The Anonymous Widower

JERA Nex BP, EnBW Submit Morven Offshore Wind Farm Application

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

A joint venture between JERA Nex BP and EnBW has submitted Section 36 consent applications for the Morven offshore wind farm to the Scottish government

These two paragraphs add a few details.

The developer secured the seabed rights for the Morven offshore wind farm as a single project in the ScotWind Leasing Round in 2022 and split it into two separate projects during the early development phase.

Located around 60 kilometres off the coast of Aberdeenshire at its closest point, the site is planned to house Morven North and Morven South, which would have a combined installed capacity of up to 3 GW and around 190 wind turbines in total.

Morven Offshore Wind Farm now has a comprehensive web site.

The web site says that the electricity will be brought ashore at Hawthorn Pit.

This Google Map shows the location of Hawthorn Pit.

Note.

  1. Hawthorn Pit is indicated by the red arrow.
  2. Sunderland is at the top of the map on the coast.
  3. Aura Power has already obtained planning permission for Hawthorn Pit solar farm, which will be up to 49.9 MW.
  4. Zenobe are developing a battery-energy-storage-system(BESS) 1.5 km to the South-East of the new Hawthorn Pit substation, which will have an output of 300 MW. Sloppily, there is no detail on capacity, but Google AI indicates, it is a 300 MW/600 MWh battery.
  5. Hawthorn Pit substation is also the expected to be the Southern end of Eastern Green Link 1, which will help to bring Scottish wind power to England, which will be a 2 GW undersea interconnector to Torness.

In Murphy Starts Work On £2.5bn Eastern Green Link 1, I detail the start of building of Eastern Green Link 1 and say it should be operational by 2029.

When Is The Morven Offshore Wind Farm Expected To Be Commissioned?

I asked Google AI the question above and received this answer.

The 2.9 GW Morven offshore wind farm is expected to be fully commissioned and operational between 2031 and 2035, with initial grid connections and power export potentially starting as early as 2030.

The timeline for full deployment of the Morven Offshore Wind Farm remains somewhat flexible as it depends on final planning approvals and connection offers from the National Energy System Operator (NESO).

The Cables For The Morven Offshore Wind Farm And Eastern Green Link 1

This map clipped from the Morven Offshore Wind Farm web site, shows the locations of Aberdeen, Hawthorn Pit and the Morven Offshore Wind Farm.

Note.

  1. The location of the Morven wind array was first mentioned in June 2020, as part of ScotWind by Crown Estate Scotland.
  2. The development of Eastern Green Link 1 was first mentioned in May 2021, by National Grid.
  3. Torness is to the East of Edinburgh.
  4. Eastern Green Link 1 connects Torness and Hawthorn Pit.
  5. the Morven wind array connects to England at Hawthorn Pit.

Over the last few years National Grid and other companies have been developing a technique called offshore hybrid assets, which I describe in What Are Offshore Hybrid Assets?.

An offshore hybrid asset typically connects two countries via a large offshore wind farm, which can then send electricity to both countries.

In a traditional design, there would need to be.

  • A 2 GW cable between Torness and Hawthorn Pit.
  • A 2.9 GW cable between Morven and Hawthorn Pit.

In the Offshore Hybrid Asset design, there would need to be.

  • A 2 GW cable between Torness and Morven
  • A 2.9 GW cable between Morven and Hawthorn Pit.

I suspect cable would be saved.

This map shows the position of each ScotWind Leasing wind farm.

Note.

  1. The numbers are Scotwind’s lease number in their documents.
  2. Morven is ScotWind lease number 1.
  3. Eastern Green Link 1 is one of four interconnectors down the East Coast of the UK.
  4. I have added up the ScotWind lease numbers 1-6 and they total 10.5 GW.

That would be a lot of power to capture just by converting the four Eastern Green Link interconnectors into offshore hybrid assets.

How Will Aquaventus Connect To Aberdeen?

This is RWE’s description of AquaVentus, which is sub-titled Hydrogen Production In The North Sea.

Hydrogen is considered the great hope of decarbonisation in all sectors that cannot be electrified, e.g. industrial manufacturing, aviation and shipping. Massive investments in the expansion of renewable energy are needed to enable carbon-neutral hydrogen production. After all, wind, solar and hydroelectric power form the basis of climate-friendly hydrogen.

In its quest for climate-friendly hydrogen production, the AquaVentus initiative has set its sights on one renewable energy generation technology: offshore wind. The initiative aims to use electricity from offshore wind farms to operate electrolysers also installed at sea on an industrial scale. Plans envisage setting up electrolysis units in the North Sea with a total capacity of 10 gigawatts, enough to produce 1 million metric tons of green hydrogen.

RWE have also put this AquaVentus video on their web site.

Note, that in the video AquaVentus connects Germany to Denmark, Norway, The Netherlands and Aberdeen and Humberside in the UK.

I asked Google AI, the question in the title of this section, and received this answer.

AquaVentus connects to Aberdeen through a strategic infrastructure partnership with Hydrogen Scotland. The two organizations are integrating offshore wind power, offshore electrolysis, and a shared cross-border pipeline to link Scottish renewable generation with European industrial markets.

The connection strategy relies on a multi-stage approach across the North Sea:

Offshore Production & Transmission: AquaVentus aims to produce green hydrogen directly offshore. It will be transported via a pan-European pipeline network—such as the planned 400 km AquaDuctus to link offshore hubs with both the UK and mainland Europe.

Scottish-German Export Corridor: Building on previous research like the Scot2Ger study, this pipeline corridor directly connects Scotland’s abundant offshore wind resources to European demand, establishing Aberdeen as a critical origin node.

Integrated Energy Backbone: The initiative champions hybrid connection concepts (combining both power cables and hydrogen pipelines). This allows for maximum flexibility when integrating Aberdeen’s local onshore hydrogen infrastructure with broader transnational energy grids.

I will now ask Google AI some supplementary questions about AquaVentus in UK waters.

“Will AquaVentus Produce Hydrogen In UK Waters?”

Google AI gave this reply.

Yes, AquaVentus plans to produce green hydrogen in UK waters. The German-led consortium has partnered with Hydrogen Scotland to harness Scotland’s offshore wind potential for large-scale, cross-border hydrogen production and export.

Key Details of the UK-German Initiative

Production Scale: The initiative aims to install 10 gigawatts (GW) of offshore electrolysis capacity in the North Sea by 2035, producing up to 1 million metric tonnes of green hydrogen annually.

The “Pipes and Wires” Model: Offshore wind parks will be equipped with hybrid connection concepts, providing the flexibility to either send electricity directly to the grid or convert it into hydrogen via offshore electrolysers.

Transportation: The produced hydrogen will be transported to land via a shared transnational subsea pipeline corridor, linking Scottish resources to Germany and mainland Europe.The partnership is specifically aimed at creating a North Sea hydrogen corridor to boost energy security and build the foundational European Hydrogen Backbone.

“Will AquaVentus Land Hydrogen In Scotland?”

Google AI gave this reply.

Yes, the German-led AquaVentus initiative plans to land green hydrogen in Scotland as part of a coordinated North Sea energy corridor.

The cross-border initiative involves the following components:

The Pipeline Connection: A key part of the plan is the AquaDuctus offshore subsea pipeline, designed to collect green hydrogen produced from central North Sea wind farms and land it on the coast.

Scottish Partnership: Hydrogen Scotland and AquaVentus have formalized a Memorandum of Understanding to combine Scotland’s massive offshore wind potential with German infrastructure and electrolysis expertise.

Export Ambitions: Scotland aims to produce up to 3.3 Mt of green hydrogen per year by 2045, heavily relying on pipelines and networks to export this to mainland European hubs like Germany.

Offshore Facilities: The broader initiative plans to install 10 GW of offshore electrolysis capacity in the North Sea to produce up to 1 million tonnes of hydrogen annually.

Note that Google AI has told me that a Megatonne of hydrogen is currently worth around £2.5-5 billion.

 

“Will AquaVentus Connect To Any Of The ScotWind Leasing Wind Farms?”

Google AI gave this reply.

Yes, AquaVentus plans to link Scottish offshore wind resources (including ScotWind farms) to mainland Europe. Through an agreement with Hydrogen Scotland, AquaVentus intends to utilize hybrid “pipes and wires” infrastructure to transmit power or convert it into green hydrogen for direct pipeline transport.

The partnership serves several strategic goals:

The “Pipes & Wires” Concept: Wind farms built under the ScotWind leasing round will have the flexibility to either route electricity to the UK grid or convert it into green hydrogen via offshore electrolysers.

Cross-Border Pipelines: The hydrogen generated by Scottish offshore wind is targeted to be fed into the planned AquaDuctus pipeline, which forms a transnational energy corridor connecting the UK to Germany and the rest of Europe.

Policy Integration: AquaVentus is actively advocating for legal reforms to accommodate these cross-border hybrid connections, allowing direct pipeline integration for future offshore parks.

I believe these ScotWind Leasing wind farms could be connected to AquaVentus.

  • 1 – Morven – 2.9 GW – JERA Nex BP, EnBW
  • 2 – Ossian – 2.6 GW – SSE Renewables
  • 3 – Bellrock – 1.2 GW – Falck Renewables
  • 4 – CampionWind – 2 GW – Scottish Power, Shell
  • 5 – Muir Mhòr – 0.8 GW – Vattenfall
  • 6 – Bowdun –  – 1 GW – Thistle Wind Partners

Note.

  1. All companies are major energy companies.
  2. The wind farms are in a cluster to the South-East of Scotland.
  3. Wind farms 2-5 are floating, and 1 and 6 are fixed.
  4. There is a maximum power of 10.5 GW.
  5. These wind farms would not need to be shut down, when there was too much wind, if the excess electricity could be converted into hydrogen.
  6. The “Pipes & Wires” Concept would allow all energy generated to be transferred to shore, either as electricity or hydrogen.

Cables would need to be laid to perform the functions of the Eastern Green Links 1-4.

  • Eastern Green Link 1 – Torness and Hawthorn Pit
  • Eastern Green Link 2 – Peterhead and Drax
  • Eastern Green Link 3 – Westfield and Lincolnshire
  • Eastern Green Link 4 – Peterhead and Lincolnshire

Eastern Green Link 5 is under development between Aberdeenshire and Lincolnshire.

“Is Anderby Creek An Important Node In The Electricity Grid?”

Google AI gave this reply.

Yes, Anderby Creek has become a highly important landfall location for the UK’s electricity grid, acting as a crucial connection point for high-capacity subsea cables bringing renewable energy from Scotland and offshore wind farms into England.

Its role in the national grid’s infrastructure centers on several major “superhighway” projects:

Eastern Green Link 5 (EGL 5): This £3bn National Grid project involves a 585km subsea High Voltage Direct Current (HVDC) cable carrying up to 2 GW of clean power (enough for two million homes) from Aberdeenshire, Scotland, to Anderby Creek.

Eastern Green Links 3 & 4 (EGL 3 / EGL 4): These are additional massive subsea cable projects that also plan to make landfall at Anderby Creek to transport Scottish wind energy down the UK coastline.

Offshore Wind Export Cables: Beyond long-distance transmission, the village already hosts export cables from local offshore wind developments like the Triton Knoll Wind Farm.

Because of the massive volume of power coming ashore, Anderby Creek serves as the starting point for significant onshore infrastructure. The cables transition underground at the beach and run roughly 8km inland to a proposed new converter station near Bilsby/Alford, where the power is converted and integrated into the broader Great Grid Upgrade.

“Will AquaVentus Have Access To The UK’s hydrogen Storage On Humberside?”

 

Google AI gave this reply.

Yes. Through a strategic partnership with Hydrogen Scotland, the AquaVentus initiative aims to establish cross-border offshore infrastructure that connects the central North Sea with existing and planned hydrogen networks across the UK, including those on Humberside.

The pipeline infrastructure associated with AquaVentus is envisioned to reach the UK just south of the massive hydrogen storage facilities located in East Yorkshire. While the German offshore pipeline (like AquaDuctus) is focused on landing green hydrogen into Germany, the broader AquaVentus framework is designed to integrate with British transmission networks and link to underground cavern storage in the UK.

On Humberside, major energy giants (including Centrica, Equinor, and SSE Thermal) are developing the integrated Humber Hydrogen transport and storage network. This system encompasses large-scale hydrogen storage at the Aldbrough Hydrogen Storage site and Rough Gas Storage. Because the AquaVentus UK branch connects to the Humber area’s onshore network, it positions the initiative to take advantage of these regional storage assets as a cornerstone for international trade and domestic energy resilience.

I think this is key as it gives AquaVentus access to very large hydrogen storage.

Conclusion

It almost looks to me, that National Grid and AquaVentus are combining their pipes and wires between the Southern North Sea and Aberdeen.

  • Hydrogen offtake for Germany will be at Wilhelmshaven.
  • Hydrogen offtake for England will be at Humberside.
  • Hydrogen offtake for Scotland will be at Aberdeen.
  • Electricity offtake for Germany will be at Wilhelmshaven.
  • Electricity offtake for England will be at Anderby Creek.
  • Electricity offtake for England will be at Hawthorn Pit.
  • Electricity offtake for Scotland will be at Torness.
  • Electricity offtake for Scotland will be at Aberdeen.

Note.

  1. There will probably be other connections to onshore locations and offshore wind farms.
  2. Hydrogen imports will be possible from Denmark, Norway and The Netherlands direct into AquaVentus.

 

 

 

 

 

 

 

 

 

 

 

 

 

June 5, 2026 Posted by | Artificial Intelligence, Energy, Energy Storage, Hydrogen | , , , , , , , , , , , , , , , , , , , , , , , , , , , , , | Leave a comment

Murphy Starts Work On £2.5bn Eastern Green Link 1

The title of this post, is the same as that as this article on Construction Enquirer.

This is the sub-heading.

Murphy has started work on its first package on the vast £2.5bn Eastern Green Link 1

These two paragraphs add more detail.

The joint venture between SP Energy Networks and National Grid Electricity Transmission will see the installation of a 196km, high voltage, subsea electricity cable between Torness in East Lothian, Scotland, and Hawthorn Pit in County Durham.

Murphy is one of the main works contractors alongside Metlen, GE Vernova and Prysmian.

Murphy’s task seems to be to design and build the new substation, integrate it with the existing one and connect it all to Eastern Green Link 1 and other assets. Work is expected to complete in March 2028.

Google AI predicts that Eastern Green Link 1 will be commissioned by 2029, so it should be up and running before the expected election helping to balance and stabilise Scottish and English wind power at a rate of up to 2 GW day and night.

June 5, 2026 Posted by | Energy | , , , , , , , , , , , | 1 Comment

National Grid Rollout New Technology To Expand The Capacity Of Existing Power Lines

The title of this post, is the same as that of this press release from National Grid.

These four bullet points act as sub-headings.

  • Latest rollout of Dynamic Line Rating (DLR) technology highlights spare capacity on existing power lines allowing greater power flows

  • New instalments on 585km of key north to south transmission network routes has the potential to save consumers up to £50 million in constraint costs

  • Over the last five years DLR has saved £21million in constraint costs and complemented upgrades to the existing transmission network (such as reconductoring and the use of power flow controllers) which have added over 16GW of new capacity to the existing network.

  • National Grid is unlocking more power from the existing grid faster and more cheaply, using innovative technology to meet increased demand, alongside constructing new infrastructure.

These first three paragraphs of the press release describe National Grid’s use of Dynamic Line Rating.

National Grid has announced a significant expansion of Dynamic Line Rating (DLR) technology across its electricity transmission network in England and Wales. Under a new five-year contract, Dynamic Line Ratings will be deployed across an additional 585km of key north-to-south transmission routes, potentially saving consumers up to £50 million over the next five years.

Meeting the growing demand for electricity requires both new infrastructure and smarter use of what already exists. DLR is an innovative yet proven technology that continuously monitors overhead line conditions to calculate a real-time capacity rating based on actual conductor behaviour and local weather, rather than the fixed conservative assumptions that have historically governed line ratings.

The result is a safe, reliable optimisation of available capacity on existing infrastructure, with the sensors and data analytics platforms allowing for a safe increase of the power carrying capacity of a circuit by an average of 8%. This reduces the need for constraint payments, where a generator is paid to stop generating to avoid overloading the electricity network.

This is an brilliant application of instrumentation, automation and very smart computing, that creates an average of eight per cent more capacity in the National Grid.

It’s like smart motorways for electrons, that from the press release appears to work.

I have some thoughts.

Reconductoring Is Mentioned

I suspect that the grid is highly instrumented and the grid can pick up areas that need to be replaced, but the masses of data a system like this will collect, will only improve their knowledge of the grid and give better predictions of where and how cables need to be replaced. Sophisticated modelling will also indicate, things like whether fatter cables here and there could squeeze more capacity into the network.

In the 1970s, I provided the software for the Water Resources Board to analyse and plan the pipelines and reservoirs for water supply in large parts of England.

Given that over the years, most of the problems over the years with the water industry, seem to apply to sewage, ownership, politics, equipment failure, rather than taps actually running dry, I suspect that Dr. Dimeloe and his team did a magnificent job. I would love to know the truth from one of the team.

As fifty years later, modelling software must be more sophisticated, I suspect a continuous analysis of the grid could give substantial benefits.

More And Better Sensors Will Be Developed

As needs arise, the systems will get more and more sophisticated and I wouldn’t be surprised to see the capacity of the grid increase by more than expected.

There Are 4,000 Miles Of High Voltage Overhead Lines In The UK

So if, National Grid can get an eight percent increase as the press release indicates, they might be able to add the equivalent of 320 miles to the electricity transmission network, without the hassle of applying for planning permission or dealing with Nimbies.

There might also be a cost saving as Google AI indicated that high voltage transmission lines cost around two million pounds per mile.

I Can Envisage Sophisticated Connection Networks For Offshore Wind Farms Using Coastal Or Even Offshore Batteries To Maximise The Energy Generated

Consider.

  • The output of a wind farm varies throughout the day and night.
  • Some of the variation in a wind farm’s output may be predictable.
  • Batteries and/or capacitors are good at smoothing variation in electrical power output and demand.
  • Capacitors are useful for smoothing out high-frequencies.
  • Highview Power are now building a 50 MW/300 MWh and a 500 MW/3.2 GWh battery, that both come with a sophisticated control system, they call a stability island providing inertia (frequency stability), short-circuit strength, and voltage control.
  • Dynamic Line Rating can be applied to the transmission line, that connects the wind farm and the battery to the grid.

Getting all these assets to work as a team, is a challenge some of the world’s best engineer/programmers would relish.

I could envisage, that systems like this could deliver hundreds of mill-pond smooth megawatts, that would be just what data centre owners wanted and needed.

Conclusion

The application of Dynamic Line Rating is going to revolutionise the electricity grid all over the world.

 

 

May 4, 2026 Posted by | Computing, Energy, Energy Storage | , , , , , , , , , , , , , , , | 2 Comments

TenneT, National Grid Ink Joint Development Agreement For LionLink Offshore Wind Interconnector

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

Transmission system operators (TSOs) TenneT and National Grid Ventures (NGV) have signed a Joint Development Agreement (JDA) to advance LionLink, a hybrid interconnector linking the UK and the Netherlands via a future offshore wind farm in the Dutch North Sea.

These three paragraphs add more details.

The agreement sets out how the two partners will jointly develop LionLink towards a final investment decision (FID), including arrangements on procurement, governance, and planning, while also aiming to increase transparency on project costs ahead of construction.

LionLink is designed to integrate cross-border electricity interconnection with offshore wind by establishing a direct connection between the two countries through a grid link to the planned Nederwiek 3 offshore wind farm. According to the developers, this approach will maximise the use of offshore wind, provide additional system flexibility, and reduce the overall amount of required offshore infrastructure.

The LionLink project was launched in April 2023, when the Netherlands and the UK unveiled their plan to build the interconnector, a first-of-its-kind electricity link to connect offshore wind between the two countries via interconnections.

The same article also said these two paragraphs about the operation of the BritNed interconnector.

While the companies move forward with LionLink, their existing BritNed interconnector is marking 15 years of operation. Since entering service in 2011, the 1 GW subsea link has enabled nearly 93 TWh of electricity trading between Great Britain and the Netherlands.

Over the past five years, BritNed has exchanged enough electricity annually to power around 1.4 million households. The 260-kilometre interconnector remains a key part of both countries’ energy systems and has generated around EUR 1 billion in auction revenues on the Dutch side during its operational lifetime, TenneT said in a press release on 1 April.

It looks like BritNed has been a good investment for all stakeholders.

Note.

  1. LionLink will be a 2 GW interconnector.
  2. LionLink will land at Walberswick in Suffolk.
  3. LionLink has a web site.
  4. BritNed is a 1 GW interconnector.
  5. BritNed lands at the Isle of Grain in Kent.
  6. BritNed has a web site.
  7. NemoLink is an interconnector between Kent and Belgium.
  8. NeuConnect will be a 1.4 GW interconnector between the Isle of Grain and Wilhelmshaven, which will be operational by 2028.
  9. There are two actual and two proposed interconnectors between the UK and France.

The List of high-voltage transmission links in the United Kingdom in Wikipedia is growing.

The Wikipedia entry says this about the Rise of UK Interconnection.

The Department for Energy Security and Net Zero’s Digest of UK Energy Statistics reports that the UK was a net importer of electricity in 2024, with net imports of 33.4 TWh, up 40% from 2023.

Interconnectors allow the trade of electricity between countries with excess generation (for example, intermittent renewable) and those with high demand. Interconnectors play a key part in balancing variable renewable generation, for example the 1.4 GW North Sea Link allows the UK to export excess power to Norway during windy periods to conserve Norwegian hydro stocks, and import Norwegian hydro power on less windy days.

During the 2022 energy crisis, the UK exported record amounts of power to mainland Europe, helping to alleviate the effects of the Russian invasion of Ukraine on European security of supply.

As of 12 November 2024, Great Britain had nine operational international electricity interconnectors.

The UK is becoming an offshore energy substation on Europe’s North-West coast.

 

 

April 2, 2026 Posted by | Energy | , , , , , , , , , , , , , , , | Leave a comment

Do British And German Offshore Wind Farm Generate Maximum Power At Different Times

In National Grid, TenneT Germany Launch GriffinLink, A First Of A Find Project To Maximise Offshore Wind, I discussed GriffinLink, which will be an offshore link between British and German offshore wind farms.

Somebody has asked me if wind farms are in phase with each other, as obviously this would effect how they perform and are are controlled.

So I asked Google AI, the question in the title of this post and received this reply.

Yes, British and German offshore wind farms often generate their maximum power at different times, although they are both located in the North Sea and share similar peak seasons. The variations in generation are driven by localized weather patterns, specifically the movement of low-pressure systems.

Key Differences in Generation Times:

Regional Weather Patterns: While North Sea wind farms are often closely correlated, significant differences arise when weather systems move from west to east. Wind often hits the UK’s North Sea sites first, meaning they may hit maximum generation capacity hours before German or Danish sites, which are further east.

Time of Day (Diurnal Differences): Because UK wind farms are located in the Irish Sea, the Scottish coast, and the North Sea, they can exhibit different diurnal (daily) peak times compared to German sites in the North Sea and Baltic Sea.

Seasonal Peaks: Both countries experience the highest output during winter months (e.g., December). However, during specific, localized, long-lasting high-pressure systems (“Dunkelflaute”), one country might experience a complete drop in wind while the other continues to produce, or vice versa.

Why They Differ:

Geography: The UK’s extensive, spread-out coastline (Irish Sea, Atlantic coast, North Sea) offers a different wind profile than the more concentrated German offshore projects in the North Sea and Baltic Sea.

Correlation Challenges: Research shows that while North Sea countries have similar wind profiles, there is not 100% correlation. Meteorological differences in how wind speeds behave across the North Sea allow for complementary production.

This difference is highly advantageous for European energy security, as it allows for the balancing of intermittent wind power across the region.

The conclusion from Google AI, is almost predicting that GriffinLink will be developed. From my experience of mathematical modelling the cost and financial benefits should be fairly easy to predict.

Will The UK And The Republic Of Ireland Link Their Offshore Wind Farms To Improve Efficiency?

This may seem an obvious idea, especially as UK and Republic of Ireland are heavily interconnected.

So I asked Google AI, the question in the title of this section and received this reply.

Yes, the United Kingdom and the Republic of Ireland are taking significant, active steps to link their offshore wind farms and electricity grids to improve efficiency, increase renewable energy production, and enhance energy security. Following a Memorandum of Understanding (MoU) signed in September 2023, the two countries are collaborating on developing subsea energy infrastructure in the Irish and Celtic Seas.

Here are the key details regarding this cooperation:

Deepened Collaboration: As of March 2025, the UK and Ireland are working on a new data-sharing arrangement to lay the groundwork for directly connecting offshore wind farms to each other’s national energy networks.

Offshore Hybrid Assets (OHAs): The plans include developing offshore hybrid assets, which are subsea cables that directly link offshore wind farms to both countries’ grids, reducing infrastructure costs and maximizing efficiency.

Subsea Mapping & Interconnection: Both nations are mapping the Celtic Sea to identify optimal locations for interconnectors and to improve the interoperability of their grids.

Existing & New Projects: While Ireland’s current interconnection to the UK is limited (approx. 500MW), capacity is planned to increase significantly. Specific projects like Mares Connect (linking North Wales and Ireland) are being developed to provide750MW of additional capacity.

Regional Cooperation: Ireland is also participating in the “Hamburg Declaration” (signed Jan 2026), joining the UK and other North Sea countries to commit to 300GW of offshore wind by 2050 through shared, regional infrastructure.

This cooperation aims to allow Ireland to export its surplus renewable energy during high generation, while benefiting from the UK’s robust grid during lower wind conditions.

Will The UK AndNorway Link Their Offshore Wind Farms To Improve Efficiency?

As we have interconnectors with Norway, I asked Google AI, the question in the title of this section and received this reply.

Yes, the UK and Norway are actively planning and implementing initiatives to link their offshore wind farms and electricity grids to improve efficiency, energy security, and grid balancing. Following a series of agreements, including a major pact in January 2026, the two countries are collaborating on “hybrid” projects that connect offshore wind sites directly to multiple countries.

It does look like that the co-operations between the UK and Germany, Norway and the Republic of Ireland are setting examples that should be copied all over the world.

But then, you should always follow the mathematics.

But somehow, I can’t see President Trump signing any windmill co-operation with his neighbours.

February 23, 2026 Posted by | Artificial Intelligence, Energy | , , , , , , , , , , , , , , , , , , | Leave a comment

National Grid, TenneT Germany Launch GriffinLink, A First Of A Find Project To Maximise Offshore Wind

The title of this post is the sane as that of this press release from National Grid.

These three bullet points serve as sub headings.

  • National Grid and TenneT Germany announce our cooperation on GriffinLink, a planned GB-Germany multi-purpose interconnector (MPI).

  • GriffinLink would support energy security, accelerate the connection of offshore wind and mark a coordinated approach on supply chains and infrastructure.

  • Announced at the North Sea Summit in Hamburg, the project could maximise shared offshore wind resources in the most efficient way.

These two paragraphs add more detail.

National Grid will partner with TenneT Germany to develop GriffinLink, a new multi-purpose interconnector (MPI) project, which could connect British and German offshore wind to both countries. It marks a step towards a more integrated, flexible, and efficient energy system for both Great Britain and Germany which delivers secure, affordable energy for consumers.

GriffinLink could make an important contribution to security of supply and market integration in northwestern Europe. Cross-border hybrid energy systems such as GriffinLink make it possible to feed cleaner electricity into the grid where it can be generated and transport it exactly where it is needed.

Note this integrated approach means.

  1. Better utilisation of the grids and is a more efficient use of renewable energy across national borders;
  2. Lowering the costs involved, and the supply chain materials required and;
  3. A reduced impact on coastal communities and the environment.

As a ‘multi-purpose’ interconnector connecting wind in two countries, GriffinLink would be the first project of its kind in Europe and a milestone for cross-border energy security and stability.

It will also connect the UK’s offshore wind power to someone someone who needs it and will pay good money for it.

I asked Google AI, “How much energy we will be exporting to Europe in 2030” and received this reply.

By 2030, the UK is expected to be exporting significant amounts of electricity to Germany, largely enabled by the NeuConnect interconnector, which is set to become operational around 2028 and will have a capacity of 1.4 GW. While precise, definitive figures for 2030 are subject to market conditions, key data suggests:

NeuConnect Capacity: The 725km subsea link between Kent (UK) and Wilhelmshaven (Germany) will allow 1.4 GW of electricity to flow in either direction.

Net Export Position: The UK is positioned to become a net exporter of electricity to Europe by the 2030s, fueled by a massive expansion in offshore wind capacity, aiming for up to 50GW by 2030.

Grid Interconnection: By 2030, the UK’s total interconnection capacity to Europe is planned to increase to 18GW, up from 8GW.

Hydrogen Focus: In addition to electricity, the UK is exploring the potential to export up to 35 TWh of hydrogen to Germany by 2030.

That will do nicely!

 

February 11, 2026 Posted by | Artificial Intelligence, Energy, Hydrogen | , , , , , , | 1 Comment

Britain’s Biggest Clean Power Projects Among 2.4GW Of Transmission Connections National Grid Delivers In 2025

The title of this post, is the same as that of this press release from National Grid.

This is the sub-heading.

Record-breaking renewable power projects are among the 2.4GW of new generation connections we plugged into our transmission network during 2025, in another key step in the UK’s clean energy transition.

This first paragraph adds some detail to the headlines.

This year’s works build on the 3GW of connections we delivered in 2024 – which included a new interconnector between Wales and Ireland – and is part of 12.6GW of generation capacity we’ve connected in England and Wales over the past five years.

The rate of connections appear to have been fairly steady over the last five years, at about 2.5 GW/year.

Three projects are highlighted.

  • In April the 373MW Cleve Hill Solar Park, Britain’s largest solar array, began exporting power across the network following work to connect it at our Cleve Hill substation in Kent.

 

  • Over summer Statera Energy’s Thurrock Storage project, the country’s biggest battery energy storage system (BESS), connected at our Tilbury substation in Essex to add 300MW of flexible capacity across London and the south east.

 

  • And in September we completed upgrades and commissioning activity at our Lackenby substation in North Yorkshire in readiness for RWE’s Sofia offshore wind farm – one of the world’s biggest – to complete construction.

They also completed works for more than 400MW of additional BESS connections during the year, including a 150MW scheme connecting at Ferrybridge substation in West Yorkshire, a 100MW facility plugging in at Thornton substation in North Yorkshire, and further projects at our substations in Enderby (Leicestershire), Rainhill (Merseyside) and Bredbury (Greater Manchester).

I think that adds up to ten projects in total.

It looks like National Grid had a good year.

 

January 5, 2026 Posted by | Energy, Energy Storage | , , , , , | 2 Comments

£1.5 billion Enables UK-US Pair To Get Their Hands On Europe’s Giant LNG Terminal

The title of this post, is the same as that of this article on Offshore Energy.

This is the sub-heading.

UK-based energy player Centrica and U.S. investment firm Energy Capital Partners (ECP), part of Bridgeport Group, have brought into their fold a liquefied natural gas (LNG) terminal in Kent County, United Kingdom.

This paragraph gives Centrica’s view of the Grain LNG Terminal.

The UK firm portrays the terminal as Europe’s largest LNG regasification facility, with a capacity of 15 million tonnes of LNG a year. Located on the UK’s Isle of Grain, the terminal features unloading infrastructure, regasification equipment, and truck-loading facilities.

In a press release, which is entitled Investment in Grain LNG, that was published in August 2025, Centrica said this.

Opportunities for efficiencies to create additional near-term value, and future development options including a combined heat and power plant, bunkering, hydrogen and ammonia.

The tone of the article in Offshore Energy and the press release is unmistakable. – Centrica intend to make good use of their investment.

I suggest you read both documents fully.

  •  Europe’s largest LNG regasification facility, with a capacity of 15 million tonnes of LNG a year, will certainly need a large combined heat and power plant.
  • Will any spare power from the CHP plant, be sent to Germany, through the 1.4 GW NeuConnect interconnector, which should be commissioned by 2028?
  • Hydrogen, ammonia and LNG are the three low-carbon fuels used by modern ships, so I suspect hydrogen and ammonia will be produced on the island.
  • Centrica are investors in the efficient hydrogen-generation process ; HiiROC.
  • Hydrogen and nitrogen are the two feedstocks for ammonia.

Centrica certainly have big plans for the Grain LNG Terminal.

I shall be following Centrica closely.

 

 

 

 

 

 

December 1, 2025 Posted by | Energy, Hydrogen | , , , , , , , , , | Leave a comment

National Grid And Emerald AI Announce Strategic Partnership To Demonstrate AI Power Flexibility In The UK

The title of this post, is the same as that of this press release from National Grid.

This is the sub-heading.

National Grid and Emerald AI are partnering to show how AI data centres can support a smarter, more flexible grid.
A UK-first live trial is planned for late 2025 on a grid connected data centre using Emerald AI’s platform.
Targeted for late 2025, the demonstration will use cutting-edge NVIDIA GPUs, to dynamically adjust energy consumption
Increased flexibility of data centre consumption can unlock capacity and accelerate connections to the electricity network.

These three introductory paragraphs indicate how the strategy partnership will work.

National Grid and Emerald AI today announced a strategic partnership to demonstrate how AI data centres can work with the transmission network to adjust their energy use in real time, making better use of existing capacity to support the UK’s growing digital needs.

The partners will deliver a live demonstration in the United Kingdom showcasing Emerald Conductor, an AI-powered system that acts as a smart mediator between the grid and a data centre, supporting flexible management of energy demand. Targeted for late 2025, the demonstration will use cutting-edge NVIDIA GPUs, dynamically adjust energy consumption, and support grid stability.

The electricity transmission network is designed with built-in redundancy to deliver world-class reliability and keep the lights on for customers. Capacity is typically available outside of peak events like hot summer days or cold winter storms, when there’s high demand for cooling and heating. That means, in many cases, there’s room on the existing grid to connect new data centres, if they can temporarily dial down energy usage during periods of peak demand.

Yesterday, there was an article in The Times which was entitled Octopus Energy Prepares Kraken Software Arm for Potential IPO.

I asked Google AI what Octopus Energy’s Kraken software does and received this answer.

Launched as part of the Octopus Energy Group in 2016, Kraken now serves 70 million household and business energy accounts worldwide through an operating system that processes 15 billion new data points each day. The software underpins Octopus Energy’s customer management and increasingly sophisticated smart tariffs.

I wouldn’t be surprised that similar methodology is used by both Emerald IT and Kraken.

As I have written at least four scheduling algorithms to best allocate available resources to tasks that need to be done for project management and other similar fields, I would have my ideas about the methods used by the two companies.

I am also sure, that the generic algorithm, that I have used in the past, could step up to the plate one more time, if anybody were to be interested.

 

September 19, 2025 Posted by | Computing, Energy | , , , , , , | 1 Comment

National Grid Has Awarded £12bn In HVDC Supply Chain Agreements

The title of this post, is the same as that of this press release from National Grid.

These are the first three paragraphs.

National Grid has completed the award of its High Voltage Direct Current (HVDC) civil works supply chain framework, with £12bn worth of agreements confirmed. This announcement marks the third and final stage of our £59bn supply chain framework awards and underlines the commitment to delivering the energy infrastructure needed to support the Great Grid Upgrade and the UK’s energy transition.

A total of six HVDC converter civil works suppliers have been awarded positions on Lot 1 of the Framework Agreement totalling approximately £9.07bn. In addition, three HVDC onshore cable civil works suppliers being awarded places on Lot 2 of the Framework, worth an estimated £3.7bn. The successful HVDC converter civils suppliers are Balfour Beatty, BAM Nuttall, Galliford Try, Laing O’Rourke, Skanska and Taylor Woodrow. The HVDC onshore cable civils Framework has been awarded to Balfour Beatty, Murphy, and VolkerFitzpatrick.

Contracts have been secured for a five-year period, with the potential to extend for a further three years. Both Frameworks cover confirmed and anticipated projects, including Eastern Green Link 4, in partnership with SP Energy Networks and LionLink in partnership with TenneT .

These are a lot of money allocated to projects, that will be delivered in the next few years.

Where’s the consolidated plan for capital expenditure from the Water Industry?

Water is also simpler, than electricity, as you are only dealing with one country. If you go through the paragraphs above, you’ll find TenneT, who do a similar job to National Grid in the Netherlands and parts of Germany.

I also found this advert from Thames Water, in a Southeastern train last week.

Does this indicate that Thames Water has project management problems?

August 25, 2025 Posted by | Energy, Environment | , , , , | Leave a comment