare, Merthyr Tydfil, Rhymney and Treherbert
  • Exeter to Barnstaple
  • Glasgow Central to East Kilbride
  • Manchester to Buxton

All are in areas, where putting up overhead gantries may be challenging and opposed by some campaigners.

As an example consider the Manchester to Buxton route.

  • The height difference is 220 metres.
  • One of Northern’s Class 319 trains weighs 140.3 tonnes.
  • These trains have a capacity of around 320 passengers.
  • If each passenger weighs 90 Kg with baggage, bikes and buggies, this gives a train weight of 167.3 tonnes.

These figures mean that just over 100 kWh of electricity would be needed to raise the train to Buxton.

Coming down the hill, a full train would convert the height and weight into kinetic energy, which would need to be absorbed by the brakes. Only small amounts of new energy would need to be applied to nudge the train onto the hill towards Manchester.

The brakes on trains working these routes must take a severe hammering.

Supposing, we take a modern train with these characteristics.

  • Four cars.
  • Electric traction.
  • 200 kWh of battery capacity to handle regenerative braking.

Such a train would not be a difficult design and I suspect that Bombardier may already have designed an Aventra with these characteristics.

Only the uphill line would be electrified and operation would be as follows.

  • Climbing to Buxton, the train would use power from the electrification.
  • On the climb, the train could also use some battery power for efficiency reasons.
  • The train would arrive at Buxton with enough power left in the batteries to provide hotel power in the stop at Buxton and nudge the train down the hill.
  • On the descent, regenerative braking would be used to slow the train, with the energy created being stored in the batteries.
  • On the level run to Manchester, battery power could be used, rather than electrification power to increase efficiency.

How efficient would that be, with respect to the use of electricity?

I would also investigate the use of intelligent third-rail electrification, to minimise visual impact and the need to raise any bridges or structures over the line.

Gravity is free and reliable, so why not use it?

We don’t know the full

Conclusion On Possible Developments

Without taking great risks, there are lots of ideas out there that will help to electrify routes in an affordable manner.

Conclusion

I very much feel we’ll be seeing more electrification in the next few years.

 

 

 

 

 

 

 

 