This document on the Network Rail web site is entitled Highlights Of The Great North Rail Project.

There is this section which is entitled We Build A Railway Station In Just Nine Months.

It’s about the building of Maghull North station.

This is said.

Network Rail undertook the scheme on behalf of Merseytravel, appointing contractor Buckingham Group.

How did we deliver the station so quickly and carry out most of the works while keeping the railway line open? A head start, line access and a tight summer deadline.

Robert Grey, a project manager of infrastructure projects at Network Rail, said: “Nine months is quite short for a station… The restricting factor is the access. We had quite a bit of flexibility there. We had access for long weekends and a 12-day possession of the line after Christmas… Without those we’d still be there now.”

I also put it down to the Liverpudlian attitude, which in my experience seems to accept disruption to their lives without complaining too much and then joke about it, when it’s all over.

I was in Liverpool during the bus strike of 1968. where Liverpudlians just walked.

Some of this attitude would be of great help in sorting the problem of the Steventon Bridge in Oxfordshire. I wrote about this bridge at the end of The Stone Arch Railway Bridges Of Scotland.

September 23, 2018 - Posted by | Travel | , , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.