Stone Crossing Station – June 27th 2022

I changed trains yesterday at Stone Crossing station and took these pictures.

Note.

  1. It is a basic station with two long platforms.
  2. There is a bridge at one end.
  3. More houses are being built nearby, behind the trees.

It needs upgrading to the Twentieth Century.

A Second Visit To Stone Crossing Station

As I wanted to look at the footbridge, I went back again today.

This looks very much like an interim design to get passengers and pedestrians across the line safety.

A Crossrail To Ebbsfleet Station

This station will need to be made step-free, if Crossrail is extended to Ebbsfleet station.

The station will be handling ten trains per hour (tph) in both directions.

 

 

June 28, 2022 Posted by | Transport/Travel | , , , , | 1 Comment

Northfleet Station – June 27th 2022

This Google Map shows Northfleet station.

Note.

  1. The two tracks through the station are the North Kent Line.
  2. The other two tracks are freight sidings.
  3. The car-parks at Ebbsfleet station are in the South-West corner of the map.
  4. There appears to be a large cleared site to the North-West of the station.

These pictures show the station.

Northfleet station is best characterised by a series of negatives.

  • No step-free access from street-to-platform.
  • No step-free access from platform-to-train.
  • No train information on the London-bound platform.
  • No toilets.
  • No ticket office.
  • No staff
  • Not enough seats.
  • Not enough car parking.
  • Not enough trains.

The only thing that is ready for Crossrail are the long platforms, which will take a 240 metre long train.

A Crossrail To Ebbsfleet Station

This station will need to be made step-free, if Crossrail is extended to Ebbsfleet station.

The station will be handling ten trains per hour (tph) in both directions, with 4 tph terminating at the station.

I suspect new platforms will be built to accommodate the terminating trains.

 

June 27, 2022 Posted by | Transport/Travel | , , , | 4 Comments

Swanscombe Station – June 27th 2022

I went to Swanscombe station today and took these pictures.

Note.

  1. The station is just two long platforms with steps down from the road, that goes across the bridge, that is shown in the pictures.
  2. Whilst I was at the station, a couple had great difficulty bringing a baby in a buggy down the stairs on the Eastbound platform.

This Google Map shows the station in detail.

This station is a real insult to anybody with reduced mobility.

A Second Visit To Swanscombe Station

As it was so bad, I went back again today.

As it’s Tennis Time – You Cannot Be Serious!!

A Crossrail To Ebbsfleet Station

This station will need to be made step-free, if Crossrail is extended to Ebbsfleet station.

The station will be handling ten trains per hour (tph) in both directions.

 

June 27, 2022 Posted by | Transport/Travel | , , , , | 1 Comment

Elizabeth Line To Ebbsfleet Extension Could Cost £3.2 Billion

The title of this post, is the same as that of this article on Ian Visits.

These is the first paragraph.

A report looking at transport upgrades across the southeast of England suggests that extending the Elizabeth line into Kent would cost around £3.2 billion. The report, by Transport for the South East (TfSE) also supports the proposal and looks at how it could be funded.

This image from the Abbeywood2Ebbsfleet consultation, shows the proposal.

Note, that there doesn’t appear to be too much new infrastructure, except for a proper connection between Northfleet and Ebbsfleet stations. References on the Internet, say that the similar-sized Luton DART connection at Luton Airport, cost around £225 million.

As the quoted cost is £3.2 billion, I would assume, that  installation of digital signalling on the North Kent Line and the trains that use it, is one of the major costs.

I have some thoughts.

Improvement Is Needed

There are endless jokes, which have a punchline something like, “If you want to go to X, I wouldn’t start from here.”

On Monday, I intend to go to visit my friend; Ian, who lives at Longfield in Kent. Abbey Wood is the nearest Elizabeth Line station to Longfield and it is only seventeen miles away from Abbey Wood, but the quickest way you can do it by train is 64 minutes with a change at Rochester or 79 minutes going back into London and coming out from Victoria.

As before, I leave London, I will be having breakfast with another friend in Moorgate, the Elizabeth Line to Abbey Wood will be a good place to start.

If I got the trains right, I can get between Moorgate and Northfleet in 41 minutes. Northfleet is just 5.5 miles from Longfield.

If Ian, wants to go to London, he usually drives to Ebbsfleet, where there is lots of parking and gets the Highspeed trains to Stratford or St. Pancras. Trains take 12 and 19 minutes to and from the two London termini, but go nowhere near to Canary Wharf, the City of London, Liverpool Street, Oxford Street, Paddington, West London and Heathrow.

I believe that for Ian and the other nearly million residents of West Kent, that the following should be done as soon as possible.

  • Extend the Elizabeth Line to Gravesend, which would give 300,000 more people a local Elizabeth Line station.
  • Build a people-mover between Northfleet and Ebbsfleet stations, which would create a high-capacity rail hub for North-West Kent, with connections to London, Heathrow and the Continent, and massive parking.

Heathrow and Northfleet would take under an hour and a quarter on a direct train.

Current Services Between Abbey Wood And Gravesend

Currently, these services run at some point on the North Kent Line between Abbey Wood And Gravesend stations.

  • Southeastern – London Cannon Street and London Cannon Street  – 2 tph – Via Abbey Wood, Belvedere, Erith and Slade Green.
  • Southeastern – London Cannon Street and Dartford – 2 tph – Via Abbey Wood, Belvedere, Erith, Slade Green and Dartford.
  • Southeastern – London Charing Cross and Gravesend – 2 tph – Via Dartford, Stone Crossing, Greenhithe, Swanscombe, Northfleet and Gravesend.
  • Southeastern HighSpeed – London St Pancras and Ramsgate via Faversham – 1 tph – Via Ebbsfleet International and Gravesend.
  • Thameslink – Luton and Rainham – 2 tph – Via Abbey Wood, Slade Green, Dartford, Stone Crossing, Greenhithe, Swanscombe, Northfleet and Gravesend.

Note.

  1. tph is trains per hour.
  2. I have only indicated stations, where trains stop between Abbey Wood and Gravesend stations.

Aggregating these trains gives the following totals for each station.

  • Abbey Wood – 6 tph
  • Belvedere – 4 tph
  • Erith – 4 tph
  • Slade Green – 6 tph
  • Dartford – 6 tph
  • Stone Crossing – 4 tph
  • Greenhithe – 4 tph
  • Swanscombe – 4 tph
  • Northfleet – 4 tph
  • Gravesend – 5 tph

As stations get at least four tph, with more important ones getting 5 or 6 tph, it appears to be a well-constructed timetable.

Effect Of Changing The London Cannon Street And London Cannon Street From The Erith Loop To A Dartford Service

This should make no difference to the numbers, as the service is now clear of the Elizabeth Line after Slade Green.

Effect Of Cutting Back The London Charing Cross and Gravesend Service To Dartford

This service between London Charing Cross and Gravesend has a frequency of 2 tph and calls at Dartford, Stone Crossing, Greenhithe, Swanscombe, Northfleet and Gravesend.

Cutting it back to Dartford adjusts the totals as follows.

  • Abbey Wood – 6 tph
  • Belvedere – 4 tph
  • Erith – 4 tph
  • Slade Green – 6 tph
  • Dartford – 4 tph
  • Stone Crossing – 2 tph
  • Greenhithe – 2 tph
  • Swanscombe – 2 tph
  • Northfleet – 2 tph
  • Gravesend – 3 tph

Some of the frequencies have halved.

Effect Of Adding Eight tph To Northfleet And Four tph To Gravesend On The London Charing Cross and Gravesend Service

The Elizabeth Line Extension is proposed to add the following trains to the service.

  • 8 tph will continue from Abbey Wood to Northfleet.
  • 4 tph will continue from Abbey Wood to Gravesend.

This adjusts the totals as follows.

  • Abbey Wood – 6 tph
  • Belvedere – 12 tph
  • Erith – 12 tph
  • Slade Green – 14 tph
  • Dartford – 12 tph
  • Stone Crossing – 10 tph
  • Greenhithe – 10 tph
  • Swanscombe – 10 tph
  • Northfleet – 10 tph ( 4 tph – Terminating, 6 tph – Passing through)
  • Gravesend – 7 tph ( 4 tph – Terminating, 3tph – Passing through)

Note.

  1. These surely are frequencies, that will satisfy the most picky traveller.
  2. There are freight trains running on the route.
  3. The tightest section would appear to be between Abbey Wood and Dartford, although Dartford and Northfleet is only two tph less.
  4. West of Northfleet it gets easier.
  5. But I do think though, that full digital signalling between Abbey Wood and Gravesend would be able to handle it.
  6. 14 tph is a frequency that is less than that of the central sections of the East London Line, the Elizabeth Line and Thameslink.
  7. I have flown my virtual helicopter along the line and there may be places to add a third track, which would add more capacity.

I believe that it is possible to achieve the passenger train frequencies in the last table.

Abbey Wood East Junction

This Google Map shows the track layout to the East of Abbey Wood station.

Note.

  1. There are crossovers so trains can run between the Elizabeth Line platforms on the North side of Abbey Wood station and the North Kent Line.
  2. There is space on either side of the railway.
  3. I have my doubts that the current track layout would be able to handle twelve Elizabeth Line, six North Kent Line and possibly a freight train in every hour, especially where flat junctions are involved.

I can see a flyover or dive-under being built in this area to handle the trains efficiently.

Abbey Wood Power Change-Over

Some thoughts.

  • I will assume, that the change-over between 25 KVAC overhead and 750 VDC third-rail power will take place in or near Abbey Wood station.
  • This would avoid any erection of electrification gantries to the East of Abbey Wood station.
  • If the Office of Road and Rail refuse to allow any more third rail, I could see a Headbolt Lane solution being applied, where batteries are used to bridge the 1.4 mile gap between Abbey Wood station with its 25 KVAC overhead electrification and Belvedere station with its 750 VDC third-rail electrification.
  • North Kent Line trains would take their existing route between Abbey Wood and Belvedere stations.
  • Also, if a comprehensive and efficient track layout is used here, then there might be cost savings if the Elizabeth Line trains supplied their own power from batteries.

An efficient junction to the East of Abbey Wood station, coupled with well-thought out electrification could be key to successfully handling the nearly 20 tph at Abbey Wood station.

Belvedere, Erith And Slade Green Stations

Belvedere, Erith and Slade Green stations are on a double-track section of the line.

  • The three stations are not step-free.
  • There appear to be a lot of industrial sites, that could be developed for housing.
  • There might be the possibility of adding an extra track in places.
  • Luckily, there are no level crossings.
  • There are some footbridges over the railway, that probably need updating to step-free

I suspect that developing the housing on this route will be most important.

Slade Green Depot

This Google Map shows Slade Green depot and the large triangular junction opposite the depot.

Note.

  1. Slade Green station is at the top of the map.
  2. Slade Green depot is in the South-East corner of the map.
  3. The West point of the junction leads to Bexleyheath.
  4. The West and North points of the junction are connected by the Erith Loop.
  5. The South point of the junction leads to Dartford.

There are rail capacity problems in this area.

  • Slade Green depot is not big enough.
  • One train service goes both ways on the Erith Loop between Slade Green and Bexleyheath every thirty minutes, which could be a block on increasing train frequencies between Abbey Wood and Dartford stations.
  • The proposal is saying that the Slade Green and Bexleyheath service will go via Dartford station, where it will probably reverse.

I can see comprehensive redevelopment of the depot and the junction to remove the capacity problems and perhaps build a lot of housing.

  • If the Erith Loop is not used could the centre of the junction be developed with a much-needed extension to the depot?
  • The depot might be moved elsewhere or perhaps rebuilt with tower blocks on the top.

I think that moving the Slade Green and Bexleyheath service via Dartford could mean that the Erith Loop isn’t needed, so this might free up space to increase the size of the depot.

Dartford Station

This Google Map shows Dartford station and the area around the station.

Note.

  1. The station has four long platforms.
  2. It should be able to handle the 12 tph in both directions.
  3. There is a lot of new developments by the station.
  4. The station is step-free.
  5. There are some pictures of Dartford station in Dartford Station – June 27th 2022.

But I do suspect that the station probably needs extra capacity and a substantial rebuild.

Stone Crossing, Greenhithe And Swanscombe Stations

Stone Crossing, Greenhithe and Swanscombe stations will be handling 10 tph.

  • Greenhithe is a new station with full step-free access.
  • But Stone Crossing and Swanscombe stations may need improvement to bring them up to Elizabeth Line standards.
  • More details of Stone Crossing station are given in Stone Crossing Station – June 27th 2022.
  • More details of Greenhithe station are given in Bluewater Shopping Centre By Train.
  • More details of the current state of Swanscombe station are given in Swanscombe Station – June 27th 2022.
  • The one level crossing in the area was closed in 2018.
  • There may be scope to add an extra track at places in this section.

I feel that these three stations could be fairly easy to bring up to the required standards.

Northfleet Station

Northfleet station is a station, which in the words of estate agent; Roy Brooks, would have a lot of potential.

This Google Map shows the station.

Note.

  1. The two tracks through the station are the North Kent Line.
  2. The other two tracks are freight sidings.
  3. The car-parks at Ebbsfleet station are in the South-West corner of the map.
  4. There appears to be a large cleared site to the North-West of the station.

These pictures show the station.

The requirements for the station will be as follows.

  • The ability to handle 6 tph passing through.
  • The ability to be able to handle 4 tph, that terminate at the station.
  • Terminating four tph, will probably need two platforms for all eventualities.
  • Full step-free access.
  • An interchange with Ebbsfleet International station is also needed.
  • Is car parking needed?

There is certainly enough space.

The Pedestrian Link Between Northfleet And Ebbsfleet Stations

This is part of the plan and is shown on the first map in this post.

This Google Map shows Northfleet and Ebbsfleet stations.

Note.

  1. The large Ebbsfleet International station towards the bottom of the map.
  2. Northfleet station on the North Kent Line in the North East corner of the map.
  3. The two stations are about five hundred  metres apart as the  crow flies.

There has been a lot of pressure in the past to build a pedestrian link between the two stations, as reported by the Wikipedia entry for Northfleet station.

The station is very close to Ebbsfleet International station (the NNE entrance is only 334 yards (305 m) from Northfleet’s station), but passengers (using public transport) will find it far easier to access Ebbsfleet International from Gravesend or Greenhithe, as these stations are more accessible and offer easy access to Fastrack bus services. The walking route between the two stations is 0.6 miles (1 km) or 0.8 miles (1.3 km) and a suitable pedestrian link has not been built because of funding issues and objections from Land Securities.

Why when Ebbsfleet International station was built in the early 2000s for opening in 2007, was a pedestrian link not built between the two stations?

How much did omitting the link save?

Luton Airport are building the Luton DART, which is a people mover to  connect Luton Airport Parkway station with the airport.

  • It is 1.4 miles long.
  • It is fully automated.
  • It might have an extra station serving the mid-stay parking.
  • It appears to be taking three years to build.

All of this very comprehensive system appears to be costing around £200 million.

I doubt that a simple pedestrian link, like a bridge with travellators,  would have cost more than a few tens of million pounds.

Will Northfleet/Ebbsfleet Become A Major Railway Hub?

If Northfleet station and the connection to Ebbsfleet is well designed,, I can see this station becoming a major railway hub.

  • It would have Eurostar Continental services.
  • It would have HighSpeed services to London and Kent.
  • It would have Elizabeth Line services to London and Heathrow.
  • It would have Thameslink and Southeastern services.
  • The station would have lots of parking.

I also feel in the future that more Continental services will be developed.

  • Adding extra platforms for Continental services could be easier than at St. Pancras.
  • It could be an ideal terminus for sleeper trains to and from the Continent.
  • I might be the ideal terminus for very long distance trains to and from the Continent.

Northfleet/Ebbsfleet has something that St. Pancras lacks – space.

Gravesend Station

Gravesend station is a rebuilt step-free station with three platforms, as these pictures show.

But is it the right station, for the end of the Elizabeth Line?

These points are in favour.

  • There is a bay platform, that could handle 4 tph.
  • The station is step-free.
  • The station has had a recent refurbishment.
  • It has HighSpeed services to London and East Kent.
  • Gravesend is a town of 74,000 people.
  • Passengers can change between through trains by just staying on the same platform.

But these points are against.

  • The station is on a cramped site in the town centre.
  • There is no train stabling nearby.
  • Adding lots of car parking may be difficult.
  • Suppose adding the Elizabeth Line to the town was very successful and it was felt more services were needed. Could Gravesend station cope?

These are the times for the various services.

  • HighSpeed to St. Pancras – 25 minutes
  • HighSpeed to Stratford – 17 minutes
  • Southeastern to Charing Cross – 65 minutes
  • Thameslink to Abbey Wood- 28 minutes
  • Thameslink to London Bridge – 60 minutes

I estimate that the Elizabeth Line will take just over 50 minutes to Tottenham Court Road.

This last timing in itself is a good reason for the Elizabeth Line to serve Gravesend.

But I don’t think the Elizabeth Line has to start there.

I am worried that the Elizabeth will be too successful.

  • It serves Central London, Paddington and Heathrow.
  • It will have a frequency of four tph from and to Gravesend.
  • It will have trains with a very large capacity.
  • The trains will have wi-fi and 4G connections.

I don’t think the cramped Gravesend station will be able to cope with the needs of expansion.

  • An extra platform.
  • Handling trains that need to be turned back to London.
  • More car parking.

Northfleet/Ebbsfleet will have the parking and eight tph on the Elizabeth Line, so surely the best solution is to have the actual Elizabeth Line terminal station to the East of Gravesend.

  • Travellers to the West of Gravesend will use Northfleet/Ebbsfleet.
  • Travellers in Gravesend will use Gravesend station by walking, cycling or using a local bus.
  • Travellers to the East of Gravesend will use the new terminal station.

The Elizabeth Line extension is supposedly costing £3.2 billion, so it should serve as many potential passengers as possible.

The Elephant In The Garden Of England

It is proposed that the new Lower Thames Crossing is built to the East of Gravesend.

This map from the Department of Transport, shows the route.

Note.

  1. The new crossing, which is shown in red, bypasses the Dartford Crossing on the M25.
  2. The A226 runs between Gravesend and Higham via a junction with the new crossing at Chalk.
  3. Northfleet is to the West of Gravesend.

This Google Map shows the area between Chalk and Higham.

Note.

  1. Chalk in the North-West corner of the map.
  2. Higham in the South-East corner of the map.
  3. The A226 running between Chalk and Higham.
  4. Higham station on the North Kent Line about half-way up the East side of the map.
  5. The North Kent Line running across the top of the map between Gravesend and Higham stations via Hoo Junction.

The Lower Thames Crossing will run North-South across this map to the East of Chalk and according to the Department of Transport map to the West of Thong.

I should admit, that I don’t drive, so the Lower Thames Crossing will be of no use to me, but I have friends in Kent and most seem to be in favour of the new crossing.

Reopening The Hoo Branch To Passenger Trains

In Effort To Contain Costs For Hoo Reopening, I wrote about an article in the April 2022 Edition of Modern Railways with the same title.

This is the first paragraph of the Modern Railways article..

Medway Council is working with Network Rail and other industry players in an effort to make restoration of a passenger service to Hoo on the Isle of Grain branch feasible. The Council was awarded £170 million from the Housing Infrastructure Fund in 2020 to support schemes to facilitate building of 12,000 new houses in the area, with £63 million of the HIF money for reinstatement of services on the Hoo Branch.

The article mentions, this new infrastructure.

  • A new station South of the former Sharnal Street station.
  • Works to level crossings, of which there are six between Gravesend station and proposed site of the new Hoo station.
  • A passing place at Hoo Junction, where the branch joins the North Kent Line.
  • A passing place at Cooling Street.

It looks like we may have the smaller project of reopening the Hoo branch railway, whilst a major road and tunnel is built through the area.

This OpenRailwayMap shows the North Kent Line between Gravesend and Higham stations.

Note.

  1. Gravesend station is in the North-West corner of the map.
  2. Higham station is at the Eastern edge of the map.
  3. The railway shown in orange is the North Kent Line.
  4. The railway shown in yellow is the Hoo branch.
  5. The railway shown in red is the Channel Tunnel Rail Link.

It looks like the path of the new crossing could follow a similar path to the overhead power cable shown on this map.

According to Modern Railways, the main reason for reopening the Hoo Branch for passenger trains is to provide rail access for new housing on the Isle of Grain.

  • Improving the Hoo branch will also help the freight services to the various docks and installations on the Isle of Grain.
  • Will the builders of the new crossing, use the Isle of Grain for the supply of aggregates and the disposal of tunnel spoil?
  • Remember that barges on the Thames were used to remove the tunnel spoil from London for both Crossrail and the Battersea extension to the Northern Line.

My knowledge of major projects is saying to me, that before the major works of the new crossing are started, this branch railway must be updated, otherwise it will cause problems in the future.

Could this be why, the Hoo branch reopening has been mentioned in both the April and July 2022 Editions of Modern Railways? Perhaps a sensible decision has been made, that means the Hoo branch will be improved first, to speed the construction of the new Lower Thames Crossing.

Could The Elizabeth Line Be Extended To The Proposed Hoo Station?

The proposed Hoo station is to be just South of the former Sharnal Street station.

  • This is under ten kilometres from Hoo Junction, where the North Kent Line is electrified.
  • A single platform could handle 4 tph, but provision for two platforms would be prudent.
  • A couple of sidings could provide stabling.
  • Services would join the North Kent Line at Hoo Junction.
  • Services would use battery power between Hoo Junction and Hoo station.
  • If charging were needed at Hoo station a short length of 25 KVAC overhead electrification would be needed.
  • There is plenty of power available locally to power any electrification.

This Google Map shows the possible location of the station.

Note.

  1. The A 289 road running NE-SW across the map from a roundabout in the North-East corner of the map.
  2. The A 289 leads from the roundabout in the South-West corner of the map to the Medway Tunnel to Chatham.
  3. Sharnal Street is between the two roundabouts.
  4. The single-track railway crosses the A 289 at right-angles, about 500 metres South of Sharnal Street.
  5. There is even a high voltage power line  going through the area to the South of the railway.

It seems to be an ideal place for a station with good road access, space and plenty of power to charge battery vehicles and trains.

I took these pictures of where the A289 crosses over the railway on June 27th 2022.

Note.

  1. The substation site, which is marked with Network Rail logos. It looks like power has been provided to the site.
  2. The high-voltage line passing to the South of the site.
  3. There were trucks carrying tunnel segments. Is there a factory on the Isle of Grain and will it produce segments for the Lower Thames Crossing?
  4. The Sharnal Street bridge over the railway.

It certainly looks like Network Rail have been planning a station there for some time.

Around The Isle Of Grain

I took these pictures of the Isle of Grain on June 27th 2022.

Note.

  1. There is a lot of housing planned on the island.
  2. Someone wants to build a theme park.
  3. The road past the station leads to the Medway Tunnel.

All these factors would add to the case for the station.

Battery-Electric Class 345 Trains

There would be a need to develop a third-rail battery/electric version of the Class 345 trains.

In this article in Global Rail News from 2011, which is entitled Bombardier’s AVENTRA – A new era in train performance, gives some details of the Aventra’s electrical systems. This is said.

AVENTRA can run on both 25kV AC and 750V DC power – the high-efficiency transformers being another area where a heavier component was chosen because, in the long term, it’s cheaper to run. Pairs of cars will run off a common power bus with a converter on one car powering both. The other car can be fitted with power storage devices such as super-capacitors or Lithium-ion batteries if required. The intention is that every car will be powered although trailer cars will be available.

Unlike today’s commuter trains, AVENTRA will also shut down fully at night. It will be ‘woken up’ by remote control before the driver arrives for the first shift

This was published over eleven years ago, so I suspect Bombardier have refined the concept.

A Simple Extension Of The Elizabeth Line

The branch to Hoo station could be a very simple extension of the Elizabeth Line.

  • There appear to be no challenging engineering problems.
  • Parking and cycling routes could be provided as required at the station.
  • The centre of Gravesend would be under ten minutes from Hoo station.
  • There would be a same-platform change for HighSpeed services at Gravesend station.
  • The developers of the housing would be over the moon.
  • Workers for the Lower Thames Crossing and the big energy projects on the Isle of Grain could reverse commute from London.
  • The station would only be a few minutes more than an hour from Central London.
  • The station could also double as a Park-and-Ride for Chatham and Gillingham.
  • Buses could connect Hoo station to Chatham and Gillingham.

It could prove to be a very valuable station for the Isle of Grain and the Medway Towns.

The Contactless Ticketing Conundrum

This is said on the Transport for London website.

Contactless pay as you go is accepted throughout the Elizabeth line.

So it’s just a case of Have Card Will Travel!

So this will mean, that contactless ticketing will have to be accepted at all stations East of Abbey Wood.

Everybody will love that!

Are There Any Other Possible Elizabeth Line Destinations In Kent?

Train companies, since the days of British Rail have run Peak time commuter trains to bring workers into London in the morning and take them home in the evening.

There will be four tph passing through Gravesend and they don’t all have to go to and from Hoo station.

Digital signalling will give flexibility as to which stations the trains could serve.

Possibilities include.

Gillingham

Gillingham station may be a possibility.

Maidstone West

Maidstone West station may be a possibility.

Rainham

Rainham station has three platforms and is already served by two Thameslink tph to Luton through Central London, which use the bay Platform 0

Some might argue that two Elizabeth Line tph should extend from Abbey Wood to Rainham, to give a four tph service between Abbey Wood and Rainham.

This would be a North Kent Metro.

Rochester

Rochester station has three platforms and Platform 3 can turn trains back to London.

It is already used by Thameslink to turn Peak services.

Project Management

The project may be budgeted to cost £3.2 billion, but it is a small number of independent projects.

  • Digital signalling
  • Electrification changeover at Abbey Wood station.
  • An efficient junction East of Abbey Wood.
  • Rebuild Belvedere station with step-free access.
  • Rebuild Erith station with step-free access.
  • Rebuild Slade Green station with step-free access.
  • Extend Slade Green depot.
  • Upgrade Dartford station.
  • Rebuild Stone Crossing station with step-free access.
  • Upgrade Greenhithe station.
  • Upgrade Swanscombe station.
  • Rebuild Northfleet station with step-free access and two extra bay platforms.
  • Install people mover between Northfleet and Ebbsfleet stations.
  • Upgrade the Hoo Branch.
  • Build Hoo station.

Note.

  1. Gravesend station would only need minimal updating.
  2. As I said before, I suspect the digital signalling will be the biggest cost.
  3. Choosing the optimal order is good project management!
  4. Projects that create fare revenue should be done early, especially if they don’t interfere with services on the railway.

The first projects, that I would develop would be these.

  • Rebuild Northfleet station with step-free access and two extra bay platforms.
  • Install people mover between Northfleet and Ebbsfleet stations.
  • Upgrade the Hoo Branch.
  • Build Hoo station.

As I said earlier, this project needs to be developed with the Lower Thames Crossing.

Conclusion

This seems an excellent plan.

 

 

 

 

 

June 25, 2022 Posted by | Transport/Travel | , , , , , , , , , , , , , , , | 9 Comments

Councils Back Cheaper Crossrail Extension Option To Kent

The title of this post, is the same as that as this article on New Civil Engineer.

These two paragraphs describe the preferred scheme.

The council’s opted for the cheaper extension option which would see Crossrail extended from Abbey Wood east to Slade Green, Dartford, Greenhithe and Swancombe before stopping near to HS1 station at Ebbsfleet with a stop at Northfleet.

The report notes: “The preferred scheme is one that would see 8 of the 12 Elizabeth Line trains per hour that are currently planned to terminate at Abbey Wood be extended eastwards, sharing the existing North Kent line tracks with the Southeastern and Thameslink services.

Currently, the following services use the proposed route between Abbey Wood and Northfleet.

  • Southeastern – two tph – London Cannon Street and London Cannon Street via Abbey Wood, Belvedere, Erith and Slade Green.
  • Southeastern – two tph – London Cannon Street and Dartford via Abbey Wood, Belvedere, Erith and Slade Green.
  • Southeastern – two tph – London Charing Cross and Gravesend via Dartford, Stone Crossing, Greenhithe, Swanscombe and Northfleet
  • Thameslink – two tph – Luton and Rainham via Abbey Wood, Slade Green, Dartford, Stone Crossing, Greenhithe, Swanscombe and Northfleet.

Note that tph is trains per hour.

These services provide these frequencies at the stations between Abbey Wood and Northfleet.

  • Abbey Wood – eighteen tph, which assumes twelve tph from Crossrail.
  • Belvedere – four tph
  • Erith – four tph
  • Slade Green – six tph
  • Dartford – four tph
  • Stone Crossing – four tph
  • Greenhithe – four tph
  • Swanscombe – four tph
  • Northfleet – four tph

Note twelve tph from Crossrail terminate at Abbey Wood.

If Crossrail were to run eight tph to Northfleet, this would provide these frequencies at the stations.

  • Abbey Wood – eighteen tph, which assumes twelve tph from Crossrail.
  • Belvedere – twelve tph
  • Erith – twelve tph
  • Slade Green – fourteen tph
  • Dartford – twelve tph
  • Stone Crossing – twelve tph
  • Greenhithe – twelve tph
  • Swanscombe – twelve tph
  • Northfleet – twelve tph

Note four tph from Crossrail terminate at Abbey Wood and eight tph at Northfleet.

These are my thoughts.

A Turnback Facility At Northfleet Station

There will need to be a turnback facility at Northfleet station.

  • It will have to handle eight tph
  • Nine-car Class 345 trains used by Crossrail are 205 metres long.

Eight tph would suggest that two platforms would be needed.

This Google Map shows Northfleet station.

Note.

  1. The North Kent Line goes diagonally across the map from North-West to South-East.
  2. Northfleet station is a two-platform station.
  3. To the South of the station, there are sidings, which are connected to the North Kent Line.

This picture shows the sidings from Northfleet station, with Ebbsfleet station about a mile away.

It appears that there would be space to add two well-appointed turnback platforms at Northfleet station.

These pictures show some of the features of the current Northfleet station.

Rebuilding to add the turnback facility, could also include.

  • Full step-free access
  • Modern station buildings
  • A deep clean of the pedestrian tunnel.
  • An appropriately-sized bus station, with a zero-carbon shuttle bus to Ebbsfleet station.
  • Future provision for a high-tech people-mover to Ebbsfleet station.

It is not one of the better stations on the Southeastern network.

But it certainly could be!

I very much feel that Northfleet station needs to be rebuilt with at least two extra platforms.

A People-Mover Between Ebbsfleet And Northfleet Stations

I wrote So Near And Yet So Far! about the poor connection between Ebbsfleet And Northfleet stations.

It is a design crime of the highest order.

There has been a lot of pressure in the past to build a pedestrian link between the two stations, as reported by the Wikipedia entry for Northfleet station.

The station is very close to Ebbsfleet International station (the NNE entrance is only 334 yards (305 m) from Northfleet’s station), but passengers (using public transport) will find it far easier to access Ebbsfleet International from Gravesend or Greenhithe, as these stations are more accessible and offer easy access to Fastrack bus services. The walking route between the two stations is 0.6 miles (1 km) or 0.8 miles (1.3 km) and a suitable pedestrian link has not been built because of funding issues and objections from Land Securities.

Why when Ebbsfleet International station was built in the early 2000s for opening in 2007, was a pedestrian link not built between the two stations?

It sounds like it was a Treasury design for Civil Servants, who work in Westminster and wouldn’t dream of living in Gravesend.

How much did omitting the link save?

Probably in the the long term, about two-fifths of five eighths of f***-all!

The specialists in this type of people-mover are the Doppelmayr/Garaventa Group, who in the UK have built the Emirates Air Line and the Air-Rail Link at Birmingham Airport. Currently, they are building the Luton DART people mover.

Wikipedia says that the Emirates Air-Line cost £60 million.

Wouldn’t something similar be an ideal way to welcome people to the UK?

The London Resort

The London Resort, is described like this in its Wikipedia entry.

The London Resort is a proposed theme park and resort in Swanscombe, Kent. The project was announced on 8 October 2012 and, if given planning permission, it is estimated that construction will begin in 2022, with a first gate opening in summer 2024 and a second gate by 2029.

It certainly sounds the sort of place I avoid, but just like Disneyland Paris, I feel the developers will want a rail connection.

They could even want to have another people-mover from Ebbsfleet station.

 

 

November 5, 2021 Posted by | Transport/Travel | , , , , | 4 Comments

An Analysis Of The Train Service On The East Kent Line With Respect To The Three Options For Crossrail To Ebbsfleet (C2E)

Much of the analysis is an update of a post called Up To £3 Billion For Crossrail To Ebbsfleet, that I wrote in June 2019.

Current Services Along The North Kent Line

I shall start by looking at current services on the North Kent Line.

Thameslink – Luton And Rainham (Kent)

A Thameslink service

  • Two trains per hour (tph)
  • South of the Thames, the service calls at London Bridge, Deptford, Greenwich, Maze Hill, Whatcombe Park, Charlton, Woolwich Arsenal, Plumstead, Abbey Wood, Slade Green, Dartford, Stone Crossing, Greenhithe for Bluewater, Swanscombe, Northfleet, Gravesend, Higham, Strood, Rochester, Chatham and Gillingham.
  • Eight-car Class 700 trains work the route, which have a 100 mph operating speed.
  • The service calls at Northfleet for a possible interchange with services running from Ebbsfleet International station
  • The service calls at Abbey Wood for interchange with Crossrail.

If there needed to be more capacity on this service, I suspect Thameslink could run twelve-car trains.

Southeastern – London Charing Cross And Gravesend

Southeastern Metro service.

  • Two tph
  • Calls at Waterloo East, London Bridge, Hither Green, Lee, Mottingham, New Eltham, Sidcup, Albany Park, Bexley, Crayford, Dartford, Stone Crossing, Greenhithe for Bluewater, Swanscombe and Northfleet
  • The service calls at Northfleet for a possible interchange with services running from Ebbsfleet International station.
  • The service calls at Gravesend for interchange with Southeastern HighSpeed services between St. Pancras International station and North-East Kent, East Kent and soon-to-be East Sussex.
  • Class 465 trains work the route, which have a 75 mph operating speed.

This picture shows a train for Gravesend in London Bridge station.

My feeling, is that the service would be improved by modern 100 mph trains, as these antique slow-coaches must restrict the speed of faster trains.

Southeastern – London Cannon Street And Dartford Loop Line

A Southeastern Metro service.

  • Four tph in both directions.
  • Calls at London Bridge, Deptford, Greenwich, Maze Hill, Westcombe Park, Charlton, Woolwich Dockyard, Woolwich Arsenal, Plumstead, Abbey Wood, Belvedere, Erith and Slade Green.
  • Two tph return to Cannon Street via Crayford and Sidcup and two tph return to Cannon Street via Barnehurst and Bexleyheath.
  • The service calls at Abbey Wood for a planned interchange with Crossrail.
  • Class 465 trains work the route.

As I said with the previous service, these 75 mph trains need replacing with 100 mph trains.

Southeastern – London Charing Cross And Dartford

A Southeastern Metro service.

  • Two tph
  • Calls at Waterloo East, London Bridge, Lewisham, Blackheath, Charlton, Woolwich Dockyard, Woolwich Arsenal, Plumstead, Abbey Wood, Belvedere, Erith and Slade Green.
  • The service calls at Abbey Wood for a planned interchange with Crossrail.
  • Class 465 trains work the route.

As I said with the two previous services, these 75 mph trains need replacing with 100 mph trains.

Southeastern – London Victoria And Dover

A Southeastern Mainline service.

  • Two tph
  • Calls on the North Kent Line at Rochester, Chatham, Gillingham and Rainham.
  • Class 465 trains work the route.

As I said with previous services, these 75 mph trains need replacing with 100 mph trains.

Southeastern – London Victoria And Ramsgate

A Southeastern Mainline service.

  • One tph
  • Calls on the North Kent Line at Rochester, Chatham, Gillingham and Rainham.
  • Class 465 trains work the route.

As I said with previous services, these 75 mph trains need replacing with 100 mph trains.

Southeastern – London St. Pancras And Faversham

A Southeastern HighSpeed service.

  • One tph
  • Calls at Stratford International, Ebbsfleet International, Gravesend, Strood, Rochester, Chatham, Gillingham, Rainham and Sittingbourne.
  • The service calls at Ebbsfleet International for an interchange with Continental services.
  • Class 395 trains work the route, which have a 100 mph operating speed on lines electrified using a third-rail.

This picture shows a Class 395 train at Gravesend station.

East of Ebbsfleet International, this service can be considered a 100 mph local train, that gets slowed by the 75 mph services.

Southeastern – London St Pancras International Loop Service

A Southeastern HighSpeed service.

  • One tph
  • Calls at Stratford International, Ebbsfleet International, Gravesend, Strood, Rochester, Chatham, Gillingham, Rainham, Sittingbourne, Faversham, Whitstable, Herne Bay, Birchington-on-Sea, Margate, Broadstairs, Ramsgate, Sandwich, Deal, Walmer, Martin Mill, Dover Priory, Folkestone Central, Folkestone West, Ashford International, Ebbsfleet International and Stratford International.
  • The service calls at Ebbsfleet International and Ashford International for an interchange with Continental services.
  • Class 395 trains work the route.

East of Ebbsfleet International, this service can be considered a 100 mph local train, that gets slowed by the 75 mph services.

Southeastern – London St Pancras International And Ramsgate

A Southeastern HighSpeed service.

  • One tph
  • Calls at Stratford International, Ebbsfleet International, Ashford International, Canterbury West, Ramsgate and Broadstairs
  • The service calls at Ebbsfleet International and Ashford International for an interchange with Continental services.
  • Class 395 trains work the route.

East of Ashford International, this service can be considered a 100 mph local train, that gets slowed by the 75 mph services.

A Summary Of Services By Station

I will look at the current number of trains at stations between London Bridge and Faversham.

  • Deptford – 6 tph
  • Greenwich – 6 tph
  • Maze Hill – 6 tph
  • Westcombe Park – 6 tph
  • Charlton – 8 tph
  • Woolwich Dockyard – 6 tph
  • Woolwich Arsenal – 8 tph
  • Plumstead – 8 tph
  • Abbey Wood – 8 tph
  • Belvedere – 6 tph
  • Erith – 6 tph
  • Slade Green – 6 tph
  • Dartford – 12 tph to London and 6 tph to the East
  • Stone Crossing – 4 tph
  • Greenhithe for Bluewater – 6 tph
  • Swanscombe – 4 tph
  • Northfleet – 4 tph
  • Gravesend – 6 tph to London and 5 tph to the East
  • Higham – 2 tph
  • Strood – 4 tph
  • Rochester – 7 tph
  • Chatham – 7 tph
  • Gillingham – 7 tph
  • Rainham – 7 tph to London and 5 tph to the East
  • Sittingbourne – 5 tph
  • Faversham – 5 tph

Note.

  1. This is almost a train every ten minutes all the way from London to Faversham.
  2. Between Gravesend and Faversham one tph is a Southeastern HighSpeed service.
  3. In addition Ebbsfleet International has four tph to and from London St. Pancras International.

This can be considered the base service to which Crossrail services can be added.

Service Frequency Of Option 1

The first option provides for an extension of Crossrail from Abbey Wood to Northfleet/Ebbsfleet and Gravesend, sharing the existing tracks with National Rail services.

  • Of the 12 trains per hour (tph) that are planned to run to Abbey Wood. four tph will terminate at each of Abbey Wood, Northfleet/Ebbsfleet and Gravesend.
  • Crossrail trains would call at all stations on the North Kent Line between Abbey Wood and Gravesend stations.

This gives a summary as follows.

  • Deptford – 6 tph
  • Greenwich – 6 tph
  • Maze Hill – 6 tph
  • Westcombe Park – 6 tph
  • Charlton – 8 tph
  • Woolwich Dockyard – 6 tph
  • Woolwich Arsenal – 8 tph
  • Plumstead – 8 tph
  • Abbey Wood – 20 tph
  • Belvedere – 14 tph
  • Erith – 14 tph
  • Slade Green – 14 tph
  • Dartford – 20 tph to London and 14 tph to the East
  • Stone Crossing – 12 tph
  • Greenhithe for Bluewater – 14 tph
  • Swanscombe – 12 tph
  • Northfleet – 12 tph
  • Gravesend – 10 tph to London and 5 tph to the East
  • Higham – 2 tph
  • Strood – 4 tph
  • Rochester – 7 tph
  • Chatham – 7 tph
  • Gillingham – 7 tph
  • Rainham – 7 tph to London and 5 tph to the East
  • Sittingbourne – 5 tph
  • Faversham – 5 tph

Note.

  1. Train frequencies between Abbey Wood and Northfleet have increased by 8 tph
  2. Train frequencies at Gravesend have increased by 4 tph.
  3. Train frequencies to the East of Gravesend are unchanged.
  4. Between Gravesend and Faversham one tph is a Southeastern HighSpeed service.
  5. Crossrail has a direct interchange at Gravesend with the Southeastern HighSpeed services.

I am fairly certain that signalling must be improved and train speeds must be increased for Option 1.

Service Frequency Of Option 2

The second option is to draw out Crossrail from south east London to Dartford using new dedicated tracks built next to the existing North Kent line, with increased rail service frequency between Dartford and Northfleet.

  • All the 12 tph, that currently are planned to run ro Abbey Wood, all will terminate at Dartford station.
  • Crossrail trains would call at all stations on the North Kent Line between Abbey Wood and Dartford stations.
  • I will assume that Southeastern run an extra 4 tph between Dartford and Northfleet.

This gives a summary as follows.

  • Deptford – 6 tph
  • Greenwich – 6 tph
  • Maze Hill – 6 tph
  • Westcombe Park – 6 tph
  • Charlton – 8 tph
  • Woolwich Dockyard – 6 tph
  • Woolwich Arsenal – 8 tph
  • Plumstead – 8 tph
  • Abbey Wood – 20 tph
  • Belvedere – 18 tph
  • Erith – 18 tph
  • Slade Green – 18 tph
  • Dartford – 24 tph to London and 10 tph to the East
  • Stone Crossing – 8 tph
  • Greenhithe for Bluewater – 10 tph
  • Swanscombe – 8 tph
  • Northfleet – 8 tph
  • Gravesend – 6 tph to London and 5 tph to the East
  • Higham – 2 tph
  • Strood – 4 tph
  • Rochester – 7 tph
  • Chatham – 7 tph
  • Gillingham – 7 tph
  • Rainham – 7 tph to London and 5 tph to the East
  • Sittingbourne – 5 tph
  • Faversham – 5 tph

Note.

  1. There is a big increase in services to between Abbey Wood and Dartford.
  2. There is an increase of 4 tph in services between Dartford and Northfleet.
  3. There is no increase in services at Gravesend.
  4. Between Gravesend and Faversham one tph is a Southeastern HighSpeed service.
  5. Crossrail has no direct interchange with the Southeastern HighSpeed services.

I am fairly certain that signalling must be improved and train speeds must be increased for Option 2.

Service Frequency Of Option 3

A third option consists of improving the National Rail service between Abbey Wood and Northfleet, combined with a new Bus Rapid Transit service.

  • It appears Crossrail services would stay the same at Abbey Wood, with all twelve tph terminating at the station, as are currently planned.
  • Southeastern services to Dartford via Abbey Wood would be extended to Northfleet. This would increase the number of Southeastern trains to/from London serving stations between Northfleet and Dartford for connection to Crossrail at Abbey Wood from four to eight tph.

This gives a summary as follows.

  • Deptford – 6 tph
  • Greenwich – 6 tph
  • Maze Hill – 6 tph
  • Westcombe Park – 6 tph
  • Charlton – 8 tph
  • Woolwich Dockyard – 6 tph
  • Woolwich Arsenal – 8 tph
  • Plumstead – 8 tph
  • Abbey Wood – 20 tph
  • Belvedere – 6 tph
  • Erith – 6 tph
  • Slade Green – 6 tph
  • Dartford – 8 tph to London and 10 tph to the East
  • Stone Crossing – 8 tph
  • Greenhithe for Bluewater – 10 tph
  • Swanscombe – 8 tph
  • Northfleet – 8 tph
  • Gravesend – 6 tph to London and 5 tph to the East
  • Higham – 2 tph
  • Strood – 4 tph
  • Rochester – 7 tph
  • Chatham – 7 tph
  • Gillingham – 7 tph
  • Rainham – 7 tph to London and 5 tph to the East
  • Sittingbourne – 5 tph
  • Faversham – 5 tph

Note.

    1. There is a 4 tph increase in services between Abbey Wood and Northfleet.
    2. There is no increase in services at Gravesend.
    3. Between Gravesend and Faversham one tph is a Southeastern HighSpeed service.
    4. Crossrail has no direct interchange with the Southeastern HighSpeed services.

I am fairly certain that signalling must be improved and train speeds must be increased for Option 3.

Conclusion

I have come to several small conclusions about future services on the North Kent Line.

Improved Signalling

To handle the number of trains required, I am fairly certain that modern digital signalling as used on the central sections of Crossrail and Thameslink, should be installed on the route.

Faster Trains

The operating speed of the North Kent Line is 90 mph, which is not a good fit to the operating speed of the trains.

I’m sure that train capacity would be increased if trains could operate at 90 mph or even 100 mph on the route.

 

Only Option 1 Allows Interchange Between Crossrail And Southeastern HighSpeed Services

Option 1 allows this interchange at Gravesend and it could prove useful, when travelling between North-East Kent and Crossrail stations, including Paddington and Heathrow.

More Services East Of Gravesend

I suspect that there could be extra paths to the East of Gravesend.

These could be either classic or HighSpeed services.

In Kent On The Cusp Of Change – Highspeed Routes, I said this.

The Kent On The Cusp Of Change article in the July 2017 Edition of Modern Railways talks about the Southeastern Highspeed routes through Kent.

Some principles are laid down.

The article gives an estimate that at least another twenty Class 395 trains are needed of which perhaps three would have batteries for operation along the Marshlink Line between Ashford International and Ore stations.

The new timetable proposed in the article is similar to that now, with the following changes in each hour.

  • All Day – A St. Pancras – Ashford – Dover Priory service runs once per hour and splits at Ashford with one six-car train going to and from Hastings and the other six-car train going to and from Dover Priory.
  • Off Peak – A new St. Pancras – Ashford – Canterbury West service runs once per hour.
  • All Day –  A new St. Pancras – Ebbsfleet service runs twice per hour.
  • Off Peak – A new St. Pancras – Gravesend – Strood – Maidstone West service runs once per hour.

In addition all trains passing Thanet Parkway station will stop after it opens.

Note.

  1. Southeastern HighSpeed services will serve Hastings.
  2. Gravesend gets a second Southeastern HighSpeed service to St. Pancras.

I also wrote Kent On The Cusp Of Change – Fawkham Junction Link, which is about a Network Rail proposal to use Victoria as a second terminal for Southeastern HighSpeed services.

Little has been said about using Victoria as a second terminal, but if it was, it could free up space on the North Kent Lines, which would allow more paths for Crossrail.

 

August 1, 2021 Posted by | Transport/Travel | , , , , , , , , | 2 Comments

Proposals For Crossrail Elizabeth Line Extension To Ebbsfleet Cut Down To Three Options

The title of this post, is the same as that of this article on Kent Online.

So what are the three options?

Crossrail To Northfleet/Ebbsfleet And Gravesend

The first option provides for an extension of Crossrail from Abbey Wood to Northfleet/Ebbsfleet and Gravesend, sharing the existing tracks with National Rail services.

  • Of the 12 trains per hour (tph) that are planned to run to Abbey Wood. four tph will terminate at each of Abbey Wood, Northfleet/Ebbsfleet and Gravesend.
  • A single platform at Abbey Wood, Northfleet and Gravesend would be capable of handling the required four tph.
  • Crossrail trains would call at all stations on the North Kent Line between Abbey Wood and Gravesend stations.
  • It looks like some form of people-mover will be needed between Northfleet and Ebbsfleet stations.
  • Gravesend station could either turn the trains directly or have a turnback facility to the East of the station at Hoo, where provision has been made for train stabling.
  • Extension of Crossrail’s digital signalling along the North Kent Line, at least as far as Hoo would probably be needed to cope with the extra trains.

This option would be feasible and would require just a new platform at Northfleet station, the people-mover and perhaps some work at Gravesend station.

Crossrail To Dartford And Northfleet/Ebbsfleet

The second option is to draw out Crossrail from south east London to Dartford using new dedicated tracks built next to the existing North Kent line, with increased rail service frequency between Dartford and Northfleet.

  • All the 12 tph, that currently are planned to run ro Abbey Wood, all will terminate at Dartford station.
  • Crossrail trains would call at all stations on the North Kent Line between Abbey Wood and Dartford stations.
  • It looks like some form of people-mover will be needed between Northfleet and Ebbsfleet stations.
  • Extension of Crossrail’s digital signalling along the North Kent Line, at least as far as Hoo would probably be needed to cope with the extra trains.

This option would be feasible and would require a new platform at Northfleet station, the people-mover and a lot of work between Abbey Wood and Dartford stations and at Dartford station.

A Lower Cost Option With Buses

A third option consists of improving the National Rail service between Abbey Wood and Northfleet, combined with a new Bus Rapid Transit service.

  • It appears Crossrail services would stay the same at Abbey Wood, with all twelve tph terminating at the station, as are currently planned.
  • Southeastern services to Dartford via Abbey Wood would be extended to Northfleet. This would increase the number of Southeastern trains to/from London serving stations between Northfleet and Dartford for connection to Crossrail at Abbey Wood from four to eight tph.
  • There would need to be turnback facilities at Northfleet station for the Southeastern services.
  • Extension of Crossrail’s digital signalling along the North Kent Line, at least as far as Hoo would probably be needed to cope with the extra trains.
  • A Bus Rapid Transit service would be provided between Abbey Wood and Ebbsfleet stations via Slade Green, Dartford and Bluewater.
  • A Bus Rapid Transit service would be provided between Slade Green and Ebbsfleet via Greenhithe and Northfleet.
  • Both Bus Rapid Transit services would have a frequency of six buses per hour.

This option looks to be feasible and would only require a new platform at Northfleet station.

The Views Of New Civil Engineer

This article on New Civil Engineer gives its views on the three options.

It says this of the first option.

This option would require the construction of some sections of additional track and junction works within the existing rail corridor, significant works at Abbey Wood, Slade Green and Dartford stations and require additional land to accommodate additional train stabling facilities.

And this of the second option.

This option would require significant construction work to build a new two track rail alignment alongside the existing North Kent line, requiring potential compulsory purchase of land and property beyond the existing rail corridor in some areas and significant works at Abbey Wood, Slade Green and Dartford stations, as well as the provision of new train stabling facilities.

It doesn’t comment about the third option, which I take to mean, that all work for the trains can be done within the existing rail corridor.

Components Of The Options

Although the options are different there are some components that appear in more than one option.

Improved Digital Signalling

The number of trains running to the East of Abbey Wood station, will surely  increase under all three options and I feel it is essential, that  modern digital signalling be installed on the North Kent Lines.

More Train Stabling

Commenting on the first two options, New Civil Engineer says that more stabling will be needed.

In the Gibb Report, Chris Gibb looked at stabling problems with Thameslink and found there was a problem along the North Kent Line. I wrote about it in Gibb Report – Hoo Junction Depot.

I feel that a review of all train stabling in Kent should be performed, so that there is enough space to service and stable the trains of the various operators.

When Crossrail was originally planned, the route was safeguarded to Gravesend and Hoo Junction was put forward as somewhere to stable trains.

A Turnback Platform At Northfleet Station

All three options need a turnback platform at Northfleet station.

  • In Option 1 it will be handling Crossrail trains.
  • In Options 2 and 3, it will be handling Southeastern trains.
  • It probably needs to handle four tph.
  • Nine-car Class 345 trains used by Crossrail are 205 metres long.
  • Twelve-car Class 377 trains used by Southeastern are 240 metres long.

This Google Map shows Northfleet station.

Note.

  1. The North Kent Line goes diagonally across the map from North-West to South-East.
  2. Northfleet station is a two-platform station.
  3. To the South of the station, there are sidings, which are connected to the North Kent Line.

 

This picture shows the sidings from Northfleet station, with Ebbsfleet station about a mile away.

It appears that there would be space to add a well-appointed turnback platform at Northfleet station.

These pictures show some of the features of the current Northfleet station.

Rebuilding to add the turnback platform, could also include.

  • Full step-free access
  • Modern station buildings
  • A deep clean of the pedestrian tunnel.
  • An appropriately-sized bus station, with a zero-carbon shuttle bus to Ebbsfleet station.
  • Future provision for a high-tech people-mover to Ebbsfleet station.

It is not one of the better stations on the Southeastern network.

But it certainly could be!

I very much feel that Northfleet station needs to be rebuilt with an extra platform.

A People-Mover Between Ebbsfleet And Northfleet Stations

I wrote So Near And Yet So Far! about the poor connection between Ebbsfleet And Northfleet stations.

It is a design crime of the highest order.

There has been a lot of pressure in the past to build a pedestrian link between the two stations, as reported by the Wikipedia entry for Northfleet station.

The station is very close to Ebbsfleet International station (the NNE entrance is only 334 yards (305 m) from Northfleet’s station), but passengers (using public transport) will find it far easier to access Ebbsfleet International from Gravesend or Greenhithe, as these stations are more accessible and offer easy access to Fastrack bus services. The walking route between the two stations is 0.6 miles (1 km) or 0.8 miles (1.3 km) and a suitable pedestrian link has not been built because of funding issues and objections from Land Securities.

Why when Ebbsfleet International station was built in the early 2000s for opening in 2007, was a pedestrian link not built between the two stations?

It sounds like it was a Treasury design for Civil Servants, who work in Westminster and wouldn’t dream of living in Gravesend.

How much did omitting the link save?

Probably in the the long term, about two-fifths of five eighths of f***-all!

The specialists in this type of people-mover are the Doppelmayr/Garaventa Group, who in the UK have built the Emirates Air Line and the Air-Rail Link at Birmingham Airport. Currently, they are building the Luton DART people mover.

Wikipedia says that the Emirates Air-Line cost £60million.

Wouldn’t something similar be an ideal way to welcome people to the UK?

The London Resort

The London Resort, is described like this in its Wikipedia entry.

The London Resort is a proposed theme park and resort in Swanscombe, Kent. The project was announced on 8 October 2012 and, if given planning permission, it is estimated that construction will begin in 2022, with a first gate opening in summer 2024 and a second gate by 2029.

It certainly sounds the sort of place I avoid, but just like Disneyland Paris, I feel the developers will want a rail connection.

They could even want to have another people-mover from Ebbsfleet station.

A Connection To The Bluewater Shopping Centre

The Bluewater Shopping Centre is not easy to get to by public transport and requires a bus from Greenhithe for Bluewater station.

Only Option 3 offered an improvement with a bus between Abbey Wood and Ebbsfleet stations via Slade Green, Dartford and Bluewater, that would run every ten minutes.

Conclusion

It seems that whatever option is eventually chosen, certain works will need to be performed as they are needed for all options.

  • Extension of Crossrail’s digital signalling along the North Kent Line, at least as far as Hoo junction would probably be needed to cope with the extra trains.
  • A review of train stabling in Kent should be carried out, to make sure there are enough places to service and stable the trains needed, by all the operators/
  • Northfleet station needs to be rebuilt with an extra turnback platform for at least four tph.
  • Provision should be made for a possible people-mover between Ebbsfleet And Northfleet stations.

The North Kent Line to the East of Abbey Wood station would now be ready for whichever option is chosen.

Because of the London Resort, which has still not been given a definite go-ahead we could see some changes and other options or even some that combine more than one option.

August 1, 2021 Posted by | Transport/Travel | , , , , , , | 7 Comments

Consultation Opens On Extending The Elizabeth Line Into Kent

The title of this post, is the same as that of this article on Ian Visits.

This is the introduction to Ian’s post.

A consultation has opened on proposals for improving public transport services connecting Ebbsfleet, Dartford, Slade Green, Erith and Belvedere with Abbey Wood.

The consultation is being run by the C2E Partnership, which was formed in 2016 to promote extending the Elizabeth line into Kent, although the new consultation does look at alternatives to the Lizzie line as well.

The early plans for Crossrail included running the line out towards Gravesend, but this was cut back in the 1990s, and in 2008 when Crossrail got approval, it was difficult to support the extended line. However, some passive provision was included in the station design at Abbey Wood to permit an extension to be added on later.

There are five options being looked at by the C2E Partnership.

Three of them are extensions of the Elizabeth line, one is improved services from Kent to Abbey Wood, and the final is a Rapid Bus Transit service.

There are maps of the various options.

At the moment, I doubt there is much that will happen, with low levels of commuting due to the pandemic and a near-bankrupt Transport for London.

January 28, 2021 Posted by | Transport/Travel | , , , , , | 4 Comments

C2E – Crossrail 1 1/2?

The title of this post is the same as that in this article in Rail Engineer.

It describes a proposal to extend the Abbey Wood Branch of Crossrail to Ebbsfleet International station along the North Kent Line.

The article starts with these two paragraphs.

With the main Crossrail project now mostly complete, and with tracks running right through the new tunnels, there has been much talk of Crossrail 2 as the next project, crossing under London from South West to North East and linking Wimbledon with the Leigh Valley.

Rather overlooked is a shorter-term proposal to extend the current Crossrail (or Elizabeth line as it will be called) from Abbey Wood to Ebbsfleet in Kent.

The article talks about the advantages of an extension to Ebbsfleet International station.

This proposal would connect several major brownfield development sites with central London, London City and Heathrow airports, and the West, while also connecting Crossrail passengers with Eurostar and the continent

Specific figures and points include

  • Bexley has 1,100 acres of development space available.
  • 55,000 homes could be built.
  • Potential for high-value jobs.
  • Dartford, where there is a lot of demand, has six trains per hour  (tph) to London.

In addition the following additional services call or will call in the near future at Dartford.

  • Southeastern – Two tph running between Gillingham and London Charing Cross.
  • Southeastern – Two tph running between Gravesend and London Charing Cross.
  • Thameslink – Two tph running between Rainham and Luton.

This map from the article shows the route.

I think it is a good plan and I’ll give my reasons in the following sections.

Abbey Wood Is Not A Terminal Station

Was the reason Abbey Wood station was chosen as a terminus more to do with giving a rail connection to the public transport desert of Thamesmead and all its supposed Labour voters?

  • It’s not by any important tourist venue like the Thames.
  • There’s not even a Shopping Centre.
  • There’s little space for car parking.
  • Abbey Wood station is a very cramped site.

When compared to the three other termini, it is the least significant.

  • Shenfield is a small town with shops and a railway junction.
  • Reading is a thriving city and a major transport interchange.
  • Heathrow is Heathrow.

I also suspect that the track layout at Abbey Wood station has been designed to allow Crossrail trains to continue Eastwards on the North Kent Line.

Ebbsfleet International Would Be A Much Better Terminal Station

Ebbsfleet International station has a lot going for it, as a Crossrail terminal.

  • It is a station for Eurostar and the Continent.
  • Some continental services might terminate at Ebbsfleet in the future due to capacity limitations at St. Pancras.
  • It would connect Crossrail to the Highspeed commuter services to and from East Kent and East Sussex.
  • There’s plenty of space for platforms and depots.
  • There’s already masses of car parking.
  • The area may get a theme park.

There is also the interesting possibility, that it could be faster for many passengers from Central London to use Crossrail and Ebbsfleet, rather than a taxi and St. Pancras to get a train to Paris and Brussels.

I also believe that one of our World Class architects can come up with a proposal for a passenger-friendly station that combines the current Ebbfleet International station with Northfleet station on the North Kent Line.

The Route Would Require Little Major Engineering Works

The route to Ebbsfleet would be predominantly, if not completely, on the surface, along the double-track North Kent Line. Having just flown my helicopter along the route, there is a lot of apace on either side of the tracks for quite a proportion of the route.

A four-track route would probably be impossible, but I suspect that Network Rail could design an efficient route, that would handle the services on the route efficiently.

Trains Along The North Kent Line

Current frequencies of Off Peak through trains on the North Kent Line between Abbey Wood and Gravesend stations are as follows.

  • Abbey Wood – 8 tph
  • Belvedere – 8 tph
  • Erith – 6 tph
  • Slade Green – 6 tph
  • Dartford – 4 tph
  • Stone Crossing – 4 tph
  • Greenhithe – 4 tph
  • Gravesend – 2 tph

There will be additional services in the Peak and Thameslink will run an extra two tph from Rainham to Luton, within the next year or so.

The North Kent Line doesn’t seem to have the most extensive level of services.

The New Southeastern Franchise

The new South Eastern franchise will be awarded in August 2018 and is due to start by the end of the year.

The franchise will probably bring changes and add new trains to the fleet and lines like the North Kent Line.

I also suspect that all trains running on the North Kent Line will in a few years be modern trains capable of operating at 100 mph.

Modern Signalling Could Handle Twenty-Four Trains Per Hour On The North Kent Line

There is no doubt, that if Crossrail-style signalling were applied to the North Kent Line between Abbey Wood the Medway towns, capacity could be increased, if all trains on the line were modern 100 mph units.

I doubt that twenty-four tph would be needed, but I’m sure that enough capacity could be created on the route to handle all services; curent or proposed.

How Many Trains Would Crossrail Run Between Abbey Wood And Ebbsfleet International Stations?

Crossrail’s timetable plan shows  these frequencies at the various termini in the Peak.

  • Abbey Wood – 12 tph
  • Gidea Park – 4 tph
  • Heathrow Terminal 4 – 4 tph
  • Heathrow Terminal 5 – 2 tph
  • Liverpool Street – 4 tph
  • Maidenhead – 2 tph
  • Paddington – 12 tph
  • Reading – 4 tph
  • Shenfield – 12 tph

From these figures, it would appear that four tph to Ebbsfleet International would be reasonable starting point.

This would give the following frequencies along the line.

  • Abbey Wood – 14 tph
  • Belvedere – 14 tph
  • Erith – 12 tph
  • Slade Green – 12 tph
  • Dartford – 10 tph
  • Stone Crossing – 10 tph
  • Greenhithe – 10 tph
  • Gravesend – 4 tph

Note I have added in the 2 tph Thameslink trains from Rainham to Luton.

These frequencies are well within the limits of a double-track railway with a 100 mph operating speed and modern signalling.

The Original Plan Was To Extend To Gravesend

The route for Crossrail from Abbey Wood is safeguarded to Gravesend. Under Future Extensions in the Wikipedia entry for Crossrail, this is said.

The route to Gravesend has been safeguarded by the Department for Transport, although it was made clear that as at February 2008 there was no plan to extend Crossrail beyond the then-current scheme. The following stations are on the protected route extension to Gravesend: Belvedere, Erith, Slade Green, Dartford, Stone Crossing, Greenhithe for Bluewater, Swanscombe, Northfleet, and Gravesend.

A depot would be built at Hoo Junction to the East of Gravesend.

The extended service could always call at both stations.

  • Ebbsfleet International station connects to Eurostar and has space for masses of parking.
  • Gravesend connects to services to East Kent and is on the Thames.

Money and accountants would decide.

Conclusion

Extending four tph from Abbey Wood to a new terminus at Ebbsfleet International station, doesn’t appear to be the most difficult of undertakings.

 

 