Nervous Operators Force Network Rail To Defer King’s Cross Plan

The title of this post is the same as that of this article on Rail Magazine.

King’s Cross station has to be closed for three months, so that tracks, electrification and signalling can be replaced and modernised for about 1.5 miles from the buffer stops at the station.

The original dates of the closure were to have been between December 2019 and March 2020, but now it looks like it could be delayed by up to a year.

The article on the web site, is a shortened version of the article in the magazine, where this is said.

Closure dates have yet to be announced, and NR is still developing a passenger handling strategy which could include long-distance services at Finsbury Park or some services terminating at Peterborough. Some trains could even be rerouted into London Liverpool Street.

I wonder, if Network Rail’s planners are cursing that the around thirty miles between Peterborough and Ely is not electrified.

If it were electrified, it would allow electric trains as well as diesel and bi-mode trains to access Liverpool Street station via the West Anglia Main Line.

What Benefits Would There Be From Electrifying Peterborough To Ely?

I can imagine Oxford-educated civil servants in the Department of Transport and The Treasury dismissing calls for more electrification in the backwater of East Anglia, after the successful electrification to Norwich in the 1980s.

But now Cambridge is powering ahead and East Anglia is on the rise, with the massive Port of Felixstowe needing large numbers of freight trains to other parts of mainland UK.

This East Anglian success gives reasons for the electrification of the Peterborough-Ely Line.

Direct Electric Trains Between Peterborough And Cambridge

I have met Cambridge thinkers, who believe that Peterborough is the ideal place for businesses, who need to expand from Cambridge.

Peterborough has the space that Cambridge lacks.

But the transport links between the two cities are abysmal.

  • The A14 is only a two-lane dual-carriageway, although a motorway-standard section is being added around Huntingdon.
  • Peterborough station has been improved in recent years.
  • The direct train service is an hourly three-car diesel service between Birmingham and Stansted Airport, which doesn’t stop at the increasingly-important Cambridge North station.

The road will get better, but the rail service needs improvement.

  • There needs to be at least two direct trains per hour (tph) between Cambridge and Peterborough.
  • They would stop at Cambridge North, Waterbeach, Ely and March.
  • End-to-end timing would be under an hour.
  • Greater Anglia will have the four-car bi-mode Class 755 trains, which would be ideal for the route from next year.

If the Peterborough- Ely Line was electrified, Greater Anglia could use five-car Class 720 trains.

An Electric Diversion Route For The East Coast Main Line

The works at Kings Cross station, and the possible proposal to run some trains into Liverpool Street station, show that an electric diversion route would be useful, when there are closures or problems on the East Coast Main Line.

In the case of the Kings Cross closure, if Peterborough were to be used as the terminal for some trains from the North, then I suspect some high-capacity Class 800 trains could shuttle passengers to Liverpool Street.

If the date of the Kings Cross closure is 2020, then certain things may help.

  • Crossrail will be running.
  • Extra trains will be running from Finsbury Park to Moorgate.
  • Hull Trains will be running bi-mode Class 802 trains.
  • There could be more capacity on the West Anglia Main Line.
  • There could be more capacity and some longer platforms at Liverpool Street.

What would really help, is the proposed four-tracking of the West Anglia Main Line.

The latter could prove extremely useful, when Network Rail decide to bite the bullet and four-track the Digswell Viaduct.

Extending Greater Anglia’s Network

Greater Anglia have bought new bi-mode Class 755 trains.

This would appear to be more than enough to covering the current services, as they are replacing twenty-six trains with a total of fifty-eight coaches with thirty-eight trains with a total of one hundred and thirty-eight coaches.

That is 46 % more trains and 137 % more coaches.

The new trains are also genuine 100 mph trains on both electricity and diesel.

Obviously, Greater Anglia will be running extra services, but with the explosive growth around Cambridge, coupled with the new Cambridge North station, I feel they will be running extra services on the Peterborough to Cambridge route and perhaps further.

The new Werrington Grade Separation will make a difference.

  • It will open in a couple of years.
  • Trains between Peterborough and Lincoln won’t block the East Coast Main Line.
  • The Leicester route could also be improved.

So services to and from Lincoln and Leicester would probably be easier to run from Cambridge and Stansted Airport.

CrossCountry run a service between Birmingham New Street and Stansted Airport stations.

  • The service stops at Coleshill Parlway, Nuneaton, Leicester, Melton Mowbray, Oakham, Stamford, Peterborough, March, Ely and.Cambridge and Audley End stations.
  • The service doesn’t stop at Cambridge North station.
  • The service is run by an inadequate Class 170 train, which sometimes is only two coaches and totally full.
  • Trains take just over three hours ten minutes for the journey.

Will Greater Anglia take over this route? Or possibly run a second train as far as Leicester?

Their Class 755 trains with better performance and specification would offer the following.

  • Electric running between Ely and Stansted Airport stations.
  • Greater passenger capacity.
  • wi-fi, plugs and USB sockets.
  • A three hour journey both ways.
  • The extra performance would probably allow an extra important stop at Cambridge North station.

The new trains would certainly offer what passengers want.

CrossCountry run an extra train between Birmingham New Street and Leicester, so perhaps at the Western end, the Greater Anglia service need only go as far as Leicester.

At the Stansted end of the route, there will be an hourly train between Stansted Airport and Norwich, so there could be scope for perhaps cutting one the services back to Cambridge.

Obviously, time-tabling would sort it out to the benefit of the train operators and passengers, but I can envisage a set of services like this.

  • Norwich and Stansted Airport – Greater Anglia – 1 tph
  • Birmingham New Street and Stansted Airport – CrossCountry – 1 tph
  • Leicester and Cambridge – Greater Anglia – 1 tph
  • Colchester and Peterborough – 1 tph
  • Norwich and Nottingham (Currently Liverpool Lime Street) – 1 tph

Adding these up you get.

  • Stansted Airport and Cambridge – 2 tph – As now!
  • Stansted Airport and Cambridge North – 2 tph – New service!
  • Cambridge and Ely – 4 tph – At least!
  • Ely and Peterborough – 4 tph – At least!
  • Cambridge and Peterborough – 2 tph – Up from 1 tph
  • Stansted Airport and Peterbough – 1 tph – As now!
  • Cambridge and Leicester – 2 tph = Up from 1 tph.

This pattern or something like it would be much better for all.

If the Ely-Peterborough section of the were to be electrified then it would enable the following.

  • A reduced journey time for electric or bi-mode trains.
  • If required Greater Anglia could run an extra electric service using Class 720 trains between Stansted Airport and Peterbough.

I said earlier that the Werrington Grade Separation will make it easier to run services between Peterborough and Lincoln.

So why not add an hourly service between Cambridge and Lincoln?

I can envisage, when the West Anglia Main Line is four-tracked at the southern end, that there might be enough capacity for a Liverpool Street to Lincoln service via Cambridge, Cambridge North, Ely, Peterborough, Spalding and Sleaford.

But whatever happens Greater Anglia’s choice of bi-mode Class 755 trains, seems to give them the flexibility to match services to passengers needs.

Electro-Diesel and Battery-Electric Freight Locomotives

The Class 88 locomotive is an electro-diesel freight locomotive, that can use either power from overhead electrification or an pnboard diesel engine.

I believe that locomotives like this will become more common and that eventually, we’ll see a battery-electric heavy freight locomotive.

I wrote about the latter in Thoughts On A Battery/Electric Replacement For A Class 66 Locomotive.

The Peterborough-Ely Line will see increasing numbers of trains hauled by these powerful electric locomotives, with either diesel or battery power to propel them over the gaps in the electrification.

Electrifying the line would speed these hybrid trains through and increase the capacity of the route.

Conclusion

Network Rail have annoyed the train operators with their planning and timing of the upgrade at Kings Cross station.

It looks to me, that the part of the problem, is that there is no viable electrified secondary route to London.

Bi-mode trains can use the Peterborough-Ely Line to go to Liverpool Street via Cambridge.

This line is one of those routes that sits in a sea of electrification, which carries a lot of traffic, that would bring several benefits if it were to be electrified.

  • Direct electric trains between Cambridge and Peterborough, would greatly improve the spasmodic service between the two cities, with large economic benefits to the county.
  • An electric diversion route would be created from Peterborough to Liverpool Street via Ely and Cambridge.
  • It would allow Greater Anglia to develop routes West of Cambridge to places like Lincoln and Leicester using their future fleet of Class 755 trains.
  • It would also make it easier for battery-electric freight locomotives to cover the busy freight route between Felixstowe and Peterborough.

I also feel that it wouldn’t be the most difficult route to electrify.

The Fens are flat.

There is no history of mining.

The track is fairly straight and simple.

I suspect that it could become a high-quality 90-100 mph, electrified line.

 

 

 

 

 

 

 

With

 

 

December 8, 2018 - Posted by | Transport | , , , , , , , , , , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.