Nothing Seems To Be Happening At Syon Lane Station

I passed through Syon Lane station today and thought I’d have a look at the progress on the step-free access to the station.

This page on the South Western Railway web site describes in detail, the works that will be done.

This is the first paragraph.

From the beginning of April, we’ll be building a new accessible footbridge with a lift at Syon Lane. The project is expected to be completed later this year and is mainly funded by Hounslow Council. Making the station step free will be a real positive for people with limited mobility traveling round the Hounslow Loop, however the delivery of the new bridge will affect the station and the platforms. The station will remain operational throughout the works, but there will be some access changes during the project delivery:

Consider  the bit about being finished later this year, then look at these pictures.

It looks like they’ve all packed up and gone home.

Surely, if the bridge is going to be finished this year, workmen should be hard at work building foundations and putting up towers for lifts.

But even the tea-hut has gone.

It appears that the following has been done at the station.

  • Create a level step-free route from Syon Lane to the London-bound platform.
  • Move the ticket machines and the card readers.
  • Run temporary cable ducts, along the back of the platforms.
  • Clear some ground behind the fence, where the lift towers might be placed.
  • The long platforms have been narrowed, which Network Rail say is to give space for the work.

The 3D Google Map shows the station.

I don’t know when the picture was taken, but it does look that there could have been some ground clearing about halfway along the platform.

What Do I Think Is Happening?

I think, there could be these reasons for the lack of action.

  • The project has been delayed for some reason.
  • Something very different is happening at Syon Lane station!

Speaking to a couple of travellers  at the station today, they had heard nothing and one was looking forward to the bridge.

I have no evidence, but I do have a devious and sometimes theatrical mind.

Are Network Rail conducting an experiment on the good people, who use Syon Lane station?

They have only said this about disruption to passengers.

The station will remain operational throughout the works, but there will be some access changes during the project delivery:

Could Network Rail be bringing in the bridge in a few sections and just lifting them in with a crane?

Look at the 3D Google Map above and note that the station in surrounded by houses and lots of leafy trees, which would make getting bridge sections and the crane into place difficult.

But look at the cross-section of the average footbridge tower or bridge and it is about the same as that of a train.

For this reason, I believe that the bridge components will be brought in on a special train with a large crane.

In Winner Announced In The Network Rail Footbridge Design Ideas Competition, I wrote how the competition was won by this bridge.

It is composed of the following major components.

  • Two towers with lifts.
  • Two sets of stairs
  • A bridge deck.

All components would be built in a factory.

  • They would be fully tested before delivery.
  • The components would be delivered by train.
  • The bridge would then be assembled using a rail mounted crane.

After testing, the Mayor could declare the bridge open

I suspect too, that the only preparation prior to the assembly of the bridge, is to have firm concrete bases for the bridge and a power supply for the lifts.

  • The construction of the bases could be done from the railway, so there would be no problems of bringing in the concrete.
  • The power supply might not even be needed, if the bridge had solar panels on the roof and a clear battery system.
  • It’s all a bit like giant Lego construction, but then the architect of the bridge was Danish!

Could  commuters on a Friday night return to a station little different to the one they’ve known for years and then on Monday morning  find a working step-free bridge has been erected?

Engineering is the sconce of the possible, whereas politics is dreams of the impossible!

Is This The Future Of Step-Free Bridges?

Obviously not all, but I believe that up to a third of all stations that need a step-free bridge can use a bridge of this type.

But the station upgrade to step-free application is just one of several.

  • New stations.
  • Step-free bridges over busy roads, rivers or canals.
  • Replacement of dangerous light-controlled road crossings.

The design could also be incorporated into other buildings.

Conclusion

Something different could be happening at Syon Lane station.

June 11, 2019 - Posted by | Transport | , , , , ,

1 Comment »

  1. […] Nothing Seems To Be Happening At Syon Lane Station, I speculated that either the project to erect a step-free bridge at the station, was to be delayed […]

    Pingback by Why Are Replacement Buses Being Used To Syon Lane Station On July 20-21? « The Anonymous Widower | June 16, 2019 | Reply


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: