The Anonymous Widower

The Next Generation Of Fixed Foundation Wind Farms

This article on offshoreWIND.biz, is entitled Offshore Wind Turbines In 2022: 15 MW Prototypes Starting To Spin In Europe, Chinese Rolling Out 16 MW Models, Windcatcher And VAWTs Secure Demo Projects.

The title itself, shows 15-16 MW wind turbines and the text lists three European 15 MW and two Chinese 16 MW wind turbines, that are being developed.

This paragraph also indicates that Siemens Gamesa are in the running for orders.

So far, the SG 14-236 DD wind turbine has been selected as a preferred option for the Norfolk Vanguard and Boreas wind farms offshore the UK, as well as for the MFW Bałtyk II and MFW Bałtyk III wind farms in the Polish Baltic Sea.

Large turbines with a capacity of 15 MW and upwards appear to be becoming the new normal.

Water depths for these large turbines are forecast to be deeper than the two Norfolk wind-farms, which are between 22 and 40 metres.

This means that foundations will get much larger and heavier.

This article on offshoreWIND.biz, is entitled New Monopile Installation Method Attracts Major Backer, describes a new generation of monopiles as 100-130 metres in length, 12-15 metres in outer diameter, and a weight of up to 5,000 tonnes.

Installing these long and heavy objects safely in deep waters, is not a job for the faint-hearted.

The article describes a new method of installation, which I feel is very elegant.

  • The XXXL monopiles are built horizontally.
  • They are moved on to the jack-up ship by self-propelled modular transporters (SPMT).
  • It appears at least two or possibly up to four monopiles can be carried on the ship.
  • They are lifted into the vertical position by a lifting beam.

Note.

  1. No cranes are involved in the process.
  2. The lifting beam method of erecting the 5,000 tonne XXXL monopile is simple and very efficient.
  3. Self-propelled modular transporters were used to install the 2000 tonne subway at Hackney Wick station.
  4. Rollers are fitted on the ship to ease handling of the monopiles.

I can certainly see this specialised jack-up ship speeding up the installation of these giant monopiles.

Consequences For Floating Wind

I do wonder, if this method of installing fixed foundation wind farms, will allow larger foundations and these may mean that there is less need for the more complex floating wind farms.

January 5, 2023 Posted by | Energy | , , , , , , , , | Leave a comment

Gravitricity Makes Hydrogen Play With FlexiStore

The title of this post, is the same as that of this article on The Engineer.

This is the sub-heading.

Edinburgh-based energy storage firm Gravitricity is looking to green hydrogen, bringing a new underground storage solution to market.

The system is explained with a large graphic, showing an electrolyser, a FlexiStore and a hydrogen filling station, with this paragraph underneath.

Known as FlexiStore, the concept involves purpose-built, steel-lined shafts capable of holding up to 100 tonnes of compressed hydrogen at 220 bar – around 3.33GWh of energy, or enough to refuel over 1,000 HGVs, according to Gravitricity. Unlike naturally occurring underground storage like salt caverns, FlexiStores could be positioned anywhere, with the current plan to co-locate the storage as close as possible to renewable generation. Gravitricity says a single FlexiStore could serve a 460MW wind farm and that 1,000 units could meet the UK’s predicted hydrogen storage needs in 2050.

Note.

  1. The concept certainly solves the problem of storing hydrogen on a country-wide basis.
  2. I suspect, a machine could be designed and built to create the shafts.
  3. A 3.33 GWh store could supply 460 MW for nearly 33 hours. As a Control Engineer, that sounds a good balance for backing up a wind farm!

As ARUP has been involved in a feasibility study, I suspect there’s a fair chance that FlexiStores can be built.

January 5, 2023 Posted by | Energy, Energy Storage, Hydrogen | , , | 2 Comments

Norway’s Answer To Wind Power Intermittency Lies Offshore – Study

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the first paragraph.

SINTEF has revealed in its recent study that there is no statistical covariation or systematic correlation in time between the occurrence of offshore wind conditions in southern and northern Norway, and adds that this knowledge will increase the commercial value of Norwegian offshore wind energy.

It does seem lucky for the Norwegians, that their wind farms appear to be able to supply a more constant amount of electricity, than many of those against wind farms would have you believe.

I hope that a reputable UK agency or university, is doing a similar analysis for UK wind farms.

January 5, 2023 Posted by | Energy | , , , , | 1 Comment

World’s First Floating Offshore Wind Farm Celebrates Five Years Of Operation

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

Hywind Scotland, the first floating offshore wind farm in the world, has passed five years in operation since its commissioning in 2017.

And this is the first paragraph.

According to Equinor, Hywind Scotland is the world’s best-performing offshore wind farm, achieving a capacity factor of 54 per cent over its five years of operations.

Note.

  1. Hywind Scotland is a 30 MW wind farm with five turbines.
  2. The capacity faction is much higher than a windfarm with fixed foundations.
  3. The water depth is between 95 and120 metres.
  4. The wind farm is 30 km. off Peterhead.

There is at least 15 GW of floating wind farms being planned in UK waters before 2030.

Conclusion

The wind farm has made a good start for the first floating wind farm.

January 4, 2023 Posted by | Energy | , , , , | Leave a comment

Looking For A Job

There’s probably a lot like me these days, what with Putin’s war having depressed the financial markets and put up the cost of everything.

I’m now 75 and seem to regularly get good news about my health, which probably means that my pension will have to stretch further.

Before Christmas, I did a couple of weeks as a volunteer receptionist in a research institute and I enjoyed it.

Perhaps, I’m just lonely and feel a job would liven up my life.

I have a large number of skills and a wide range of knowledge about technical subjects.

I have programmed in many languages with the most useful probably being VB6, which I used for perhaps twenty years, so I might be the guy to update a VB6 system, that is vital to your business.

I am very much an algorithm person because of my background and have done a lot of work in project management.

I also live a few miles North of the City of London.

So if you have any ideas let me know!

January 4, 2023 Posted by | Computing | , | 5 Comments

Denmark’s Bank Robbers Count The Cost Of Cashless Society

The title of this post is the same as that of this article on The Times.

This is the second paragraph.

Figures from Finans Danmark, an industry association, show the number of attacks has collapsed in recent years as the shift towards online transactions has led many Danish banks to abandon cash services in branches. While there were 221 bank robberies in 2000, the number of hold-ups in Denmark fell to 121 in 2004, before declining to one in 2021 and none last year.

There were also no attacks on ATM machines.

Doing away with cash certainly cuts crime and it must be twelve years, since a Unite representative on Manchester buses told me he wanted cashless ticketing on Manchester’s buses and trams, as since it had been introduced in London, attacks on staff had declined dramatically.

I also wonder by how much the Income Tax take would rise?

January 3, 2023 Posted by | Finance & Investment | , , , , , , , | 1 Comment

Danes Talk 62 MW Offshore Wind Turbines For North Sea Energy Island

The title of this post, is the same as that of this article on Offshore Energy.

The Danes may talk 62 MW, but that four times larger than one of the biggest today, that I wrote about in Vestas 15 MW Prototype Turbine Produces First Power.

This paragraph says a bit more about the 62 MW turbine.

According to the DEA’s framework document for the draft plan for the strategic environmental assessment (SEA), this could be a 500-metre-tall wind turbine with a rotor diameter of 480 metres and a capacity of up to 62 MW.

This turbine is bigger in terms of capacity, than  than some whole farms.

January 3, 2023 Posted by | Energy | , , , , | 4 Comments

Ofgem OKs Transmission Investments Needed For UK’s 2030 Offshore Wind Target

The title of this post, is the same as that, of this article on offshoreWIND.biz.

This is the sub-heading.

Ofgem has approved the strategic electricity transmission reinforcements required to deliver the UK Government’s 50 GW offshore wind by 2030 target, set out as part of the regulator’s Accelerated Strategic Transmission Investment (ASTI) framework.

A map then shows the principle new transmission reinforcements.

These include two 2 GW subsea HVDC links from Peterhead to England, both of which will be taken forward as joint ventures with National Grid Electricity Transmission (NGET), a 2 GW subsea HVDC link from Spittal in Caithness, connecting to Peterhead, as well as a 1.8 GW subsea HVDC link from Arnish on the Western Isles to the Beauly area near Inverness.

The approval also implies 400 kV onshore reinforcements, between Beauly, Blackhillock, New Deer and Peterhead; between Beauly, Loch Buidhe and Spittal; and between Kintore, Tealing and Westfield; and uprating the existing Beauly to Denny line to enable 400 kV operation on both circuits.

All cables seem to lead to Peterhead.

January 3, 2023 Posted by | Energy | , , , , | 2 Comments

Is This The Television Program Of The Year?

I’m just watching The Mayfair Hotel Megabuild in BBC2.

It’s fascinating and a must watch, as builders and miners expand Claridge’s Hotel up and down!

  • More rooms and a penthouse on top.
  • A spa and two swimming pools in the basement.
  • A large number of rooms are also being refurbished.

And all while the hotel is nearly fully occupied.

I suspect that a lot of the techniques shown in the documentary have been used on the construction of the Elizabeth Line and the execution of the Bank Station Upgrade.

January 2, 2023 Posted by | World | , , , , , | 2 Comments

Portishead Reopening Finally Approved

The title of this post, is the same as that of a small article in the January 2023 Edition of Modern Railways.

These are the first two paragraphs.

Secretary of State for Transport Mark Harper has approved a Development Consent Order to reopen the railway to Portishead as part of the West of England Combined Authority’s MetroWest Phase 1B project.

Under the £152 million scheme, the disused railway between Portishead and Pill will be rebuilt, with the Pill to Ashton Junction  freight line upgraded. It joins the Bristol & Exeter route at Parson Street Junction.

Note.

  1. MetroWest is going to be Bristol’s Metro.
  2. Portishead station is going to be one of its termini.
  3. It appears that a new station is going to be built at Portishead.
  4. There used to be other stations on the branch.

I have these thoughts.

Portishead Station

In the Wikipedia entry for Portishead station, there is a section called Future, where this is said.

In April 2019 the Department for Transport committed £31.9m to cover the shortfall in finance for MetroWest Phase 1, meaning that funding for the new station and reopened line has now been secured. In November 2019 North Somerset Council submitted a Development Consent Order (DCO) application to the Planning Inspectorate, which seeks powers to build and operate the disused section of railway from Portishead to Pill, gain environmental consent to undertake works to the existing freight railway through the Avon Gorge and obtain powers for the compulsory acquisition of land. The Secretary of State for Transport is expected to make a decision within 18 months. Subject to final business case approval, construction work is expected to start on the line in December 2021 and then take around two years to complete.

The Secretary of State for Transport gave his decision in December 2022, but I would expect two year construction time to hold.

Stations On The Branch

The original branch had five stations; Ashton Gate, Clifton Bridge, Pill, Portbury and Portishead.

How many will be reopened?

In the Wikipedia entry for Ashton Gate station, there is a section called Future, where this is said.

The line through Ashton Gate would be increased to double track. Network Rail stated that it was not feasible to reopen Ashton Gate during the initial stage of the project, but that the scheme will be future-proofed to allow the construction of a station at a later date.

The section also mentions a reopened station at Pill.

The Wikipedia entry for Pill station, there is a section called Future, where this is said.

As part of the works, Pill station will be reopened. Trains both to and from Portishead will use the southern platform, which will be resurfaced and provided with a waiting shelter, lighting, passenger information displays and audible announcements. The northern platform, adjacent to the current single track line to Royal Portbury Dock, will not be reinstated, however the track will be retained for freight trains. The two tracks will have a junction east of the station.

It is expected that reopening the station will result in reduced car usage to and from Pill and the surrounding villages. Most station users will walk to the station, with the next largest share being car drivers and car passengers being dropped off, followed by cyclists and bus users. Some parking restrictions are proposed to prevent rail users parking on the local streets, which are narrow and not suitable for widening.

Note.

  1. The station design appears to not need a bridge.
  2. There would be disabled parking and a pick up/drop off point adjacent to the entrance.

I think this station design could be able to handle two trains per hour (tph).

What Will Be The Service?

This paragraph outlines the service.

An hourly service is proposed, with journey times from Portishead to the centre of Bristol expected to be around 22 minutes, which is said to be competitive with roads in the area.

Twenty-two minutes is an interesting time, as it will mean that it should be possible to do the following in an hour.

  • Go from Bristol Temple Meads to Portishead.
  • The driver changes ends and gets ready to return.
  • Go from Portishead to Bristol Temple Meads
  • The driver changes ends and gets ready to go to Portishead again.

If the train can do the full return journey in an hour, it will be able to run the service with a single train.

The Wikipedia entry for Pill station, there is a section called Future, where this is said.

Trains along the reopened line will operate between Portishead and Bristol Temple Meads, with two trains per hour in each direction. Services would call at Pill and Parson Street, with aspirations to also call at Bedminster and a reopened Ashton Gate. Trains could also be extended on to the Severn Beach Line. The trains used will be diesel multiple units, likely three carriages long.

Note.

  1. Wikipedia and Modern Railways are giving different frequencies.
  2. Two tph could probably be run by using two trains.

I suspect that the Modern Railways figure is correct, as it is the most recent.

January 2, 2023 Posted by | Transport/Travel | , , , , , , , | 5 Comments