The Anonymous Widower

Flotation, Vargronn Complete NorthConnect Deal

The title of this post, is the same as that of this article on Renews.biz.

This is the sub-heading.

1.4GW Cenos floater backers seal ‘productive partnership’ with interconnector acquisition

These three paragraphs add more details to the deal.

Flotation Energy and Vargronn have closed their acquisition of the NorthConnect interconnector project between Scotland and Norway.

The developers said the deal had followed close collaboration on shared transmission infrastructure and a common grid connection point for the interconnector and the proposed 1.4GW Cenos floating wind farm off east Scotland.

NorthConnect already has consent for an offshore and onshore cable route to a substation near Boddam, Aberdeenshire, that will link to SSEN’s Peterhead substation.

This looks like a clever use of the permissions for the interconnector to connect the Cenos wind farm to the grid.

June 13, 2025 Posted by | Energy | , , , , , | Leave a comment

UK Energy Grid Needs £60bn Upgrade To Hit Green Target, Plan Says

The title of this post, is the same as that of this article on the BBC.

This is the sub-heading.

The UK’s electricity network needs almost a further £60bn of upgrades to hit government decarbonisation targets by 2035, according to a new plan.

These five paragraphs explain the plan.

About 4,000 miles of undersea cables and 1,000 miles of onshore power lines are needed, said the National Grid’s Electricity Systems Operator (ESO).

The investment would add between £20 to £30 a year to customer bills, it said.

The government said the ESO’s plans were preliminary and yet to pass a “robust planning process”.

The plans were written up by the ESO, the organisation which runs the electricity network and would run the updated system it is calling for too. It is currently owned by National Grid but will transfer into government ownership later this year.

Its latest £58bn estimate is for work needed between 2030 and 2035 and comes on top of a previous £54bn estimate for work taking place between now and 2030.

These are my thoughts.

The Amount Of Undersea Cable

Edinburgh and London are roughly 400 miles apart as the train runs, so it looks like there could be the equivalent of ten underwater cables between the North of Scotland and England.

In Contracts Signed For Eastern Green Link 2 Cable And Converter Stations, I talked about the proposed 2 GW link between Peterhead in Scotland and Drax in England, which will be a double cable. So there’s the first two of these long cables.

It looks to me, that National Grid are proposing to use underwater cables wherever they can, so they avoid large expensive planning rows stirred up by Nimbies.

Monitoring The Undersea Cables

Last week Ofgem gave National Grid a £400,000 grant to develop new innovative technologies, which I wrote about in £400k For National Grid Innovation Projects As Part Of Ofgem Fund To Help Shape Britain’s Net Zero Transition.

One of the project is called HIRE – Hybrid-Network Improvement & Reliability Enhancement and will be used to check all these cables are performing as they should.

My electrical engineering experience tells me, that there must be some cunning way, that will detect that something is happening to the cable. The involvement of a technology company called Monitra in the project is a bit of a giveaway.

How Much Will It Cost Me?

Currently, UK consumers pay about £30 per year to have electricity delivered, so this will rise to between £50 and £60 per year.

That is just over a pound a week. I would pay about the same for a resident’s parking permit outside my house for an electric car and probably three times more for a petrol or diesel car.

Do We Have Enough Cable?

Two undersea cable factories are under development in Scotland and I suspect the 4,000 miles of undersea cables will be delivered on schedule and covered in saltires.

What About T-Pylons?

The latest onshore electricity transmission line between Hinckley Point C and Bristol, doesn’t use traditional pylons.

It uses T-pylons like these to connect the 3.26 GW nuclear power station.

Note that they are shorter, designed to be less intrusive, have a smaller footprint and are made from only ten parts.

I suspect they will cost less to install and maintain.

There is more on T-pylons in National Grid Energise World’s First T-Pylons.

I wouldn’t be surprised that some of the oldest traditional pylons will be replaced by T-pylons.

I am surprised that T-pylons are not mentioned in the BBC article.

I like T-pylons. How do you feel about them?

Eastern Green Link 2

This press release from National Grid, describes Eastern Green Link 2 like this.

Eastern Green Link 2 (EGL2) is a 525kV, 2GW high voltage direct current (HVDC) subsea transmission cable from Peterhead in Scotland to Drax in England delivered as a joint venture by National Grid and SSEN Transmission.

This map from National Grid, shows the route of the Eastern Green Link 2.

The Northern landfall is at Sandford Bay and the Southern landfall is at Wilsthorpe Beach.

This Google Map shows Sandford Bay and Peterhead power station.

Note.

  1. Sandford Bay occupies the North-East corner of the map.
  2. The red arrow indicates the main 400kV sub-station at Peterhead.
  3. The 2177 MW gas-fired Peterhead power station is to the East of the sub-station marked as SSE.

This second Google Map shows the onshore route of the cable from Wilsthorpe to Drax.

Note.

  1. Flamborough Head is in the North-East corner of the map.
  2. Wilsthorpe Beach is at Bridlington a couple of miles South of Flamborough Head.
  3. The red arrow indicates Drax Power station.
  4. An onshore underground cable will be installed from landfall in Wilsthorpe to a new onshore converter station built in Drax.

The EGL2 HVDC cable connection from Scotland to England consists of 436km of submarine cable and 69km of onshore cable.

Both converter stations will be on existing power station sites and the major onshore works will be the underground cable between Wilsthorpe and Drax.

Where Does Drax Go From Here?

Currently, Drax power station is a 2595 MW biomass-fired power station.

There are now other large power sources that could replace some or all of the output of Drax power station.

  • 2GW of Scottish wind power coming to Drax on Eastern Green Link 2.
  • 6 GW of offshore wind is being developed at the Hornsea wind farms.
  • 8 GW of offshore wind is being developed at the Dogger Bank wind farms.
  • 2.5 GW from the three gas-fired power stations at Keadby, two of which are likely to be fitted with carbon capture.
  • 1.8 GW from the proposed hydrogen-fired Keadby Hydrogen power station.

Given the bad feelings many have about Drax burning biomass, with 20.3 GW of electricity, you might think that shutting down Drax would be a simple solution.

But, according to Drax’s Wikipedia entry, it has a unique property.

Despite this intent for baseload operation, it was designed with a reasonable ability for load-following, being able to ramp up or down by 5% of full power per minute within the range of 50–100% of full power.

So Drax could be very useful in balancing the grid, by ramping up and down to fill the gap between production and need.

In addition, there is good biomass. This is from the Wikipedia entry.

A 100,000 tonne pa capacity straw pelletization facility was constructed at Capitol Park, Goole in 2008.

Drax are also promoting BECCS or Bioenergy carbon-capture and storage.

There is a Wikipedia entry for Bioenergy With Carbon Capture And Storage, of which this is the first couple of sentences.

Bioenergy with carbon capture and storage (BECCS) is the process of extracting bioenergy from biomass and capturing and storing the carbon, thereby removing it from the atmosphere. BECCS can theoretically be a “negative emissions technology” (NET).

I do feel that carbon capture and storage is a bit like sweeping the dust under the carpet, when you sweep the floor around it.

But carbon capture and use could be another matter.

This Google Map shows the Drax site.

Note how it is surrounded by agricultural land.

Could the power station be the source of pure carbon dioxide to be fed in greenhouses to flowers, herbs, salad vegetables, tomatoes and other plants?

I suspect there’s productive life left in Drax power station yet!

LionLink

LionLink, that is being developed by National Grid is a new type of interconnector, called a multi-purpose interconnector, that will connect Suffolk and The Netherlands via any convenient wind farms on the way. This means that the electricity generated can go where it is needed most.

I wrote about LionLink in World’s Largest-Of-Its-Kind Power Line To Deliver Clean Power To 1.8m UK Homes And Boost Energy Security.

Other Multi-Purpose Interconnectors

I can see other multi-purpose interconnectors like LionLink being built around the UK.

  • There could be one across the Dogger Bank to link out 8 GW of Dogger Bank wind farms with those of the Dutch, Danes and Germans on their section of the bank.
  • NorthConnect could be built between Scotland and Norway via some of the wind farms being developed to the North-East of Scotland.
  • Could wind farms to the North of Ireland use a multi-purpose interconnector between Scotland and Northern Ireland.
  • I can also see one or possibly two, being built across the Celtic Sea to link Devon, South Wales and Southern Ireland via the wind farms being developed in the area.
  • Will we also see a Channel multi-purpose interconnector to transfer electricity along the South Coast of England?

Some of these multi-purpose interconnectors could be key to creating a revenue stream, by exporting electricity, to countries in Europe, that have a pressing need for it.

Conclusion

National Grid’s excellent plan will lead to the end of the practice of shutting down wind turbines. The spare electricity will be exported to Europe, which will surely create a good cash-flow for the UK. This in turn will encourage developers to create more wind farms in the seas around the UK’s coasts.

March 19, 2024 Posted by | Energy | , , , , , , , , , , , , , , , , , , , , , | 8 Comments

13 Offshore Wind Projects Selected In World’s First Innovation And Targeted Oil & Gas Leasing Round

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

Crown Estate Scotland has selected 13 out of a total of 19 applications with a combined capacity of around 5.5 GW in the world’s first leasing round designed to enable offshore wind energy to directly supply offshore oil and gas platforms.

This paragraph outlines INTOG (Innovation and Targeted Oil & Gas) and its objectives.

INTOG, which has been designed in response to demand from government and industry to help achieve the targets of the North Sea Transition Sector Deal through decarbonising North Sea oil and gas operations, is also expected to further stimulate innovation in Scotland’s offshore wind sector, create additional supply chain opportunity, assist companies to enter the renewable energy market, and support net-zero ambitions.

This is undoubtedly the most important news of the day.

  • When complete it will generate 5416 MW of electricity.
  • 4068 MW will be used primarily to decarbonise oil and gas platforms with surplus electricity going to the grid.
  • The amount of carbon dioxide released by oil and gas platforms in the North Sea will be reduced.
  • The gas saved by decarbonising oil and gas platforms, will be transported to the shore and used in the UK gas grid.
  • 449 MW will be generated in innovative ways in small wind farms, with a capacity of less than 100 MW.

One of the benefits of INTOG is that the UK will be able to reduce gas imports, which must increase energy security.

This map from this document from the Crown Estate Scotland, shows the INTOG wind farms.

This is a list of the farms.

  • 1 – Bluefloat Energy/Renantis Partnership – Innovation – Commercial – 99.45 MW
  • 2 – Bluefloat Energy/Renantis Partnership – Innovation – Supply Chain – 99.45 MW
  • 3 – Simply Blue Energy (Scotland) – Innovation – Supply Chain – 100 MW
  • 4 – BP Alternative Energy Investments – Innovation – New Markets – 50 MW
  • 5 – ESB Asset Development – Innovation – Cost Reduction – 100 MW
  • 6 – Floatation Energy – Targeted Oil & Gas – 560 MW
  • 7 – Cerulean Winds – Targeted Oil & Gas – 1008 MW
  • 8 – Harbour Energy – Targeted Oil & Gas – 15 MW
  • 9 – Cerulean Winds – Targeted Oil & Gas – 1008 MW
  • 10 – Cerulean Winds – Targeted Oil & Gas – 1008 MW
  • 11 – Floatation Energy – Targeted Oil & Gas – 1350 MW
  • 12 – TotalEnergies – Targeted Oil & Gas – 3 MW
  • 13 – Harbour Energy – Targeted Oil & Gas – 15 MW

Note.

  1. These total up to 5.42 GW.
  2. The five Innovation sites seem to be as close to the coast as is possible.
  3. I thought some Innovation sites would be closer, so supply difficult to reach communities, but they aren’t.
  4. Floatation Energy and Cerulean Winds seemed to have bagged the lion’s share of the Targeted Oil & Gas.
  5. Sites 6 and 7 sit either side of a square area, where Targeted Oil & Gas will be considered. Is that area, the cluster of oil and gas facilities around Forties Unity, shown on the map in this page on the BP web site?
  6. Harbour Energy have secured two 15 MW sites for Targeted Oil & Gas.

These are my thoughts on the various companies.

Bluefloat Energy

Bluefloat Energy has posted this press release on their web site, which is entitled Bluefloat Energy | Renantis Partnership Bid Success For Two 99mw Innovation Projects In Crown Estate Scotland’s INTOG Process.

The press release starts with these three bullet points.

  • BlueFloat Energy | Renantis Partnership offered exclusivity rights to develop its Sinclair and Scaraben floating wind projects north of Fraserburgh – leveraging synergies via its 900MW Broadshore project.
  • The projects seek to trial innovative floating wind technology solutions, kick-starting supply chain growth and job creation in Scotland and providing a ‘stepping-stone’ to the partnership’s ScotWind projects.
  • Bid proposals include the intention to develop a scalable community benefit model – creating a potential blueprint for floating offshore wind in Scotland.

The first three paragraphs expand the bullet points.

The BlueFloat Energy and Renantis Partnership has been offered seabed exclusivity rights to develop two 99MW projects under the innovation arm of Crown Estate Scotland’s INTOG (Innovation and Targeted Oil & Gas) auction process. The auction saw ten projects bid to bring forward the development of small-scale innovation projects.

The Sinclair and Scaraben projects, located north of Fraserburgh and adjacent to the Partnership’s 900MW Broadshore project, seek to trial innovative foundation technologies, associated fabrication works and mooring systems with a view to maximising opportunities for the Scottish supply chain, driving local investment and job creation.

A key element of the bid proposals is the opportunity to test and adapt a community benefit model, governed independently, and directed by the communities in which the schemes will operate, through collaboration with our supply chain and project partners. The model could create a blueprint, shaping the future of community benefit from floating offshore wind throughout the whole of Scotland. This builds on Renantis’ successful track record of deploying similar schemes via its onshore wind farms in Scotland.

Note.

  1. Companies called Sinclair Offshore Wind Farm and Scaraben Offshore Wind Farm were registered a few months ago in Inverness.
  2. I couldn’t find the websites, so I suspect they’re still being created.
  3. These two projects appear to be pathfinders for the 900 MW Broadshore project, with regards to the supply chain and community involvement.

It certainly looks like the partnership are going about the development of these two projects in a professional manner.

BP Alternative Energy Investments

There has been no press release from BP as I write this, so I will have to deduce what BP are planning.

This map from this document from the Crown Estate Scotland, shows the Southern INTOG wind farms.

Note.

  1. Site 4 is the site of BP Alternative Energy Investments’s proposed wind farm.
  2. Sites 6 and 7 could be either side of the cluster of platforms around Forties Unity.

Consider.

  • In the wider picture of wind in the North Sea, BP’s proposed 50 MW wind farm is a miniscule one. SSE Renewables’s Dogger Bank wind farm is over a hundred times as large.
  • A cable to the shore and substation for just one 50 MW wind farm would surely be expensive.
  • BP Alternative Energy Investments are also developing a 2.9 GW wind farm some sixty miles to the South.
  • It would probably be bad financial planning to put large and small wind farms so close together.

For these are other reasons, I believe that there is no reason to believe that the proposed 50 MW wind farm is a traditional wind farm.

But if I’m right about sites 6 and 7 indicating the location the position of Forties Unity, it might open up other possibilities.

This document from INEOS, who own the Forties Pipeline System, explains how the pipeline works.

The Forties Pipeline System (FPS) is an integrated oil and gas transportation and processing system. It is owned and operated by INEOS and utilises more than 500 miles of pipeline to smoothly transport crude oil and gas from more than 80 offshore fields for processing at the Kinneil Terminal. At Kinneil the oil and gas are separated, with the oil returned as Forties Blend to customers at Hound Point or pumped to the Petroineos refinery at Grangemouth.
At the same time the gas goes to our LPG export facilities or is supplied to the INEOS petrochemical plant. FPS transports around 40% of the UK’s oil production supply and brings over 400,000 barrels ashore every day.

In Can The UK Have A Capacity To Create Five GW Of Green Hydrogen?, I said the following.

Ryze Hydrogen are building the Herne Bay electrolyser.

  • It will consume 23 MW of solar and wind power.
  • It will produce ten tonnes of hydrogen per day.

The electrolyser will consume 552 MWh to produce ten tonnes of hydrogen, so creating one tonne of hydrogen needs 55.2 MWh of electricity.

If BP were to pair the wind farm with a  50 MW electrolyser it will produce 21.7 tonnes of hydrogen per day.

Could it be brought to the shore, by linking it by a pipeline to Forties Unity and then using the Forties Pipeline System?

As the category on site 4, is New Markets, are BP and INEOS investigating new markets for hydrogen and hydrogen blends?

  • Some of the latest electrolysers don’t need pure water and can use sea water. This makes them more affordable.
  • Do BP and/or INEOS have the capability to extract the hydrogen as it passes through the Cruden Bay terminal, to provide the hydrogen for Aberdeen’s buses and other users?
  • INEOS and BP probably have some of the best oil and gas engineers in the world.
  • How many other places in the world have an offshore oil or gas field set in a windy sea, where floating wind- turbine/electrolysers could generate hydrogen and send it ashore in an existing pipeline?
  • Several of these offshore oil and gas fields and the pipelines could even be owned by BP or its associates.
  • Remember that hydrogen is the lightest element, so I suspect it could be separated out by using this property.

This BP site, is to me, one of the most interesting of the successful bids.

  • BP probably have a large collection of bonkers ideas, that have been suggested during their long involvement with offshore oil and gas.
  • Some ideas could be even suggested by employees, whose fathers worked for BP fifty years ago. I’ve met a few BP employees, whose father also did.
  • Will the wind farm, be a floating electrolyser at the centre of a cluster of a few large floating turbines?
  • Will each turbine have its own electrolyser and the substation only handle hydrogen?
  • Will the floating electrolyser have hydrogen storage?
  • Have BP got a floating or semi-submersible platform, that could either go to the breakers or be repurposed as the floating electrolyser?
  • Repurposing a previous platform, would make all the right noises.

So many possibilities and so far, no clues as to what will be built have been given.

See also.

Further Thoughts On BP’s Successful INTOG Bid

Cerulean Winds

In What Is INTOG?, I said this about Cerulean Winds.

Cerulean sounds like it could be a sea monster, but it is a shade of blue.

This article on offshoreWind.biz is entitled Cerulean Reveals 6 GW Floating Offshore Wind Bid Under INTOG Leasing Round.

These are the two introductory paragraphs.

Green energy infrastructure developer Cerulean Winds has revealed it will bid for four seabed lease sites with a combined capacity of 6 GW of floating wind to decarbonise the UK’s oil and gas sector under Crown Estate Scotland’s Innovation and Targeted Oil and Gas (INTOG) leasing round.

This scale will remove more emissions quickly, keep costs lower for platform operators and provide the anchor for large-scale North-South offshore transmission, Cerulean Winds said.

Note.

    1. It is privately-funded project, that needs no government subsidy and will cost £30 billion.
    2. It looks like each site will be a hundred turbines.
    3. If they’re the same, they could be 1.5 GW each.
    4. Each site will need £7.5 billion of investment. So it looks like Cerulean have access to a similar magic money tree as Kwasi Kwarteng.

Effectively, they’re building four 1.5 GW power stations in the seas around us to power a large proportion of the oil and gas rigs.

For more on Cerulean Winds’s massive project see Cerulean Winds Is A Different Type Of Wind Energy Company.

So does it mean, that instead of 6 GW, they were only successful at three sites and the other or others were in the six unsuccessful applications?

There is a press release on the Cerulean Winds web site, which is entitled Cerulean Winds Wins Bid For Three INTOG Floating Wind Sites, where this is said.

Cerulean Winds and Frontier Power International have been awarded three lease options for the Central North Sea in the highly competitive INTOG leasing round, the results of which were announced by Crown Estate Scotland today.

The sites, in the Central North Sea, will enable the green infrastructure developer and its partners to develop large floating offshore windfarms to decarbonise oil and gas assets. The scale of the development will enable a UK wide offshore transmission system, that can offer green energy to offshore assets in any location and create a beneficial export opportunity.

Nothing about unsuccessful applications was said.

This map from this document from the Crown Estate Scotland, shows the Southern INTOG wind farms.

Note.

  1. Sites 7, 9 and 10 are Cerulean’s sites.
  2. Sites 6 and 11 are Floatation Energy’s sites.
  3. Site 4 is BP Alternative Energy Investments’s Innovation site.
  4. Sites 8, 12 and 13 are much smaller sites.

It looks like Cerulean and Floatation Energy are well-placed to power a sizeable proportion of the platforms in the area.

ESB Asset Development

ESB Asset Development appear to be a subsidiary of ESB Group.

The ESB Group is described like this in the first paragraph of their Wikipedia entry.

The Electricity Supply Board is a state owned (95%; the rest are owned by employees) electricity company operating in the Republic of Ireland. While historically a monopoly, the ESB now operates as a commercial semi-state concern in a “liberalised” and competitive market. It is a statutory corporation whose members are appointed by the Government of Ireland.

This press release, is entitled ESB Offered Exclusive Rights To Develop Innovative 100MW Floating Offshore Wind Project In The Malin Sea.

These two paragraphs outline the project.

ESB today welcomes the outcome of Crown Estate Scotland’s latest seabed leasing process which has resulted in the offer of exclusive development rights to ESB for a 100MW floating wind project in Scottish waters off the north coast of Northern Ireland. The successful project, Malin Sea Wind, is a collaborative bid between ESB and leading technology developers Dublin Offshore Technology and Belfast-based CATAGEN. The outcome underscores ESB’s growing capabilities and expanding presence in the offshore wind industry.

The Innovation and Targeted Oil and Gas (INTOG) seabed leasing process, run by Crown Estate Scotland, aims to drive cost reduction in the offshore wind sector by enabling the deployment of new and innovative technologies, and to harness wind energy to decarbonize the oil and gas sector. Malin Sea Wind aims to support the reduction of floating offshore wind costs by demonstrating Dublin Offshore’s patented load-reduction technology. Furthermore, the project will support decarbonisation of the aviation sector by powering sustainable aviation fuel (SAF) production technology currently under development by net-zero technology specialists, CATAGEN.

Note.

  1. I’ve just looked at the Technology page of the Dublin Offshore Technology web site.
  2. In the 1970s, I built large numbers of mathematical models of steel, concrete and water cylinders in my work with a Cambridge University spin-out called Balaena Structures.
  3. I believe, that an experienced mathematically modeller could simulate this clever system.

That would prove if it works or not!

This Google Map shows the Malin Sea.

Note.

  1. Malin Head is marked by the red arrows on the Northern Irish coast.
  2. The most Westerly Scottish island is Islay and the most Easterly is the Isle of Arran.
  3. Between the two islands is the Kintyre peninsula.
  4. Portrush can be picked out on the Northern Irish coast.

By overlaying the two maps, I suspect the centroid of the wind farm will be North of Portrush about a few miles North of the Southern end of Arran.

I suspect that if all goes well, there could be a lot of floating wind turbines in the area.

This Google Map shows the River Foyle estuary and Foyle Port to the North-East of Londonderry/Derry.

Note.

  1. Coolkeeragh ESB and Lisahally biomas power station on the South bank of the River Foyle.
  2. Lisahally biomas power station has a capacity of 16 MW.
  3. There appears to be a large substation at Coolkeeragh ESB.
  4. A tanker of some sort seems to be discharging.

Until told, I’ve guessed wrong, it looks to me like Coolkeeragh ESB could be the destination for the electricity generated by Malin Sea Wind. Given that this project’s aim is cost reduction, a 100 MW wind farm could make a difference.

In addition could Foyle Port be used to assemble and maintain the floating turbines?

Floatation Energy

Floatation Energy have posted this press release on their web site, which is entitled Flotation Energy and Vårgrønn Awarded Exclusivity To Develop Up To 1.9 GW Of Floating Offshore Wind In Scotland.

The first part of the press release, has a graphic.

It shows how their proposed system will work.

  • A floating wind farm will be placed between the shore and oil and gas platforms to be decarbonised.
  • The wind farm will be connected to the shore by means of a bi-directional cable, so that the wind farm can export electricity to the grid and when the wind isn’t blowing the grid can power the platforms.
  • A cable between the wind farm and the platforms completes the system.

It is a simple system, where all elements have been built many times.

Floatation Energy must have been fairly confident that their bids would be successful as they have already named the farms and set up web sites.

The websites are very informative.

The Timeline for 2019-2021 on the Green Volt web site describes the describes the progress so far on the project.

2019 – As construction of the Kindardine offshore floating wind farm kicks off, Flotation Energy identifies the Buzzard oil facility (a relatively new oil and gas platform with a long field life and high electrical load) as the optimal starting point for a significant contribution to the North Sea Transition Deal – the process of replacing large scale, inefficient gas-fired power generation with renewable electricity from offshore wind.

2020 – Flotation Energy begins environmental surveys on the Ettrick/Blackbird oil field, a redundant site nearby Buzzard, which is in the process of decommissioning. The “brownfield” site is confirmed as an exceptional opportunity to create an offshore floating wind farm, with water depths of 90-100m and high quality wind resource.

2021 – Flotation Energy works with regulators to understand the potential for project “Green Volt” to decarbonise offshore power generation for Buzzard. Flotation Energy completes and submits an Environmental Scoping report to Marine Scotland, reaching the first major milestone in the Marine Consent process. Crown Estate Scotland announces a new leasing round for Innovation and Targeted Oil and Gas Decarbonisation (INTOG).

On a section on the Cenos web site, there is a section called Efficient Grid Connection, where this is said.

The power generated by the wind turbines will be Alternating Current (AC) and routed to a substation platform. AC power will be exported to the oil and gas platforms.

For efficient export to the UK grid, the substation platform will include a converter station to change the AC power to Direct Current (DC) before the power is transported to shore. This is due to transporting AC power over long distances leading to much of the power being lost.

Cenos is working in partnership with the consented NorthConnect interconnector project, to utilise their DC cable routing where possible. Cenos will also use the NorthConnect onshore converter station planned for Fourfields near Boddam, which then has an agreed link into the Peterhead Substation. This collaboration minimises the need to construct additional infrastructure for the Cenos project.

That all sounds very practical.

Note.

  1. Floatation Energy delivered the Kincardine offshore floating wind farm.
  2. Both wind farms appear to use the same shore substation.
  3. Buzzard oil field is being expanded, so it could be an even more excellent oil field to decarbonise.
  4. NorthConnect is a bit of an on-off project.

Floatation Energy seem to have made a very professional start to the delivery of their two wind farms.

Harbour Energy

The Wikipedia entry for Harbour Energy describes the company like this.

Harbour Energy plc is an independent oil and gas company based in Edinburgh, Scotland. It is the United Kingdom’s largest independent oil and gas business. It is listed on the London Stock Exchange and is a constituent of the FTSE 250 Index.

But if you look at news items and the share price of the company, things could look better for Harbour Energy.

On their map of UK operations, I can count nearly twenty oil and gas fields.

As they have other oil and gas fields around the world, decarbonisation of their offshore operations could increase production by a few percent and substantially cut their carbon emissions.

That is a philosophy that could be good for profits and ultimately the share price.

So has the company gone for a very simple approach of two identical floating wind turbines?

They have been successful in obtaining leases for sites 8 and 13.

  • Both have a capacity of 15 MW, so are the farms a single 15 MW wind turbine?
  • I think this is likely, unless it is decided to opt for say a 16 MW turbine.
  • Or even a smaller one, if the platform is in a bad place for wind.
  • The wind turbine would be parked by the platform to be decarbonised and connected up, to a simple substation on the platform.
  • I would recommend a battery on the platform, so that if the wind wasn’t blowing, power was still supplied to the platform.
  • There would be no need for any cable between shore and wind farm and the only substation, would be a relatively simple one with a battery on the platform.

It could be a very efficient way of decarbonising a large number of platforms.

Once Harbour Energy have proved the concept, I could build a simple mathematical model in Excel, to work out any change in profitability and carbon emissions for a particular oil or gas platform.

Who Is Britannia Ltd?

In this document from the Crown Estate Scotland, there is a section that gives the partners in each project.

Listed for site 8 are Chrysaor (U.K.) and Britannia Limited and for site 13 is Chryasaor Petroleum Company UK Limited.

This page on the Harbour Energy web site gives the history of Chrysaor and Harbour Energy.

This is the heading.

Chrysaor was founded in 2007 with the purpose of applying development and commercial skills to oil and gas assets and to realise their value safely.

This is the history.

The Group grew rapidly over the years through a series of acquisitions. With backing from Harbour Energy – an investment vehicle formed by EIG Global Energy Partners – Chrysaor acquired significant asset packages in the UK North Sea from Shell (2017) and ConocoPhillips (2019) to become the UK’s largest producer of hydrocarbons.

In 2021, Chrysaor merged with Premier Oil to become Harbour Energy plc.

So that explains the use of the Chrysaor name or Chryasaor as someone misspelt it on the Crown Estate Scotland document.

I asked myself, if Britannia Ltd. could be a technology company, so I checked them out. The only company, I could find was a former investment trust, that was dissolved over ten years ago.

But Britannia is an oil and gas field in the North Sea, which is partially owned by Harbour Energy. It has a page on Harbour Enerrgy’s web site, which is entitled Greater Britannia Area.

This is said about the Britannia field.

Britannia in Block 16/26 of the UK central North Sea sits approximately 210-kilometres north east of Aberdeen. The complex consists of a drilling, production and accommodation platform, a long-term compression module of mono-column design and a 90-metre bridge connected to a production and utilities platform. Britannia is one of the largest natural gas and condensate fields in the North Sea. Commercial production began in 1998. Condensate is delivered through the Forties Pipeline to the oil stabilisation and processing plant at Kerse of Kinneil near Grangemouth and natural gas is transported through a dedicated Britannia pipeline to the Scottish Area Gas Evacuation (SAGE) facility at St Fergus.

Looking at the maps on the Crown Estate Scotland, Harbour Energy and others, it looks like site 8 could be close to the

Greater Britannia Area or even the Britannia field itself.

Simply Blue Energy

Simply Blue Energy are developing the 100 MW Salamander wind farm.

I wrote about this project in The Salamander Project.

Did it get chosen, as it was a project, where the design was at an advanced stage?

TotalEnergies

I wouldn’t be surprised to find out that TotalEnergies have gone a very similar route to Harbour Energy, but they are trying it out with a 3 MW turbine.

Conclusion

They are an excellent group of good ideas and let’s hope that they make others think in better and move innovative ways.

Politics will never save the world, but engineering and science just might!

March 25, 2023 Posted by | Energy, World | , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , | 4 Comments

Has The NorthConnect Interconnector Been Binned?

If you type “NorthConnect interconnector” into Google and select News, the latest stories are from March 2020.

One story from that date is this article on Energy Live News, which is entitled Norway Postpones Decision On Interconnector To Scotland.

These are the first three paragraphs.

The Norwegian Ministry of Petroleum and Energy (MPE) has postponed a decision on whether to allow the construction of a new subsea power cable between Norway and Scotland.

The 1,400MW Project NorthConnect, which is partly owned by Swedish energy group Vattenfall, has been put on hold pending public consultation and performance and cost reviews of similar projects under construction.

Minister of Petroleum and Energy Tina Bru, said: “The Norwegian and Nordic power system is going through significant changes, at a rapid pace. Two new interconnectors, to the UK and Germany respectively, will be commissioned in the near future.

The NorthConnect web site has some community news from last year.

So has this project been binned?

June 14, 2022 Posted by | Energy | , | 12 Comments

Is This The World’s Most Ambitious Green Energy Solution?

In the 1970s and 1980s, when I was developing Artemis, which was the first desk-sized project management system, we were heavily involved in North Sea Oil, with dozens of systems in Aberdeen.  As Norway developed the oil business on the other side of the North Sea, the number of systems there grew to at least twenty.

Increasingly, I became aware of a Norwegian company called Kværner, which seemed to have large numbers of Artemis systems.

In 2002, Kværner merged with Aker Maritime and this eventually led to the formation of Aker Solutions in 2008, which is a company that is headquartered in Oslo and employs nearly 14,000.

According to Wikipedia, the Kværner name was dropped somewhere along the way, as non-Scandinavians have difficulty pronouncing Kværner.

Aker Solutions appears to be wholly Scandinavian-owned, with Aker ASA owning a third of the company.

They are a very respected company, when it comes to offshore engineering for oil and gas and wind projects.

Aker ASA also have a subsidiary called Aker Horizons, which has this web site, where they call themselves a planet-positive company.

This page on the Aker Horizons is entitled Northern Horizons: A Pathway for Scotland to Become a Clean Energy Exporter.

These first two paragraphs outline the project.

A vision to utilise Scottish offshore wind resources in the North Sea to make the country an exporter of clean energy has been unveiled at the COP 26 climate change conference in Glasgow.

The Northern Horizons Project has been unveiled by Aker Horizons’ portfolio companies Aker Offshore Wind and Aker Clean Hydrogen, who have the technical know-how and expertise to realise the project, and DNV, the independent energy expert and assurance provider.

Various targets and ambitions are listed.

  • 10 GW of renewable energy in the North Sea.
  • 5 GW of green hydrogen.
  • Giant turbines nearly as tall as the London Shard on floating platforms more than 130km from Shetland.
  • Enough liquid hydrogen will be produced to power 40 percent of the total mileage of local UK buses.
  • Enough synthetic fuel to make 750 round trips from the UK to New York.

A completion date of 2030 for this project is mentioned.

This article on The Engineer is entitled Northern Horizons Plans Clean Energy Exports For Scotland.

The article is dated the 4th of November 2021 and starts with this sub-heading and an informative video.

Aker Horizons’ new initiative, Northern Horizons, aims to make Scotland a clean energy exporter by utilising offshore wind resources in the North Sea.

There is an explanatory graphic of the project which shows the following.

  • Floating wind turbines.
  • A floating DC substation.
  • A floating hydrogen electrolyser.
  • An onshore net-zero refinery to produce synthetic aviation fuel and diesel.
  • A hydrogen pipeline to mainland Scotland.
  • Zero-carbon energy for Shetland.

It is all very comprehensive.

These are some other thoughts.

Project Orion

Project Orion how has its own web site and the project that seems to have similar objectives to Northern Horizons.

The title on the home page is Building A World-Leading Clean Energy Island.

There is this statement on the home page.

Orion is a bold, ambitious project that aims to transform Shetland into the home of secure and affordable clean energy.

We will fuel a cleaner future and protect the environment by harnessing the islands’ renewables potential, using onshore and offshore wind, tidal and wave energy.

The graphic has similar features to that Northern Horizons in the article on The Engineer, with the addition of providing an oxygen feed to Skyrora for rocket fuel.

German Finance

I feel very much, that the Germans could be providing finance for developments around Shetland, as the area could be a major source of hydrogen to replace Vlad the Mad’s tainted gas.

In Do BP And The Germans Have A Cunning Plan For European Energy Domination?, I described how BP is working with German utilities and finance to give Germany the hydrogen it needs.

NorthConnect

The NorthConnect (also known as Scotland–Norway interconnector) is a proposed 650 km (400-mile) 1,400 MW HVDC interconnector over the floor of the North Sea.

  • It will run between Peterhead in North-East Scotland and Norway.

This project appears to be stalled, but with the harvesting of more renewable energy on Shetland, I can see this link being progressed, so that surplus energy can be stored in Norway’s pumped storage hydro.

Icelink

Icelink is a proposed electricity interconnector between Iceland and Great Britain.

  • It would be the longest undersea interconnector in the world, with a length of 620 to 750 miles.
  • It would be a 800–1,200 MW high-voltage direct current (HVDC) link.
  • National Grid is part of the consortium planning to build the link.
  • Iceland has a surplus of renewable energy and the UK, is the only place close enough for a connection.

I believe that if Icelink were to be built in conjunction with energy developments on and around Shetland, a more powerful and efficient interconnector could emerge.

Conclusion

This ambitious project will transform the Shetlands and the energy industry in wider Scotland.

This project is to the North-East of Shetland, but the islands are surrounded by sea, so how many other Northern Horizons can be built in a ring around the islands?

March 22, 2022 Posted by | Energy | , , , , , , , , , , , , , , , , , , | 4 Comments

Future Offshore Wind Power Capacity In The UK

I am building this table, so that I can get a feel for the electricity needs of the UK.

According to Wikipedia, on February 2020, there were thirty six offshore wind farms consisting of 2180 turbines with a combined capacity of 8113 megawatts or 8.113 gigawatts.

Currently, these offshore wind farms are under construction, proposed or are in an exploratory phase.

  • Triton Knoll – 857 MW – 2021 – Under Construction
  • Hornsea Two – 1386 MW – 2022 – Under Construction
  • Moray East – 960 MW – 2022 – Under Construction
  • Neart Na Gaoithe – 450 MW – 2023 – Under Construction
  • Seagreen Phase 1 – 1075 MW – 2023 – Under Construction
  • Dogger Bank A – 1200 MW – 2023/24 – Proposed
  • Dogger Bank B – 1200 MW – 2024/25 – Proposed
  • Dogger Bank C – 1200 MW – 2024/25 – Proposed
  • Moray West – 1200 MW – 2024/25  – Exploratory
  • Hornsea Three – 2400 MW – 2025 – Proposed
  • East Anglia One North 800 MW – 2026 – Exploratory
  • East Anglia Two – 900 MW – 2026 – Exploratory
  • East Anglia Three – 1400 MW – 2026 – Exploratory
  • Sofia Offshore Wind Farm Phase 1 – 1400 MW – 2023/2026 – Under Construction
  • Hornsea Four – 1000 MW (?) – 2027 – Exploratory
  • Rampion Two Extension – 1200 MW – Exploratory
  • Norfolk Vanguard – 1800 MW – Exploratory
  • Norfolk Boreas – 1800 MW – Exploratory

Note.

  1. The date is the possible final commissioning date.
  2. I have no commissioning dates for the last three wind farms.
  3. Wikipedia says that the Hornsea Four capacity is unknown by Ørsted due to the ever increasing size of available wind turbines for the project.

I can total up these wind farms by commissioning date.

  • 2021 – 857 MW
  • 2022 – 2346 MW
  • 2023 – 1525 MW
  • 2024 – 1200 MW
  • 2025 – 6000 MW
  • 2026 – 4500 MW
  • Others – 5800 MW

I can draw these conclusions.

  • Total wind farm capacity commissioned each year is increasing.
  • It looks like there will be a capacity to install up to 5000 or 6000 MW every year from about 2025.
  • If we add my figures for 2021-2026 to the 8113 MW currently installed we get 24541 MW.
  • Adding in 6000 MW for each of the four years from 2027-2030 gives a total of 48541 MW or 48.5 GW.

As I write this on a Sunday afternoon, wind power (onshore and offshore) is supplying 13 GW or forty-four percent of our electricity needs.

I have further thoughts.

Parallels With North Sea Oil And Gas

I was very much involved in the development of North Sea oil and gas, as my software was used on a large number of the projects. I had many discussions with those managing these projects and what was crucial in shortening project times was the increasing availability of bigger rigs, platforms and equipment.

Big certainly was better.

I believe that as we get more experienced, we’ll see bigger and better equipment speeding the building of offshore wind farms.

Reuse of Redundant North Sea Oil And Gas Platforms

Don’t underestimate the ability of engineers to repurpose redundant oil and gas platforms for use with windfarms.

Electrolysers on the platforms can convert the electricity into hydrogen and use redundant gas pipes to bring it ashore.

Some processes like steelmaking could use a lot of hydrogen.

Platforms can be used as sub-stations to collect electricity from windfarms and distribute it to the various countries around the North Sea.

Hydrogen

Some processes like steelmaking could use a lot of hydrogen. And I don’t think steelmakers would be happy, if the supply was intermittent.

So why not produce it with giant electrolysers on redundant oil and gas platforms and store it in redundant gas fields under the sea?

A large store of hydrogen under the sea could have the following uses.

  • Steelmaking.
  • Feedstock for chemical manufacture.
  • Transport
  • Power generation in a gas-fired power station, that can run on hydrogen.

It would just need a large enough hydrogen store.

Energy Storage

This large amount of wind power will need a large amount of energy storage to cover for when the wind doesn’t blow.

Some of this storage may even be provided by using hydrogen, as I indicated previously.

But ideas for energy storage are coming thick and fast.

The North Sea Link To Norway

The North Sea Link is much more important than an interconnector between Blyth in Northumberland and Norway.

  • At the Norwegian end the link is connected to a vast pumped storage energy system in the mountains of Norway.
  • This pumped storage system is filled in two ways; Norwegian rain and snow and UK wind power through the interconnector.
  • In times of need, we can draw electricity through the interconnector from Norway.
  • It has a capacity of 1.4 GW.
  • It was delivered on time for a cost of around €2 billion.

It can almost be thought of as an international bank of electricity and is probably one of the most significant pieces of European infrastructure built in recent years.

There are also plans to build NorthConnect, that would connect Peterhead in Scotland to Norway.

Conclusion

It looks like we’ll be able to reap the wind. And possibly 50 GW of it!

 

January 2, 2022 Posted by | Energy, Energy Storage, Hydrogen | , , , , , , | 2 Comments