Example Cost And Timescale For A Step-Free Footbridge
This article on Network Rail’s web site is entitled Investment In West Calder Gives Station Accessibility A Lift.
The project replaced an existing bridge.
- It cost £2.7 million.
- It took ten months to build and commission.
- Station access was maintained at all times.
It looks to have been a well-managed project.
This picture shows the bridge.
How would it compare with the recent winner of Network Rail’s competition to find a new footbridge design?
Having not seen either bridge in the metal, I’ll give my judgement when I have.