Barking Riverside Extension – 24th June 2019

I took these pictures, where the arking Riverside Extension will turn off to the East of Renwick Road bridge.

It looks like the piles are going in and there is a lot of catenary renewal.

I think that this project could be on time.

June 25, 2019 Posted by | Transport | , | Leave a comment

Engineering Work Closures Between Barnes And Feltham In June And July

There is more up-to-date information on this page on South Western Railway’s web site, which is entitled Engineering Works.

These are what I found.

Saturday 20 July and Sunday 21 July

Buses replace trains between Barnes and Feltham via Hounslow Saturday 20 and Sunday 21 July

Saturday 27 July and Sunday 28 July

Buses replace trains between Barnes and Feltham via Hounslow Saturday 27 and Sunday 28 July

Sunday 11 August

Buses replace trains between Barnes and Feltham via Hounslow Sunday 11 August

Sunday 18 August

Altered train services and replacement buses in the Feltham area Sunday 18 August

Sunday 25 August

Altered train services and replacement buses in the Feltham area Sunday 25 August

Thoughts On Works In The Area

My thoughts on the two projects follow.

Syon Lane Footbridge

When I wrote Why Are Replacement Buses Being Used To Syon Lane Station On July 20-21?, I didn’t find the two later closures through Syon Lane station.

I was checking the on-line timetable and it appears that the closure is not total on the days mentioned, in the current timetable.

It looks to me that Network Rail and South Western Railway are playing this in a safety first manner, as few people are going to complain, if a closure doesn’t happen and a shiny new step-free bridge has appeared and is almost ready for use.

Bedfont Lane Level Crossing Removal At Feltham Station

In The Removal Of Bedfont Lane Level Crossing, I gave a schedule of the works and it appears nothing much is slated to be done until later in the year.

I need more information about why there are closures in the Feltham area.

I did find this image of the proposed pedestrian and cycling bridge.

It certainly looks very traditional with long ramps.

This picture shows the progress on the 25th June 2019

Note the platform extensions and the pillar on the far side to support the bridge.

I’m not sure, if the ramps in the picture are part of an older bridge or new!

Conclusion

It’s all happening in Hounslow.

 

June 25, 2019 Posted by | Transport | , , , , | 1 Comment

The New Entrance To Moorgate Station

The new entrance to Moorgate station, is now more visible behind the hoardings.

But there still appears to be a lot to do!

June 25, 2019 Posted by | Transport | , | Leave a comment