National Grid To Accelerate Up To 20GW Of Grid Connections Across Its Transmission And Distribution Networks

The title of this post, is the same as that of this press release from National Grid.

These four bullet points, act as sub-headings.

  • Connection dates of 10GW of battery projects accelerated at transmission level, and 10GW of capacity unlocked at distribution level, both part of the Electricity System Operator (ESO)’s connections five-point plan.
  • Battery energy storage projects connecting to the transmission network to be offered new connection dates averaging four years earlier than their current agreement.
  • The accelerated 20GW equates to the capacity of six Hinkley Point C nuclear power stations.
  • Work is part of ongoing collaborative industry efforts, together with Ofgem and government, to speed up and reform connections.

This is the opening paragraph.

National Grid is accelerating the connection of up to 20GW of clean energy projects to its electricity transmission and distribution networks in England and Wales as part of ongoing collaborative work across industry.

As I write this, the UK is generating 38.5 GW of electricity, so another 20 GW will be a large increase in capacity.

I shall look at what National Grid are proposing in sections.

10 GW Of Battery Power

These two paragraphs, outline the plan for 10 GW of battery power.

On its transmission network, 19 battery energy storage projects worth around 10GW will be offered dates to plug in averaging four years earlier than their current agreement, based on a new approach which removes the need for non-essential engineering works prior to connecting storage.

The new policy is part of National Grid’s connections reform initiative targeting transmission capacity, spearheaded by the ESO – which owns the contractual relationship with connecting projects – and actioned jointly with National Grid Electricity Transmission (ET), the part of the business which designs and builds the transmission infrastructure needed in England and Wales to plug projects in.

It looks to me that someone has been doing some serious mathematical modelling of the UK’s electricity network.

Fifty years ago, I provided the differential equation solving software, that enabled the Water Resources Board to plan, where reservoirs and pipelines were to be built. I have no idea how successful it was, but we don’t seem to have any serious water supply problems, except when there is equipment failures or serious drought.

But modelling water and electrical networks is mathematically similar, with rainfall, pipelines and reservoirs in the water network and power generation, transmission lines and batteries and pumped storage hydroelectricity in the electricity network.

I’d be interesting to know what software was used to solve the mathematical model.

I certainly agree with the solution.

Two of our modern sources of renewable energy; solar and wind are not very predictable, but cost a lot of capital investment to build.

So it is very wrong not to do something positive with any excess electricity generated. And what better place to put it than in a battery, so it can be retrieved later.

The earlier, the batteries come on stream, the earlier, the batteries can save all the excess electricity.

So moving the plug in dates for battery storage four years earlier is a very positive thing to do.

A simple calculation shows that for 10 GW, we would need nineteen batteries of about 526 MW.

Ideally, like power stations, they would be spread around the country.

Could Pumped-Storage Hydroelectricity Be Used?

The largest battery in the UK is the Dinorwig pumped-storage hydroelectric power station, which is commonly known as Electric Mountain or Mynydd Gwefru if you’re Welsh.

  • It opened in 1984, after a ten years of construction.
  • It has a power output of 1.8 GW.
  • The energy storage capacity of the station is around 9.1 GWh.

Roughly, every gigawatt of output is backed up by 5 GWh of storage.

If the proposed nineteen new batteries have the same power to storage ratio as Electric Mountain, then each battery will have a storage capacity of 2.63 GWh

SSE Renewables are planning two large pumped-storage hydroelectric power stations in Scotland.

A quick calculation, says we’d need seven pumped-storage hydroelectric power stations, which need a lot of space and a handy mountain.

I don’t think pumped-storage hydroelectric would be feasible.

Could Lithium-Ion Batteries Be Used?

My mathematical jottings have shown we need nineteen batteries with this specification.

  • An output of about 526 MW.
  • A storage capacity of around 2.63 GWh

This Wikipedia entry gives a list of the world’s largest battery power stations.

The current largest is Vistra Moss Landing battery in California, which has this specification.

  • An output of 750 MW.
  • A storage capacity of 3 GWh

Reading the Wikipedia entry for Vistra Moss Landing, it appears to have taken five years to construct.

I believe that nineteen lithium-ion batteries could handle National Grid’s need and they could be built in a reasonable time.

Could Any Other Batteries Be Used?

Rounding the battery size, I feel it would be better have twenty batteries with this specification.

  • An output of 500 MW.
  • A storage capacity of 2.5 GWh

Are there any companies that could produce a battery of that size?

Form Energy

Form Energy are well-backed with an MIT heritage, but their largest proposed battery is only 10 MW/1 GWh.

They could be a possibility, but I feel it’s only a small chance.

Highview Power

Highview Power say this about their next projects on this page of their web site.

Highview Power’s next projects will be located in Scotland and the North East and each will be 200MW/2.5GWh capacity. These will be located on the national transmission network where the wind is being generated and therefore will enable these regions to unleash their untapped renewable energy potential and store excess wind power at scale.

Note.

  1. This is more like the size.
  2. Work is now underway at Carrington – a 50MW / 300MWh plant at Trafford Energy Park near Manchester.
  3. Highview’s technology uses liquid air to store energy and well-proven turbo-machinery.
  4. Highview have a co-operation agreement with Ørsted

They are a definite possibility.

10 GW Of Extra Unlocked Capacity

These two paragraphs, outline the plan for 10 GW of extra unlocked capacity.

On its distribution network in the Midlands, South West of England and South Wales, the additional 10GW of unlocked capacity announced recently is set to accelerate the connection of scores of low carbon technology projects, bringing forward some ‘shovel ready’ schemes by up to five years.

National Grid has already been in contact with more than 200 projects interested in fast tracking their distribution connection dates in the first wave of the capacity release, with 16 expressing an interest in connecting in the next 12 months and another 180 looking to connect within two to five years.

This page from National Grid ESO, lists the actions that were taken to release the extra grid capacity.

Conclusion

This looks to be a very good plan from National Grid.

 

 

November 6, 2023 Posted by | Energy, Energy Storage | , , , , , , , , , , | 3 Comments

Carlton Power Secures Planning Consent For World’s Largest Battery Energy Storage Scheme

The title of this post, is the same as that of this news story from Carlton Power.

This is the sub-heading.

£750m 1GW Battery Project To Be Built At Carlton Power’s Trafford Low Carbon Energy Park In Greater Manchester

These three paragraphs outline the project.

Carlton Power, the UK independent energy infrastructure development company, has secured planning permission for the world’s largest battery energy storage scheme (BESS), a 1GW (1040MW / 2080MWh) project located at the Trafford Low Carbon Energy Park in Greater Manchester. The £750m BESS scheme will strengthen the security and resilience of the energy system in the North West of England, and support the energy transition and the growth of renewable power generation in the region.

Planning permission for the BESS was granted by Trafford Council, the local planning authority.

Subject to a final investment decision, construction of the battery storage scheme is expected to begin in the first quarter of next year (2024) with it entering commercial operation in the final quarter of 2025. Carlton Power is in advanced talks with companies to finance, build and operate the Trafford BESS.

I have a few thoughts.

It’s A Monster

This Wikipedia entry, lists the World’s Largest Grid Batteries.

  • The current largest is Vistra Moss Landing battery in the United States, which has a capacity of 1600 MWh and an output of 400 MW.
  • The Trafford BESS will have a capacity of 2080 MWh and an output of 1040 MW.

By both measures the Trafford BESS is larger.

Where Will It Get The Energy?

Consider.

I can see enough renewable energy being generated to replace Carrington gas-fired power station.

Who Will Finance, Build And Operate The Trafford BESS?

There are two major Energy Storage Funds in the UK.

Note.

  1. There are other smaller funds.
  2. The figures given are cumulative outputs for the portfolios.
  3. Sourcing the large number of batteries might be a problem.
  4. As the maths of these batteries are now well-known, I would expect that finance shouldn’t be too much of a problem.
  5. Local companies like Liverpool Victoria or Peel Holdings could even take a position.

A large American contractor backed by US money could swallow the whole project.

That happened with North Sea oil and gas in the last century.

Is Highview Power’s CRYOBattery Still Planned?

Carlton Power’s news story says this about Highview Power’s plans.

In addition to Carlton Power’s two projects, Highview Power Storage Inc. is planning to build and operate the world’s first commercial liquid air storage system – a £250m 250MWh long duration, cryogenic energy storage system – on the Trafford Low Carbon Energy Park, which was until 1991 the site of the Carrington coal-fired power station. The Low Carbon Energy Park is located close to Manchester Ship Canal and the £750m Carrington flexible gas-fired power station which entered operation in 2016.

It seems that the CRYOBattery is still planned.

Conclusion

Manchester is getting a powerful zero-carbon hub.

July 24, 2023 Posted by | Energy, Energy Storage | , , , , , , , , , , | 2 Comments

Japanese Companies To Invest GBP 14.2 Billion In UK’s Offshore Wind, Green Hydrogen

The title of this post, is the same as that of this article on offshoreWIND.biz.

This is the sub-heading.

Japanese giants Marubeni Corporation, Sumitomo Corporation, and Sumitomo Electric Industries have committed to investing a total of GBP 14.2 billion (approximately EUR 16.3 billion) in offshore wind and green hydrogen projects, and the offshore wind supply chain in the UK

These two paragraphs add a bit of context and flesh to the deal.

Ahead of the UK Prime Minister’s business reception in Tokyo on 18 May, the UK government announced that leading Japanese businesses have committed to invest GBP 17.7 billion (approx. EUR 20.3 billion) in businesses and projects across the UK.

Of this, GBP 14.2 billion has been committed by Marubeni, Sumitomo and Sumitomo Electric for projects in offshore wind, green hydrogen and offshore wind supply chain.

SSE’s Berwick Bank Wind Farm will have a capacity of 4.1 GW and is budgeted to cost just short of £18 billion. Doing a quick calculation, indicates that £14.2 billion would only finance £3.23 GW of offshore wind.

But the Japanese say they will invest in offshore wind, green hydrogen and offshore wind supply chain. Investing in the offshore wind supply chain, would surely attract more money as the developers placed orders for foundations, floaters, electrical gubbins and support vessels.

Note.

  1. In Japanese Giant Sumitomo Heavy Invests In Liquid-Air Energy Storage Pioneer, I wrote about Sumitomo’s investment in English energy storage. company; Highview Power.
  2. Electrolyser company; iTM Power has also sold a 1.4 MW electrolyser to Sumitomo and signed an agreement over American sales with another Japanese company.

I can see other similar co-operative deals being developed. Possible areas could be cables, transformers and support vessels.

May 19, 2023 Posted by | Energy, Hydrogen | , , , , , , , | 2 Comments

Gresham House Energy Storage Sets GBP80 Million Fundraise

Gresham House Energy Storage Fund must be doing something right, as similar headlines are used in half-a-dozen places on the Internet and they regularly seem to be raising more money.

But then, as a Graduate Control Engineer and a previous owner of half a finance company, I’ve always thought raising money to build batteries was a good idea.

My only niggle with Gresham House, is that I would have thought by now, they would have put some money into building one of the excellent new technology batteries that are coming through.

The storage fund or some of its employees, may of course have contributed to some of the crowdfunding for these new technologies, all of which I feel have a good chance of being a success.

Note.

  1. Energy Dome is Italian and all the others are at least fifty percent British.
  2. Most of the British batteries have had backing from the UK government.
  3. All these batteries are environmentally-friendly.
  4. None of these batteries use large quantities of rare and expensive materials.
  5. Energy Dome even uses carbon dioxide as the energy storage medium.

In addition, in Scotland, there is traditional pumped storage hydro-electricity.

Project Iliad

This article on renews.biz has a slightly different headline of Gresham House To Raise £80m For US Battery Buildout.

This is the first two paragraphs.

Gresham House Energy Storage Fund is seeking to raise £80m through a share placing.

The new equity raised will primarily be used to finance 160MW of solar with co-located four-hour battery projects in California, US, known as Project Iliad.

The article then gives a lot of financial details of Project Iliad and Gresham House.

Will Gresham House be backing co-located solar/battery projects in the UK?

  • In Cleve Hill Solar Park, I write about a co-located solar/battery project in Kent.
  • This press release from National Grid is entitled UK’s First Transmission-Connected Solar Farm Goes Live, which also describes a co-located solar/battery project, being built near Bristol.

These two projects are certainly serious and could be pathfinders for a whole host of co-located solar/battery projects.

WillGresham House back some of this new generation?

 

May 18, 2023 Posted by | Energy, Energy Storage, Finance & Investment | , , , , , , , , , , , | 1 Comment

Boralex Commissions BESS At Wind Farm In France In EU-Supported Demonstration Project

The title of this post, is the same as that of this article on Energy Storage News.

These two paragraphs outline the project.

Canada-based renewable energy firm Boralex has turned on a 3.3MWh battery storage unit attached to a wind farm in France.

The battery storage project has been installed at the site of the Plouguin wind farm, an 8MW generating facility in the Finistere department of Brittany, northwest France.

Note.

  1. The project was co-financed by the European Union through its European Regional Development Fund (ERDF).
  2. The project was launched to demonstrate the technical feasibility of a hybrid wind-plus-storage project.
  3. Boralex added in its announcement that the project will contribute to the stability of the French electricity grid.

There will be a lot of projects like this in the future.

This paragraph makes an interesting point about using batteries with solar and wind power.

Wind farms are less frequently hybridised with energy storage than solar PV because of the larger minimum project size and less predictable variability, with sharper peaks meaning heavier battery cycling and potentially faster degradation.

My control engineering knowledge and experience says that larger power sources and those that are highly variable will need batteries with more capacity for the same stability and quality of power output.

This sounds to me like a very good reason for developing larger and more affordable batteries, like those of Cheesecake Energy, Energy Dome, Gravitricity and Highview Power.

It also probably means that to stabilise several gigawatts of wind power, you need a very large amount of storage, that can only be provided by pumped storage hydroelectricity.

Conclusion

A very large amount energy storage is going to be needed.

Projects like these are essential to make sure we use them to their full possibilities.

May 2, 2023 Posted by | Energy, Energy Storage | , , , , , , , , , , , | Leave a comment

Highview Power And Ørsted Collaborate To Unlock Greater Value From The Next Generation Of Wind Farms

The title of this post, is the same as that of this press release from Ørsted.

This is the sub-heading.

Highview Power and Ørsted have signed a Memorandum of Understanding aiming to prove the feasibility and economic value of co-locating long duration energy storage with offshore wind.

This first paragraph indicates how the two companies will work together.

The two companies will carry out detailed technical analysis and an economic assessment during 2023 that will investigate how combining Ørsted’s wind technology with Highview Power’s liquid air energy storage can deliver a stronger investment case for future offshore wind projects by reducing wind curtailment, increasing productivity, and helping the move to a more flexible, resilient zero carbon grid.

This all good stuff and as a Control Engineer, I know, there is a very good chance, it will bring forward worthwhile benefits.

April 6, 2023 Posted by | Energy, Energy Storage | , , , , | 1 Comment

Diversifying A US$200 billion Market: The Alternatives To Li-ion Batteries For Grid-Scale Energy Storage

The title of this post, is the same as that of this article on Energy Storage News.

This is the introductory paragraph.

The global need for grid-scale energy storage will rise rapidly in the coming years as the transition away from fossil fuels accelerates. Energy storage can help meet the need for reliability and resilience on the grid, but lithium-ion is not the only option, writes Oliver Warren of climate and ESG-focused investment bank and advisory group DAI Magister.

Oliver starts by saying we need to ramp up capacity.

According to the International Energy Agency (IEA), to decarbonise electricity globally the world’s energy storage capacity must increase by a factor of 40x+ by 2030, reaching a total of 700 GW, or around 25% of global electricity usage (23,000TWh per annum). For comparison, this would be like swelling the size of the UK’s land to that of the USA.

Similar to how “nobody ever gets fired for buying IBM”, lithium-ion holds a similar place in grid scale electrical storage today.

And just as IBM did in the last decades of the last century, the builders of lithium-ion will fight back.

He then lists the problems of grid-scale lithium-ion batteries.

  • Shortage of cobalt.
  • Toxic and polluting extraction of some much needed metals and rare earths from unstable countries.
  • Lack of capacity to load follow.
  • Limited lifespan.

He does suggest vehicle-to-grid can provide 7TWh of storage by 2030, but it has similar problems to lithium-ion grid scale batteries.

Finally, he covers these what he considers several viable methods of energy storage in detail.

He introduces them with this paragraph.

No single killer application or technology exists to get the job done. Diversification is key with success dependent on the wide-scale adoption of multiple grid-scale energy storage solutions.

Note.

  1. All systems are environmentally-friendly and use readily-available materials like air, water, sea-water, steel and concrete for their systems.
  2. The most exotic materials used are probably in the control computers.
  3. Some systems use readily-available proven turbo-machinery.
  4. Most systems appear to be scalable.
  5. All systems would appear to have a working life measured in decades.
  6. I would expect that most well-educated teenagers could understand how these systems worked.

Only Augwind Energy and Lumenion are new to me.

He finally sums up the economics and the market potential.

Our ability to expand energy storage capacity is one of the most pressing issues that will determine whether this defining ‘transitional’ decade is a success. But we’ll need to invest wisely into the right technologies that get the greatest bang for the buck (in terms of GWh capacity and return on capital) given the limited lifespan of Li-Ion and the decarbonisation of the grid.

At a current capital cost of US$2,000 per kW quoted by the US National Renewable Energy Laboratory (NREL) for 6-hour Li-ion battery storage, the 700GW of capacity needed by 2030 equates to around a US$1.5 trillion market over the coming decade, making it worth nearly US$200 billion a year.

The Energy Storage News article is a comprehensive must read for anyone, who is considering purchasing or investing in energy storage.

I have some further thoughts.

From My Experience Would I Add Any Other Systems?

I would add the following.

  • Form Energy, because its iron-air battery is well-backed financially.
  • Gravitricity, because it can use disused mine shafts to store energy and the world has lots of those.
  • STORE Consortium, because its 3D-printed concrete hemispheres, that store energy using pressurised sea-water can be placed within a wind farm.

I also suspect that someone will come up with an energy storage system based on tidal range.

Finance

When we started Metier Management Systems, finance to breakout from the first initial sales was a problem. We solved the problem with good financial planning and an innovative bank manager who believed us all the way.

David, was a rogue, but he was a rogue on the side of the angels. Long after Metier, he even came to my fiftieth birthday party.

David would have found a way to fund any of these systems, as they tick all the boxes of demonstrated, environmentally-friendly, safe and understandable. They are also likely to be bought by companies, governments and organisations with a high net value, a very respectable reputation and/or large amounts of money.

I also think, that just as we did with the original Artemis project management system, some of these systems can be leased to the operators.

Second-Use Of Systems

Several of these systems could be moved on to a new location, if say they were supporting an industry that failed.

That would surely help the financing of systems.

February 23, 2023 Posted by | Energy, Energy Storage, Finance & Investment | , , , , , , , , , , , , , | 1 Comment

Wind Power For 1.2m Homes Is Wasted Because Of Lack Of Storage

The title of this post, is the same as that of this article on the Daily Telegraph.

These two paragraphs outline what happened.

Enough wind power to supply 1.2m homes a day was wasted over winter because there is no capacity to store extra energy generated on gusty days, according to new research.

National Grid’s electricity system operator asked wind turbines which were expected to generate about 1.35 terawatt-hours of electricity between October and January to switch off instead because they were not needed to meet demand at the time, according to the consultancy Stonehaven.

The problem has been flagged up by Rupert Pearce of Highview Power, who in my view could have a solution with their CRYOBatteries.

Pearce is quoted as saying this.

Renewable energy storage is essential to powering a cleaner, cheaper, always-on Britain.

By capturing and storing excess renewable energy, which is now the UK’s cheapest, most secure and most abundant form of energy, we can power Britain’s homes and businesses with renewable green energy, taking millions of tonnes of carbon out of the atmosphere and ending a culture of reliance on expensive foreign imports.

He’s too bloody right! And my experience of mathematical modelling large vessels at ICI in the 1970s, says that Highview Power have one of the sensible solutions to large scale energy storage.

February 9, 2023 Posted by | Energy, Energy Storage | , , , , , | 2 Comments

First Offtake Deal Signed For 500MW/4,000MWh Advanced Compressed Air Energy Storage Project In California

The title of this post, is the same as that of this article on Energy Storage News.

These three paragraphs explain the deal.

Advanced compressed air energy storage (A-CAES) company Hydrostor has signed a power purchase agreement (PPA) for one of its flagship large-scale projects in California.

Central Coast Community Energy, one of California’s several dozen Community Choice Aggregator (CCA) non-profit energy suppliers, has signed a 200MW/1,600MWh energy storage PPA with a 25-year term with Toronto-headquartered Hydrostor for its Willow Rock Energy Storage Center.

That’s just under half of the output and capacity of the planned 8-hour, long-duration energy storage (LDES) facility, which is designed to be 500MW/4,000MWh. This is its first offtake deal, but the company is in discussion for others to take the rest of the plant’s available resource.

The article says that Hydrostor aim to have the plant online by 2028.

This segment describes their current projects.

It is currently working on large-scale projects with around 9GWh storage capacity in total across two sites in California as well as another in Australia.

Together with Willow Rock in Kern County, Hydrostor is developing the 400MW/3,200MWh Pechos Energy Storage Center in San Luis Obispo County, California, and the 200MW/1,500MWh Silver City Energy Storage Center in Broken Hill, New South Wales, Australia.

On its UK Projects page, Highview talks about a 200MW/2.5GWh facility in Yorkshire, which puts the two companies in similar markets, with Hydrostor appearing to have slightly larger systems under development.

Conclusion

It will be interesting to see how this technology progresses and which company does best in what is a very large energy storage market.

January 14, 2023 Posted by | Energy, Energy Storage | , , , , , | 1 Comment

How Liquid Air Could Solve The UK’s Energy Conundrum

The title of this post, is the same as that of this article on The Telegraph.

The article is mainly an article that described the technology and it discloses a few facts.

  • The Carrington plant should be delivered in 2024.
  • Carrington will be a 30 MW/30 MWh system.
  • Efficiency is around 50 %, but there are possibilities to raise it to 70 %.
  • Australia is mentioned as a market.
  • It is likely to be paired with supercapacitors or a flywheel to have a quick start.
  • It seems to me, that turning an idea into a practical system is taking a lot of work and money, and a bit of a rethink.

But hopefully, the system will eventually be developed, as it does promise to be an energy storage system, that doesn’t make high demands on the environment in terms of expensive metals and rare earths.

January 9, 2023 Posted by | Energy, Energy Storage | , , | Leave a comment