The builders now seem to be on the home straight at Hackney Wick station.

The fitting out is well underway on the platforms and it appears that the ground level works are progressing.

Because of today’s weather, I didn’t really want to have a look at ground level.

Building A Station Without Closing The Railway Line

After the initial closure at Easter 2017, to install the subway, which I wrote about in A Tough Way To Spend Easter, I’m pretty certain, there has not been a major closure of the line and work to build the station has continued, whilst trains have continued to run on the railway and stop at the platforms for passengers.

I suspect that project managers have learned a lot from this project.

May 12, 2018 - Posted by | Travel | , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.