Save Loch Ness Campaigners Fear Highland Council Hydro Decision Will Pave Way For Further Approvals
The title of this post, is the same as this article from the Press & Journal.
This is the sub-heading.
Campaigners have hit out after councillors decided to raise no objection to plans, but only by the narrowest of margins
These three paragraphs add some more detail.
A community group has been left “disappointed” after Highland councillors decided to raise no objection to a proposed new hydro scheme at Loch Ness.
The Save Loch Ness group has been campaigning against what it brands the “industrialisation” of the loch, including the proposal for the Glen Earrach Pumped Storage Hydro (PSH) scheme.
Yesterday, as a consultee on the project which will ultimately be decided by Scottish ministers, Highland Council’s south planning committee decided to raise no objection to the plans – but only on the casting vote of chairman Paul Oldham.
I can sympathise with the community group, but I believe that the Glen Earrach scheme can be incorporated sympathetically into Loch Ness.
- The Glen Earrach scheme will be a 2 GW/34 GWh pumped storage hydro scheme, which could be the largest in the UK. So it is important.
- The Glen Earrach scheme will contribute to a Community Wealth Fund, which is expected to deliver over £20 million a year over the operational lifetime of the project.
- The economics are favourable because the large height difference between the upper reservoir, at nearly 500 m above sea level, and Loch Ness
- It could create up to a thousand construction jobs.
- There appear to be no current plans for a visitor centre.
- Once operational, the majority of the project’s infrastructure will be located underground.
- The project is expected to be complete in 2031.
- It is likely to last 125 years. I don’t think this is surprising, given that Invergarry hydro power station has just celebrated seventy years of operation, which I wrote about in 70 Years Of Clean, Renewable Power From Invergarry Power Station.
- There were objections to the Coire Glas pumped storage hydro scheme, at the other end of the Great Glen.
- The cost of the scheme appears to be around £3 billion.
Whether this scheme is approved will be a close run thing.
But it will be needed to help back-up all of Scotland’s offshore wind power, which currently stands at 5.7 GW and could reach 40 GW by 2040, according to Gooogle AI and Wikipedia.