The title of this post, is the same as that of this article on the BBC.

This is the first four paragraphs.

A test train has travelled along part of a new Northumberland line ahead of the reintroduction of passenger services.

Six new stations are to be built and 18 miles (29km) of track upgraded between Newcastle and Morpeth.

The test train contained dignitaries and rail officials, with full services expected to start in 2024.

Northern said it was looking at running two trains an hour six days a week and hourly services on Sundays.

It very much sounds to be a good start.

The article certainly has a good picture of one of the bridges on the line.

Morpeth?

Note that the article says that the first phase goes to Morpeth. I had thought it was going to Ashington.

Or could it be that Network Rail want to open up Newcastle and Morpeth to take some local services off the East Coast Main Line.

August 13, 2021 Posted by | Transport/Travel | , , | 2 Comments

Middlesbrough To London LNER Trains To Run From 13 December

The title of this post, is the same as that of this article on the BBC.

The title is clear and these paragraphs give details of the train service.

The daily weekday service in each direction will also connect nearby Thornaby with London King’s Cross.

The services will depart Middlesbrough at 07:08 and Thornaby at 07:15, arriving at King’s Cross at 10:22.

Northbound from London will leave at 15:25, stopping at York, to Thornaby at 18:08 and Middlesbrough at 18:18.

This is obviously not a complete service.

  • It will be impossible to use direct trains to spend a day on Teesside from London, as I have done many times over the years, usually with a change at Darlington station.
  • It needs to run seven days a week.

But as the article says, more work needs to be done at Middlesbrough to turn the trains.

Currently, LNER run one train per two hours (1tp2h) to York, which alternates with a service to Lincoln at the same frequency.

LNER have said, that the Middlesbrough service will be an extension of the York service.

  • As York trains can be nine-car trains, this could explain the need for works at Middlesbrough station.
  • As York and Middlesbrough are 51 miles and an hour apart, it looks to me, that once Middlesbrough station has been updated, LNER can extend services to Middlesbrough according to passenger demand.

I suspect that eventually, the London and Middlesbrough service will have a similar frequency as the Harrogate and Lincoln services of five trains per day (tpd).

What Real Time Trains Says About The Service

Although it’s exactly four months before the service starts, it has already been entered into Real Time Trains.

The following information is given about the services.

  • One seven-minute stop at York going South and a five-minute stop going North.
  • Changeover between diesel and electric at Longlands junction, where the Teesside trains leave and join the East Coast Main Line.
  • Services do not appear to pass through Northallerton station.

Train times are as given by the BBC.

Splitting And Joining At Newark

I think it would be possible to combine the Lincoln, Middlesbrough and York services into one service.

  • A pair of five-car Azumas would run between Kings Cross and Newark North Gate, with stops at Stevenage, Peterborough and Grantham.
  • They would split at Newark North Gate station.
  • The front train would continue Northwards to Middlesbrough, with stops at Retford, Doncaster, York and Thornaby.
  • The rear train would continue Eastwards to Lincoln, with a possible extension to Grimsby Town and Cleethorpes.

Returning South the trains would join at Newark North Gate.

Note.

  1. As TransPennine Express services to and from Middlesbrough, call at Northallerton, LNER services could do the same.
  2. As with splitting and joining at Newark, only a five-car train runs to and from Middlesbrough, this could be used before the new platform at Middlesbrough is constructed.
  3. if this service ran at a frequency of 1tp2h, there would be space in the timetable for a new 1tp2h service to perhaps Newcastle and Edinburgh.

There are a lot of possibilities.

Battery-Electric Trains Between London And Middlesbrough

Only the twenty miles between Northallerton and Middlesbrough on the route are without electrification.

Hitachi have announced the Hitachi Intercity Tri-Mode Battery Train, which is described in this Hitachi infographic.

I believe that a version of this train could be given sufficient battery range to be able to achieve a round trip to Middlesbrough station from the electrification of the East Coast Main Line, without any need for charging at Middlesbrough.

It could be one of the first InterCity services in the world, run by battery-electric trains.

August 13, 2021 Posted by | Transport/Travel | , , , , , | 5 Comments