Example Cost And Timescale For A Step-Free Footbridge

This article on Network Rail’s web site is entitled Investment In West Calder Gives Station Accessibility A Lift.

The project replaced an existing bridge.

  • It cost £2.7 million.
  • It took ten months to build and commission.
  • Station access was maintained at all times.

It looks to have been a well-managed project.

This picture shows the bridge.

How would it compare with the recent winner of Network Rail’s competition to find a new footbridge design?

Having not seen either bridge in the metal, I’ll give my judgement when I have.

May 1, 2019 - Posted by | Transport/Travel | , , , , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: