Seaway7 Installs Final Foundation At Seagreen Offshore Wind Farm
The title of this post, is the same as that of this article on offshoreWIND.biz.
This is the sub-heading.
Seaway7 has installed the final wind turbine foundation on Seagreen Offshore Wind Farm, off the coast of Angus, Scotland, concluding the 18-month installation campaign.
Note.
- As 114 foundations have been installed in eighteen months or just over six installations in a month.
- According to Deepest Ever Fixed-Bottom Wind Turbine Foundation Stands Offshore Scotland, each foundation weighs two thousand tonnes.
- Some are also the deepest ever turbine foundations with a depth or is that height of nearly sixty metres.
- The Seagreen web site, says that phase 1 will be complete in the second quarter of this year.
- The first phase will generate 1075 MW.
We should raise a few cheers for the companies involved.