The Anonymous Widower

Battery-Electric Class 331 Trains On The Radar

In the June 2021 Edition of Modern Railways, there is an article which is entitled Northern Looks To The Future.

This is a paragraph.

Also on the radar is the creation of hybrid Class 331 EMUs fitted with batteries. A proposal has been developed by CAF and owner Eversholt Rail to augment three-car ‘331s’ with a fourth vehicle containing batteries, which would see batteries also fitted to the existing centre car. The Manchester to Windermere route has been touted as a possible location for deployment, with trains switching to battery power on the non-electrified branch from Oxenholme, although the line’s user group still favours electrification of the branch.

I have a few thoughts.

Electrification at Oxenholme

In Surprising Electrification At Oxenholme, I detailed the electrification at Oxenholme station in May 2018.

Consider.

  • Platform 3 used by the Windermere trains is fully electrified.
  • The crossover South of the station used by trains going between the Windermere Branch Line and the West Coast Main Line is fully electrified.
  • The electrification continues for perhaps a hundred metres along the Windermere branch.

I am fairly certain, that this electrification has been designed so that a bi-mode or battery-electric train can perform a reliable power changeover in Platform 3 at Oxenholme station.

What Will Be The Range Of A Four-Car Battery-Electric Class 331 Train?

This is very much a case of how long is a piece of string.

At least we know from the extract above that the train is designed to do a return trip between Oxenholme and Windermere stations, which is a distance of 20.4 miles and a six minute turnround.

We should also note that Hitachi are claiming a range of 56 miles for their Regional Battery Train, which is described in this Hitachi infographic.

As the Class 331 with batteries will compete with the Hitachi Reional Battery Train, I would suspect that the range on easy level ground would be at least fifty miles at a speed of over 80 mph, if not 100 mph.

A Selection Of Possible Routes

These are a selection of other Northern routes where the battery-electric Class 331 trains might be used.

Manchester Airport and Barrow-in-Furness

Consider.

  • This is a sibling route to the Manchester Airport and Windermere route and currently has eleven services to Windermere’s four.
  • This is a 103.7 mile route.
  • All but 28.1 miles is electrified.

Battery-electric Class 331 trains with a charge at Barrow-in-Furness should be able to handle this route.

Lancaster and Barrow-in-Furness

Consider.

  • This is a 34.8 mile route
  • All but 28.1 miles is electrified.
  • Lancaster is a fully electrified station.

Battery-electric Class 331 trains with a charge at Barrow-in-Furness should be able to handle this route.

Carlisle and Barrow-in-Furness

This is the 85.7 mile route of the Cumbrian Coast Line of which none is electrified.

Consider.

  • Carnforth is a fully-electrified station.
  • Barrow-in-Furness station could be electrified.
  • It is a fairly level route along the coast.
  • I suspect that electricity supplies are available at Barrow-in-Furness, Sellafield, Whitehaven and Workington to power electrification.
  • Carlisle is a fully-electrified station.
  • Barrow-in-Furness and Sellafield are only 35 miles apart.
  • CAF have produced trams for Birmingham and Seville, that work with discontinuous electrification.
  • There are parts of the route, where there would be those, who would object to the erection of electrification gantries.

I feel it would be possible to electrify the Cumbrian Coast Line using battery-electric Class 331 trains, with a range of at least fifty miles and some short sections of new electrification.

Surely, a battery-electric train along the Cumbrian Coast by the Lake District would be the ideal train for the area

Lancaster and Morecambe

Consider.

  • This is a 4 mile route.
  • None is electrified.
  • Heysham is another four miles past Morecambe.
  • Lancaster is a fully-electrified station.

This route might have been built for battery-electric trains.

This route might be possible with no extra infrastructure.

York and Blackpool North

Consider.

  • This is a 105.5 mile route.
  • In a few years about 62 miles will be without electrification.
  • It goes through the picturesque Calder Valley.

As with the Cumbrian Coast Line, I believe that this service could be run using battery-electric Class 331 trains, with a range of at least fifty miles and some short sections of new electrification.

Preston and Colne

Consider.

  • This is a 29 mile route.
  • None is electrified.
  • It is steeply uphill to Colne.

Battery-electric Class 331 trains with a charge at Colne should be able to handle this route.

Alternatively, they could use Newton’s friend to return down the hill.

This route might be possible with no extra infrastructure.

As with York and Blackpool North, this route would benefit with electrification between Preston and Blackburn.

Preston and Blackpool South

Consider.

  • This is a 20 mile route.
  • 7.7 miles is electrified.

Battery-electric Class 331 trains  should be able to handle this route.

This route might be possible with no extra infrastructure.

In an ideal world, Preston and Blackburn would be electrified and trains would run between Colne and Blackpool South, as they used to do.

Liverpool Lime Street and Manchester Airport

Consider.

  • This is a 45.5 mile route,
  • 26.5 miles is not electrified.
  • It is fully electrified at both ends.

Battery-electric Class 331 trains  should be able to handle this route.

This route might be possible with no extra infrastructure.

Liverpool Lime Street and Manchester Oxford Road

Consider.

  • This is a 34.2 mile route.
  • 26.5 miles is not electrified.
  • It is fully electrified at both ends.

Battery-electric Class 331 trains  should be able to handle this route.

This route might be possible with no extra infrastructure.

Southport and Alderley Edge

  • This is a 52 mile route,
  • 27 miles is not electrified.
  • It is fully electrified at the Southern end.
  • There is third rail electrification at Southport.

Battery-electric Class 331 trains with a charge at Southport should be able to handle this route.

Could some Class 331 be fitted with third-rail equipment to charge on Merseyrail’s third-rail electrification?

Manchester Piccadilly and Chester

Consider.

  • This is a 45 mile route.
  • 38 miles is not electrified.
  • It is fully electrified at Manchester end.
  • There is third rail electrification at Chester.

Battery-electric Class 331 trains with a charge at Chester should be able to handle this route.

Could some Class 331 be fitted with third-rail equipment to charge on Merseyrail’s third-rail electrification?

Manchester Piccadilly and Buxton

Consider.

  • This is a 25.5 mile route.
  • 17.8 miles is not electrified.
  • It is steeply uphill to Buxton.

Battery-electric Class 331 trains with a charge at Buxton should be able to handle this route.

Alternatively, they could use Newton’s friend to return down the hill.

This route might be possible with no extra infrastructure.

Manchester Piccadilly and Rose Hill Marple

Consider.

  • This is a 13.3 mile route.
  • 8.3 miles is not electrified.
  • It is fully electrified at Manchester end.

Battery-electric Class 331 trains should be able to handle this route.

This route might be possible with no extra infrastructure.

Manchester Piccadilly and New Mills Central

Consider.

  • This is a 13 mile route.
  • Only 2 miles is electrified.
  • It is fully electrified at Manchester end.

Battery-electric Class 331 trains should be able to handle this route.

This route might be possible with no extra infrastructure.

Manchester Piccadilly and Sheffield

Consider.

  • This is a 42 mile route.
  • Only 2 miles is electrified.
  • It is fully electrified at Manchester end.
  • It is a scenic route.

Battery-electric Class 331 trains with a fifty mile range and a charge at Sheffield should be able to handle this route.

Southport and Stalybridge

  • This is a 45 mile route.
  • 27 miles is not electrified.
  • It will be fully electrified at the Southern end, when electrification between Manchester Victoria and Stalybridge is completed.
  • There is third rail electrification at Southport.

Battery-electric Class 331 trains with a charge at Southport should be able to handle this route.

Could some Class 331 be fitted with third-rail equipment to charge on Merseyrail’s third-rail electrification?

Manchester Victoria And Kirkby

  • The Kirkby end of this route will change to the new Headbolt Lane station in a couple of years.
  • This is a 30 mile route.
  • 28 miles is not electrified.
  • It is fully electrified at the Southern end.
  • There is third rail electrification at Kirkby or Headbolt Lane.

Battery-electric Class 331 trains with a charge at Kirkby or Headbolt Lane should be able to handle this route.

Could some Class 331 be fitted with third-rail equipment to charge on Merseyrail’s third-rail electrification?

I would hope that the new Headbolt Lane station is being designed with battery-electric trains from Manchester in mind!

Rochdale And Clitheroe

Consider.

  • This is a 44.7 mile route.
  • There is 10.7 miles of electrification between Bolton and Manchester Victoria.
  • The Clitheroe end of the route has 23.7 miles of line without electrification.
  • The Rochdale end of the route has 10.4 miles of line without electrification.
  • It is steeply uphill to Clitheroe.

Battery-electric Class 331 trains should be able to handle the Rochdale end, but could struggle with the climb to Clitheroe.

But it appears that all services needing to climb the hills to Colne and Clitheroe now stop in Platform 2, which is different to Wikipedia, which says that services to Clitheroe stop in Platform 1.

  • With charging in platform 2 and a fifty-mile range battery-electric Class 331 trains could reach Clitheroe (9.8 miles), Colne (17 miles), and possibly Leeds (50 miles).
  • With charging in platform 4 and a fifty-mile range battery-electric Class 331 trains could reach Bolton (14 miles) and Preston (12 miles)
  • Would a fully-charged train leaving Blackburn be able to go via Todmorden and reach the electrification at Manchester Victoria, which is a distance of 39.4 miles?

Note.

If necessary a few well-planned extra miles of electrification would ensure reliable battery-electric services  in East Lancashire centred on Blackburn.

The closely-related Blackburn and Rochdale and Blackburn and Wigan Wallgate services would fit in well with an electrified Blackburn station, that could fully charge trains.

I certainly believe that electrifying Preston and Blackburn could give extra benefits.

  • Battery-electric trains between Blackpool and Liverpool in the West and Colne, Hebden Bridge, Bradford, Leeds and York in the East.
  • Direct electric services from Euston to Blackburn and Burnley.
  • Fast freight paths across the Pennines.

In addition, it would probably allow battery-electric trains to run to Leeds via a reinstated Skipton and Colne link.

Wigan And Leeds

Consider.

  • The route can terminate at either Wigan North Western or Wigan Wallgate station.
  • This is a 68.2 mile route using Wigan North Western.
  • Wigan North Western is a fully-electrified station.
  • The 16 miles between Wigan North Western and Salford Crescent stations is not electrified.
  • The 5 miles between Salford Crescent and Manchester Victoria stations is electrified.
  • The 37.2 miles between Manchester Victoria and Mirfield stations is not electrified.
  • The 12.2 miles between Mirfield and Leeds will be electrified in the next few years.
  • Leeds is a fully-electrified station.

Battery-electric Class 331 trains with a fifty mile range should be able to handle this route.

Chester And Leeds

Consider.

  • This is a 89.7 mile route.
  • There is third rail electrification at Chester.
  • The 18.1 miles between Chester and Warrington Bank Quay stations is not electrified.
  • The 21.8 miles between Warrington Bank Quay and Manchester Victoria stations is electrified.
  • The 40.3 miles between Manchester Victoria and Bradford Interchange stations is not electrified.
  • The 9.4 miles between Bradford Interchange and Leeds stations is not electrified.
  • Leeds is a fully-electrified station.
  • There seems to be generous turnround times at Chester and Leeds.

It looks to me that the trains are going to need a full battery charge at Bradford Interchange or perhaps Leeds and Bradford Interchange needs to be fully electrified.

I also feel that it would help if the electrification through Manchester Victoria were to be extended towards Rochdale.

But I don’t think it will be impossible for battery-electric Class 331 trains to work the route between Leeds and Chester with some new electrification and/or charging at Bradford Interchange.

Manchester Victoria And Leeds

Consider.

  • This is a shortened version of the Chester and Leeds route.
  • This is a 49.8 mile route.
  • Manchester Victoria is a fully-electrified station.
  • The 40.3 miles between Manchester Victoria and Bradford Interchange stations is not electrified.
  • The 9.4 miles between Bradford Interchange and Leeds stations is not electrified.
  • Leeds is a fully-electrified station.

My comments would be similar to the Chester and Leeds route.

Leeds And York Via Harrogate And Knaresborough

Consider.

  • This is a 38.8 mile route.
  • Leeds is a fully-electrified station.
  • The Harrogate Line is not electrified.
  • York is a fully-electrified station.

Battery-electric Class 331 trains with a fifty mile range should be able to handle this route.

There are two other services on the Harrogate Line.

  • Leeds and Harrogate – 18.3 miles
  • Leeds and Knaresborough – 22.1 miles

I have a feeling that a fleet of battery-electric trains could electrify all services on the Harrogate Line with no extra infrastructure.

Summing Up The Possible Routes

I have assumed that the proposed battery-electric Class 331 train has a range of around fifty miles, which is not unlike that for the Hitachi Regional Battery Train.

It would appear that many of Northern’s routes can be run by a train with this range including some that are around a hundred miles.

There are also routes like the Harrogate Line, which would accept a battery-electric Class 331 train tomorrow, if it were available.

Will A  Mix Of Four-Car Electric And Battery-Electric Trains Be Better Than A Mix Of Four-Car And Three-Car Electric Trains?

If the technology is right, I suspect that a four-car battery-electric Class 331 train will be able to substitute for one without batteries on a route that doesn’t need battery power.

This must surely have advantages when trains are in maintenance or otherwise unavailable, as nothing annoys passengers more than an overcrowded train.

Conclusion

The Modern Railways article also says this.

More widely, Northern has previously stated ambitions to acquire more trains, and work was underway last year to identify what this requirement might be.

From my simple analysis on some of their routes, I would look to acquire some four-car battery-electric Class 331 trains, once they have been oroven to work.

May 23, 2021 Posted by | Transport/Travel | , , , , , , , | 1 Comment

Latest On Hydrogen Trains In The Tees Valley

In the June 2021 Edition of Modern Railways, there is an article which is entitled Northern Looks To The Future.

This is a paragraph.

Northern has been working on proposals to introduce both hydrogen and battery conversions. For the former, the Tees Valley has been selected for the potential deployment of a whole system production pilot for a hydrogen fleet, with a dedicated depot, fuelling infrastructure and trains. A sub-fleet of Class 600 HMUs, converted by Alstom and Eversholt Rail from Class 321 EMUs and dubbed ‘Breeze’, is the preferred option for routes radiating from Middlesbrough to Nunthorpe, Bishop Auckland and Saltburn, creating a small self-contained network. If approved, these plans would fit with the Government’s aim to develop a hydrogen hub in the Tees Valley.

Could the Class 600 trains finally be on their way?

May 22, 2021 Posted by | Hydrogen | , , , | 2 Comments

Northern Could Introduce Class 769 Trains At The Time-Table Change

In the June 2021 Edition of Modern Railways, there is an article which is entitled Northern Looks To The Future.

This is a paragraph.

After a series of delays, the May timetable change was due to see introduce the first of its eight Class 769 bi-modes into service. Converted from Class 319 EMUs by Brush Traction for owner Porterbrook, the Class 769 ‘Flex’ units are capable of overhead electric and diesel operation and will be deployed on Southport to Alderley Edge/Stalybridge services.Northern After a series of delays, the May timetable change was due to see Northern introduce the first of its eight Class 769 bi-modes into service. Converted from Class 319 EMUs by Brush Traction for owner Porterbrook, the Class 769 ‘Flex’ units are capable of overhead electric and diesel operation and will be deployed on Southport to Alderley Edge/Stalybridge services.

I have just checked on Real Time Trains and the Class 769 trains appear to be running.

May 22, 2021 Posted by | Transport/Travel | , | 1 Comment

How Siemens Gamesa Could Give Coal Plants a Second Life

This article on Greentech Media is a must-read as it makes you think. This is the sub-title.

The ETES thermal battery can offer coal plants a new life as heat and power storage hubs. The first customer for a full-size version could be on-board as early as next year.

It talks about the philosophy of reusing coal-fired power station sites and some of their equipment like turbines.

It is an idea much more applicable to countries like the US and Germany rather than the UK, as they still have lots of operational coal-fired power stations and and we only have a few.

I first came across this idea, when Highview Power were talking about their 50/MW/400 MWh installation in Vermont, which was to be built on the site of a demolished coal-fired power station. The utility company and Highview were in that case just reusing the grid connection.

But then I’ve heard of other energy storage systems using old power station sites.

And not to forget that Highview Power’s installation at Carrington is close to a gas-fired power station.

 

May 22, 2021 Posted by | Energy, Energy Storage | , , , | Leave a comment

Bang Goes My Holiday!

There are various things I want to visit in Germany and I felt that the best thing to do would be go for a few days,

But the BBC are reporting these facts about travel to Germany.

  • From Sunday, people travelling from the UK will not be allowed to enter Germany
  • The decision is down to a rise in cases of the Indian variant in the UK
  • German citizens and residents, plus people with an exceptional reason, can still enter – but face a two-week quarantine

So bang goes my holiday!

I particularly wanted to go to Hamburg to take a few pictures of the Siemens Gamesa ETES trial installation in the city.

However I’ve been able to locate the installation on Google Maps.

Note.

  1. The wind-turbine towards the South-West corner of the map.
  2. Siemens Gamesa ETES trial installation is the prominent odd shaped building towards the South-East corner of the map, just below the shadow of the turbine.
  3. The installation seems to have lots of pipes connected to it.

This second map shows the installation from an angle.

This document on the Siemens Gamesa web site describes the installation.

  • The nominal power is 30 MW.
  • The capacity is 130 MWh.
  • 80 % of the technology is off the shelf.

The picture on the front says “Welcome To The New Stone Age”.

If anybody should find themselves in Hamburg with some time to waste, I’d be very grateful for a copyright-free image.

The installation appears to be just off the VollHöfner Weiden.

May 22, 2021 Posted by | Energy Storage, Health, Transport/Travel, World | , , | 3 Comments

JCB Finds Cheap Way To Run Digger Using Hydrogen

The title of this post, is the same as that of this article on The Times.

This is the first two paragraphs.

An operational hydrogen combustion engine developed in Derbyshire could speed up the shift towards zero-emissions transport.

JCB, the construction equipment manufacturer, said that the engine would be capable of powering heavy machinery and vehicles without producing any carbon dioxide.

As they have just modified one of their own production diesel engines to run on hydrogen, this sounds like a major breakthrough of the largest kind!

The caption on the picture says this.

JCB says that the technology could be applied in trucks, vans, trains, buses and even large cars.

What about small cars?

Or perhaps, that market will be left to Aquarius Engines, which I wrote about in New Hydrogen Engine Design Unveiled To Overcome Reliance On Fuel Cells.

You wait months for a major breakthrough in hydrogen propulsion to come along and then two ideas come along in one day.

The article gets better as you read it fully, which I suggest you do.

  • It appears, that development only started last July.
  • The engines are based on their current JCB diesel engines.
  • Emissions include water, no CO2 and practically zero levels of NOx.

The article says this about costs.

It is thought that the hydrogen engines will cost about £10,000 each; costs will be kept down by using the same production lines and many of the same components as diesel engines. By comparison a prototype hydrogen fuel cell system, which is being adapted for a 20-tonne excavator as part of another JCB trial, will cost about £100,000. Batteries needed to power such a machine would probably cost in the region of £160,000, the company said.

When you consider that family member; Joe Bamford owns Wrightbus, I would expect that you’ll see a development of these engines coming to a bus route near you!

Conclusion

I have made money backing developments based on the properties of fluid flow at the small end of gaseous flow.

There are some weird effects there, which are not taught in A-level physics.

Have JCB found how to apply them to create the ultimate zero-carbon power unit?

I’m certainly not ruling it out!

May 22, 2021 Posted by | Hydrogen | , , , | 5 Comments

Through Settle And Carlisle Service Under Consideration

The title of this post, is the same as that of an article in the June 2021 Edition of Modern Railways.

This is the first paragraph.

Plans for a new Leeds to Glasgow through service via the Settle and Carlisle line are being developed, with CrossCountry and the Department for Transport starting to look at the possible scheme.

It sounds like a sensible idea to me.

The article also suggests the following.

  • CrossCountry is a possible operator.
  • CrossCountry are keen to improve services between Leeds and Glasgow
  • The trains could be InterCity 125s, freed up, by a the arrival of Class 221 trains from Avanti West Coast, when they receive their new Class 805 trains.
  • Maintenance of the trains wouldn’t be a problem, as this could be done at Neville Hill in Leeds or Craigentinny in Edinburgh.
  • Services could start in December 2023.

I have a few thoughts of my own!

The Route

The route between Leeds and Carlisle is obvious, but there are two routes between Carlisle and Glasgow.

Trains would probably choose a route and call at stations to maximise passenger numbers.

These stations are on the various routes.

  • Settle and Carlisle – Shipley, Bingley, Keighley, Skipton, Gargrave, Hellifield, Long Preston, Settle, Horton in Ribblesdale, Ribblehead, Dent, Garsdale, Kirkby Stephen, Appleby, Langwathby, Lazonby & Kirkoswald and Armathwaite
  • Glasgow South Western – Dunlop, Stewarton, Kilmaurs, Kilmarnock, Auchinleck, New Cumnock, Kirkconnel, Sanquhar, Dumfries, Annan and Gretna Green
  • West Coast Main – Motherwell, Carstairs and Lockerbie

There are certainly a lot of possibilities.

 Upgrading The InterCity 125 Trains

CrossCountry appear to have enough InterCity 125 trains to muster five in a two Class 43  power car and seven Mark 3 coach formation.

They may not be fully in-line with the latest regulations and there may be a need for a certain degree of refurbishment.

These pictures show some details of a refurbished Great Western Railway Castle, which has been fitted with sliding doors.

Will The InterCity 125 Trains Be Shortened?

Scotrail’s Inter7City trains and Great Western Railway’s Castle trains have all been shortened to four or five coaches.

This picture shows a pair of Castles.

Journey Times, Timetable And Frequency

The current journey time between Leeds and Glasgow Central stations via the East Coast Main Line is four hours and eight minutes with nine stops.

The Modern Railways article says this about the current service.

The new service would be targeted at business and leisure travellers, with through journey times competitive with road and faster than the current direct CrossCountry Leeds to Glasgow services via the East Coast main line.

I would expect that CrossCountry are looking for a time of around four hours including the turn round.

  • Stops could be removed to achieve the timing.
  • The trains could run at 125 mph on the West Coast Main Line.

This could enable a train to have the following diagram.

  • 0800 – Depart Leeds
  • 1200 – Depart Glasgow Central
  • 1600 – Depart Leeds
  • 2000 – Depart Glasgow Central
  • Before 2400 – Arrive Leeds

Note.

  1. A second train could start in Glasgow and perform the mirrored timetable.
  2. Timings would probably be ideal for train catering.
  3. Trains would leave both termini at 0800, 1200, 1600 and 2000.
  4. The timetable would need just two trains.

I also think, if a second pair of trains were to be worked into the timetable, there could be one train every two hours on the route, if the demand was there.

I certainly believe there could be a timetable, that would meet the objectives of attracting business and leisure passengers away from the roads.

Tourism And Leisure Potential

The Settle and Carlisle Line is known as one of the most scenic railway lines in England, if not the whole of the UK.

There are important tourist sites all along the route between Leeds and Glasgow

Many of the stations are used by walkers and others interested in country pursuits.

I believe that it is a route that needs a quality rail service.

Travel Between London and Towns Along The Settle And Carlisle Line

In Thoughts On Digital Signalling On The East Coast Main Line, I said this.

I think it is highly likely that in the future, there will be at least one train per hour (tph) between London Kings Cross and Leeds, that does the trip in two hours.

It may seem fast compared to today, but I do believe it is possible.

With a timely connection at Leeds station, will this encourage passengers to places along the Settle and Carlisle line to use the train?

What About the Carbon Emissions?

The one problem with using InterCity 125 trains on this route, is that they are diesel-powered, using a pair of Class 43 locomotives.

But then there are over a hundred of these diesel-electric locomotives in service, nearly all of which are now powered by modern MTU diesel engines, which were fitted in the first decade of this century.

Consider.

  • The locomotives and the coaches they haul have an iconic status.
  • Great Western Railway and Scotrail have recently developed shorter versions of the trains for important routes.
  • There are over a hundred of the locomotives in service.
  • Companies like ULEMCo are developing technology to create diesel-powered vehicles that can run on diesel or hydrogen.
  • There is plenty of space in the back of the locomotives for extra equipment.
  • MTU have a very large number of diesel engines in service. It must be in the company’s interest to find an easy way to cut carbon emissions.
  • I believe that the modern MTU diesel engines could run on biodiesel to reduce their carbon footprint.

And we shouldn’t forget JCB’s technology, which I wrote about in JCB Finds Cheap Way To Run Digger Using Hydrogen.

If they could develop a 2 MW hydrogen engine, it could be a shoe-in.

I believe that for these and other reasons, a solution will be found to reduce the carbon emissions of these locomotives to acceptable levels.

Conclusion

In this quick look, it appears to me that a Glasgow and Leeds service using InterCity 125 trains could be a very good idea.

May 21, 2021 Posted by | Transport/Travel | , , , , , , , , , , , , , , , , , , , | 5 Comments

New Hydrogen Engine Design Unveiled To Overcome Reliance On Fuel Cells

The title of this post, is the same as that of this article on Hydrogen Fuel News.

The article describes an innovative hydrogen-powered engine developed  by an Israeli company called Aquarius Engines.

This is the sub-heading, that gives a little bit more information.

Aquarius Engines has developed a small 10kg emission-free unit operating entirely on H2.

It appears to be based on the company’s patented single-piston-linear-engine.

This page on the Aquarius web site describes the combustion technology in a short video.

Wikipedia also has an entry on the free-piston engine.

The power output of the Aquarius engine is not given.

Conclusion

I have a hunch, that Aquarius Engines might be on to something!

Light weight is so important in many applications.

 

May 21, 2021 Posted by | Hydrogen, Transport/Travel, World | , | 1 Comment

Gravitricity Adds Hydrogen To Energy Storage Mix

The title of this post, is the same as that of this press release on the Gravitricity web site.

These are the first two paragraphs of the press release.

Energy storage specialists Gravitricity have revealed plans to add hydrogen and heat storage to their underground gravity energy system.

The Edinburgh innovators have submitted a global patent to turn purpose-built shafts into pressurised energy stores, capable of safely accumulating significant quantities of the gas.

These are my observations.

  • I believe the original concept of storing energy will work, which is why I have invested.
  • Other companies are proposing to store hydrogen under pressure below ground.
  • Heat is being extracted from the London Underground and used for heating buildings.
  • Using one hole for three purposes must be more cost-efficient.

These processes might be easier with a regular clean purpose-built shaft!

May 20, 2021 Posted by | Energy Storage, Hydrogen | | Leave a comment

£3m Hackney Overground Station Upgrade To Begin In June

The title of this post, is the same as that of this article on the Hackney Gazette.

Selfishly, this is the improvement, that I’m waiting for.

I live to the West of Dalston Junction station on the 38 bus route. The second entrance will make getting to and from Stratford and the various attractions there much easier.

May 20, 2021 Posted by | Transport/Travel | , , , , | 1 Comment